Fostering and Leveraging Opportunities for Water Security Program

Abstract*

The development objective of the Fostering and Leveraging Opportunities for Water Security (FLOWS) Program Project for Kosovo is to: (i) strengthen national capacity for managing water security, and (ii) improve water security in Morava e Binces basin. The project comprises of three components. The first component, foundational measures for water security will build the foundations for water security in the country, thereby increasing targeted communities’...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The proposed project development objective is to: (i) strengthen national capacity for managing water security, and (ii) improve water security in Morava e Binces basin.

Key Details

Project Details

  • P169150

  • Active

  • Ahmed Abdelghany

  • Ministry of Finance, Labor and Transfers

  • Kosovo

  • May 17, 2019

  • (as of board presentation)

    June 9, 2020

  • March 1, 2022

  • US$ 28.49 million

  • Ministry of Environment, Spatial Planning and Infrastructure

  • Europe and Central Asia

  • 2020

  • US$ 29.58 million

  • N/A

  • March 18, 2024

  • November 30, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 27.40
Trust Funds 1.09
EC: European Commission 1.09

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 27.40
IBRD + IDA Commitment 27.40
Lending Instrument
Grant Amount 2.18
Total Project Cost** 28.49

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 9, 2020 IDA-66360 Loan Commitment 27,400,000.00
Aug 6, 2024 IDA-66360 Loan Disb 247,301.56
May 15, 2024 IDA-66360 Int Charges 1,201.07
May 15, 2024 IDA-66360 Int Charges 2,001.80
May 15, 2024 IDA-66360 Int Charges 2,001.80
Jul 23, 2024 IDA-66360 Loan Disb 229,422.56
Nov 15, 2023 IDA-66360 Int Charges 412.66
Nov 15, 2023 IDA-66360 Int Charges 687.80
Nov 15, 2023 IDA-66360 Int Charges 687.80
Jan 23, 2024 IDA-66360 Loan Disb 492,706.50
Jun 21, 2023 IDA-66360 Loan Disb 230,377.88

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2024-11-28
Overall Implementation Progress (IP) Moderately Unsatisfactory 2024-11-28
Procurement Moderately Unsatisfactory 2024-11-28
Progress towards achievement of PDO Moderately Satisfactory 2024-11-28
Financial Management Satisfactory 2024-11-28
Monitoring and Evaluation Satisfactory 2024-11-28

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • National Water Resources Investment Preparation Study developed including climate change analysis, and presented for endorsement tothe government.ValueNoNoYes
    DateJanuary 1, 2020March 18, 2024November 30, 2025
    Comment
  • Percentage of Hidromorava RWC customers with at least 18 hours of water supplyValue75.0075.0095.00
    DateJanuary 1, 2020March 18, 2024November 30, 2025
    Comment
  • Number of new and refurbished stations with data for near real-time hydro-met, climate, and spatial planning made publicly availableValue0.0022.0020.00
    DateJanuary 1, 2020March 18, 2024November 30, 2025
    Comment
  • Number of people downstream of high hazard dams with access to relevant early warning systemsValue0.000.0025000.00
    DateJanuary 1, 2020March 18, 2024November 30, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Civil society initiatives financed with small grants for water security and implementedValue0.000.0020.00
    DateJanuary 1, 2020March 18, 2024November 30, 2025
    Comment
  • Number of annual monitoring resports after putting dam safety procedures in placeValue0.000.003.00
    DateJanuary 1, 2020March 18, 2024November 30, 2025
    Comment
  • Number of detailed design for FLOWS2 investments completedValue0.000.002.00
    DateJanuary 1, 2020March 18, 2024November 30, 2025
    Comment
  • Number of young professionals trainedValue0.000.0035.00
    DateJanuary 1, 2020March 18, 2024November 30, 2025
    Comment
  • Structured stakeholder engagement for investment planning introduced and formal meetings held (Number)Value0.000.0010.00
    DateJanuary 1, 2020March 18, 2024November 30, 2025
    Comment
  • Annual hydrology reports reporting on water quality trends, groundwater, surface water and storage use for Morava e Binces basinValue0.0004.00
    DateJanuary 1, 2020March 18, 2024November 30, 2025
    Comment
  • Non Revenue Water (%)Value62.0062.0045.00
    DateJanuary 1, 2020March 18, 2024November 30, 2025
    Comment
  • Of which provided to (predominantly) female beneficiaries, at leastValue0.000.000.00
    Date
    Comment
  • Of which femaleValue0.000.000.00
    Date
    Comment
  • For specific women focus groups on investment prioritiesValue0.000.003.00
    DateMarch 2, 2020March 18, 2024December 31, 2025
    Comment
  • Gender action plan developed and approved by the board of directorsValue0.000.001.00
    DateMarch 2, 2020March 18, 2024December 31, 2025
    Comment
  • Increased awareness among basin inhabitants on water security and conservationValue0.000.0010.00
    DateJanuary 1, 2020March 18, 2024November 30, 2025
    Comment
  • Water Resources Investment Preparation Study prepared and discussed with stakeholdersValueNoNoYes
    DateMarch 2, 2020March 18, 2024December 31, 2025
    Comment
  • Percentage beneficiaries who report that citizen engagement processes are effectiveValue0.000.0015.00
    DateMarch 2, 2020March 18, 2024December 31, 2025
    Comment
  • Number of citizens participated in the Morava e Binces river basin management platformValue0.000.00500.00
    DateMarch 2, 2020March 18, 2024December 31, 2025
    Comment
  • Of which femaleValue15.0015.000.00
    Date
    Comment
  • Number of new and refurbished stations operationalValue0.0022.0020.00
    DateJanuary 1, 2020March 18, 2024November 30, 2025
    Comment
  • Km of water supply pipeline replaced/constructed under the projectValue0.000.0018.00
    DateJanuary 1, 2020March 18, 2024November 30, 2025
    Comment