São Paulo Aricanduva Bus Rapid Transit Corridor

Abstract*

The Project will finance: (i) development of 14km BRT Aricanduva Corridor; (ii) upgrading of the São Paulo city bus operational control center; and (iii) institutional strengthening activities related to public transport planning and policies.

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objectives are to improve mobility and accessibility to jobs for socially vulnerable public transport users in the influence area of the Aricanduva Corridor and enhance operational efficiency of the São Paulo city bus system.

Key Details

Project Details

  • P169140

  • Active

  • Ana Waksberg Guerrini

  • Municipality of São Paulo

  • Brazil

  • June 28, 2019

  • (as of board presentation)

    April 22, 2020

  • April 28, 2022

  • US$ 121.25 million

  • São Paulo Municipal Secretariat of Mobility and Transport,São Paulo Municipal Secretariat of Urban Infrastructure and Works

  • Latin America and Caribbean

  • 2020

  • US$ 97.00 million

  • N/A

  • April 9, 2024

  • June 30, 2026

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 97.00
Borrower/Recipient 24.25

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 97.00
IDA Commitment N/A
IBRD + IDA Commitment 97.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 121.25

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Apr 22, 2020 IBRD-90810 Loan Commitment 97,000,000.00
Oct 26, 2023 IBRD-90810 Loan Disb 4,117,947.00
Nov 15, 2023 IBRD-90810 Int Charges 121,682.48
May 15, 2024 IBRD-90810 Int Charges 140,097.50
May 15, 2024 IBRD-90810 Int Charges 13,848.71
May 15, 2023 IBRD-90810 Int Charges 120,253.43
May 15, 2024 IBRD-90810 Int Charges 564.10
Jun 13, 2024 IBRD-90810 Loan Disb 8,980,304.00
Jun 27, 2022 IBRD-90810 Fee Charges 242,500.00
Nov 15, 2022 IBRD-90810 Int Charges 49,828.77
Nov 15, 2022 IBRD-90810 Int Charges 122,246.58
May 15, 2024 IBRD-90810 Int Charges 115,549.82

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2024-10-17
Project Management Moderately Satisfactory 2024-10-17
Financial Management Moderately Satisfactory 2024-10-17
Monitoring and Evaluation Satisfactory 2024-10-17
Overall Implementation Progress (IP) Moderately Satisfactory 2024-10-17
Procurement Moderately Satisfactory 2024-10-17

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT:
Outcomes
Risk to Development Outcome
Bank Performance
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of formal job opportunities reachable by public transport from the area of influence of the Aricanduva BRT Corridor within a90-minute one-way commuteValue2000000.002000000.000.00
    DateJanuary 1, 2020September 22, 2021
    Comment
  • On-time departures of São Paulo city busesValue67.0071.630.00
    DateJanuary 1, 2020June 30, 2022
    Comment
  • Daily bus passenger ridership on the Aricanduva BRT CorridorValue255000.00211000.000.00
    DateNovember 1, 2019June 30, 2022
    Comment
  • Scheduled São Paulo city bus trips that are not completedValue6.004.430.00
    DateDecember 1, 2019June 30, 2022
    Comment
  • Change in female bus ridership on Aricanduva BRT CorridorValue0.000.000.00
    Date
    Comment
  • Change in male bus ridership on Aricanduva BRT CorridorValue0.000.000.00
    Date
    Comment
  • Change in bus ridership of socially vulnerable users on Aricanduva BRT CorridorValue0.000.000.00
    Date
    Comment
  • Change in bus ridership of non-socially vulnerable users on Aricanduva BRT CorridorValue0.000.000.00
    Date
    Comment
  • Change in satisfaction score of socially vulnerable bus users in the area of influence of Aricanduva BRT CorridorValue0.000.000.00
    DateDecember 1, 2019September 22, 2021
    Comment
  • Change in satisfaction score of female bus users on security along Aricanduva BRT corridorValue0.000.000.00
    DateDecember 1, 2019September 22, 2021
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Commercial speed for bus vehicles along the Aricanduva BRT corridor (km/h)Value18 km/h18.66 km/h
    DateJanuary 1, 2020June 30, 2022
    Comment
  • Percentage of bus routes monitored in real time by the Operational Control Center for São Paulo city busesValue3.003.000.00
    DateDecember 31, 2019September 22, 2021
    Comment
  • BRT lanes built on Aricanduva CorridorValue0.000.000.00
    DateAugust 1, 2019September 22, 2021
    Comment
  • Upgraded Operational Control Center for São Paulo city buses is in commissionValueNoNo
    DateAugust 1, 2019September 22, 2021
    Comment
  • Roads rehablitatedValue0.000.000.00
    DateSeptember 30, 2019September 22, 2021
    Comment
  • Percentage of bus trip performance indicators under the new concession contracts of São Paulo city buses monitored by the Operational Control CenterValue0.000.000.00
    DateDecember 2, 2019September 22, 2021
    Comment
  • Roads rehabilitated - ruralValue0.000.000.00
    Date
    Comment
  • Roads rehabilitated - non-ruralValue0.000.000.00
    Date
    Comment
  • BRT stations constructed along Aricanduva CorridorValue0.000.000.00
    DateDecember 2, 2019September 22, 2021
    Comment
  • Universal access facilities at BRT stations along Aricanduva CorridorValue0.000.000.00
    DateAugust 1, 2019September 22, 2021
    Comment
  • Security cameras installed at BRT stations along Aricanduva CorridorValue0.000.000.00
    DateSeptember 30, 2019September 22, 2021
    Comment
  • Sidewalks rehabilitated on Aricanduva CorridorValue0.000.000.00
    DateDecember 2, 2019September 22, 2021
    Comment
  • Segregated bicycle lane built on Aricanduva CorridorValue0.000.000.00
    DateAugust 1, 2019September 22, 2021
    Comment
  • Intelligent traffic lights installed along Aricanduva CorridorValue0.000.000.00
    DateSeptember 30, 2019September 22, 2021
    Comment
  • Public lights installed for pedestrians and bicycle users along Aricanduva CorridorValue0.000.000.00
    DateDecember 3, 2019September 22, 2021
    Comment
  • Change in CO2 emissions of public transport vehicles as a result of implementation of Aricanduva BRTValue0 tonnes of CO2 per year0 tonnes of CO2 per year
    DateSeptember 29, 2019September 22, 2021
    Comment
  • Road Safety Assessments considered in final designsValueNoNo
    DateAugust 1, 2019September 22, 2021
    Comment
  • Sexual harassment response protocol for São Paulo city buses implementedValueNoNo
    DateSeptember 27, 2019September 22, 2021
    Comment
  • Workers that have signed the code of conduct and attended the code of conduct training for the Aricanduva BRT worksValue0.000.000.00
    DateSeptember 30, 2019September 22, 2021
    Comment
  • Grievances responded within the stipulated service standards for response timesValue0.000.000.00
    DateDecember 2, 2019September 22, 2021
    Comment