Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 97.00 |
Borrower/Recipient | 24.25 |
P169140
Active
Ana Waksberg Guerrini
Municipality of São Paulo
June 28, 2019
(as of board presentation)
April 22, 2020
April 28, 2022
US$ 121.25 million
São Paulo Municipal Secretariat of Mobility and Transport,São Paulo Municipal Secretariat of Urban Infrastructure and Works
2020
US$ 97.00 million
N/A
April 9, 2024
June 30, 2026
No
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 97.00 |
Borrower/Recipient | 24.25 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 97.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 97.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 121.25 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Apr 22, 2020 | IBRD-90810 | Loan Commitment | 97,000,000.00 |
Oct 26, 2023 | IBRD-90810 | Loan Disb | 4,117,947.00 |
Nov 15, 2023 | IBRD-90810 | Int Charges | 121,682.48 |
May 15, 2024 | IBRD-90810 | Int Charges | 140,097.50 |
May 15, 2024 | IBRD-90810 | Int Charges | 13,848.71 |
May 15, 2023 | IBRD-90810 | Int Charges | 120,253.43 |
May 15, 2024 | IBRD-90810 | Int Charges | 564.10 |
Jun 13, 2024 | IBRD-90810 | Loan Disb | 8,980,304.00 |
Jun 27, 2022 | IBRD-90810 | Fee Charges | 242,500.00 |
Nov 15, 2022 | IBRD-90810 | Int Charges | 49,828.77 |
Nov 15, 2022 | IBRD-90810 | Int Charges | 122,246.58 |
May 15, 2024 | IBRD-90810 | Int Charges | 115,549.82 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2024-10-17 |
Project Management | Moderately Satisfactory | 2024-10-17 |
Financial Management | Moderately Satisfactory | 2024-10-17 |
Monitoring and Evaluation | Satisfactory | 2024-10-17 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-10-17 |
Procurement | Moderately Satisfactory | 2024-10-17 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: |
---|---|
Outcomes | |
Risk to Development Outcome | |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of formal job opportunities reachable by public transport from the area of influence of the Aricanduva BRT Corridor within a90-minute one-way commute | Value | 2000000.00 | 2000000.00 | 0.00 |
Date | January 1, 2020 | September 22, 2021 | ||
Comment |
On-time departures of São Paulo city buses | Value | 67.00 | 71.63 | 0.00 |
Date | January 1, 2020 | June 30, 2022 | ||
Comment |
Daily bus passenger ridership on the Aricanduva BRT Corridor | Value | 255000.00 | 211000.00 | 0.00 |
Date | November 1, 2019 | June 30, 2022 | ||
Comment |
Scheduled São Paulo city bus trips that are not completed | Value | 6.00 | 4.43 | 0.00 |
Date | December 1, 2019 | June 30, 2022 | ||
Comment |
Change in female bus ridership on Aricanduva BRT Corridor | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Change in male bus ridership on Aricanduva BRT Corridor | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Change in bus ridership of socially vulnerable users on Aricanduva BRT Corridor | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Change in bus ridership of non-socially vulnerable users on Aricanduva BRT Corridor | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Change in satisfaction score of socially vulnerable bus users in the area of influence of Aricanduva BRT Corridor | Value | 0.00 | 0.00 | 0.00 |
Date | December 1, 2019 | September 22, 2021 | ||
Comment |
Change in satisfaction score of female bus users on security along Aricanduva BRT corridor | Value | 0.00 | 0.00 | 0.00 |
Date | December 1, 2019 | September 22, 2021 | ||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Commercial speed for bus vehicles along the Aricanduva BRT corridor (km/h) | Value | 18 km/h | 18.66 km/h | |
Date | January 1, 2020 | June 30, 2022 | ||
Comment |
Percentage of bus routes monitored in real time by the Operational Control Center for São Paulo city buses | Value | 3.00 | 3.00 | 0.00 |
Date | December 31, 2019 | September 22, 2021 | ||
Comment |
BRT lanes built on Aricanduva Corridor | Value | 0.00 | 0.00 | 0.00 |
Date | August 1, 2019 | September 22, 2021 | ||
Comment |
Upgraded Operational Control Center for São Paulo city buses is in commission | Value | No | No | |
Date | August 1, 2019 | September 22, 2021 | ||
Comment |
Roads rehablitated | Value | 0.00 | 0.00 | 0.00 |
Date | September 30, 2019 | September 22, 2021 | ||
Comment |
Percentage of bus trip performance indicators under the new concession contracts of São Paulo city buses monitored by the Operational Control Center | Value | 0.00 | 0.00 | 0.00 |
Date | December 2, 2019 | September 22, 2021 | ||
Comment |
Roads rehabilitated - rural | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Roads rehabilitated - non-rural | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
BRT stations constructed along Aricanduva Corridor | Value | 0.00 | 0.00 | 0.00 |
Date | December 2, 2019 | September 22, 2021 | ||
Comment |
Universal access facilities at BRT stations along Aricanduva Corridor | Value | 0.00 | 0.00 | 0.00 |
Date | August 1, 2019 | September 22, 2021 | ||
Comment |
Security cameras installed at BRT stations along Aricanduva Corridor | Value | 0.00 | 0.00 | 0.00 |
Date | September 30, 2019 | September 22, 2021 | ||
Comment |
Sidewalks rehabilitated on Aricanduva Corridor | Value | 0.00 | 0.00 | 0.00 |
Date | December 2, 2019 | September 22, 2021 | ||
Comment |
Segregated bicycle lane built on Aricanduva Corridor | Value | 0.00 | 0.00 | 0.00 |
Date | August 1, 2019 | September 22, 2021 | ||
Comment |
Intelligent traffic lights installed along Aricanduva Corridor | Value | 0.00 | 0.00 | 0.00 |
Date | September 30, 2019 | September 22, 2021 | ||
Comment |
Public lights installed for pedestrians and bicycle users along Aricanduva Corridor | Value | 0.00 | 0.00 | 0.00 |
Date | December 3, 2019 | September 22, 2021 | ||
Comment |
Change in CO2 emissions of public transport vehicles as a result of implementation of Aricanduva BRT | Value | 0 tonnes of CO2 per year | 0 tonnes of CO2 per year | |
Date | September 29, 2019 | September 22, 2021 | ||
Comment |
Road Safety Assessments considered in final designs | Value | No | No | |
Date | August 1, 2019 | September 22, 2021 | ||
Comment |
Sexual harassment response protocol for São Paulo city buses implemented | Value | No | No | |
Date | September 27, 2019 | September 22, 2021 | ||
Comment |
Workers that have signed the code of conduct and attended the code of conduct training for the Aricanduva BRT works | Value | 0.00 | 0.00 | 0.00 |
Date | September 30, 2019 | September 22, 2021 | ||
Comment |
Grievances responded within the stipulated service standards for response times | Value | 0.00 | 0.00 | 0.00 |
Date | December 2, 2019 | September 22, 2021 | ||
Comment |