Indonesia Sustainable Least-cost Electrification Technical Assistance (ISLE TA)

Development Objective

The Project Development Objective is to support the Recipient in endorsing a framework approach to electrify the Indonesian Eastern Islands in a sustainable and affordable manner, and in preparing the investments needed to implement the approach in identified Pilot Islands.

Key Details

Project Details

  • P169259

  • Active

  • Sabine Cornieti , Puguh Imanto, Muchsin Qadir

  • PT PLN (Persero)

  • Indonesia

  • January 21, 2019

  • (as of board presentation)

    July 8, 2021

  • January 31, 2023

  • US$ 2.15 million

  • PT PLN (Persero)

  • East Asia and Pacific

  • 2022

  • US$ 3.40 million

  • N/A

  • High

  • June 30, 2027

  • Yes

  • BANK APPROVED

  • November 27, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Energy Sector Management Assistance Program 2.45
Clean Technology Fund 0.95

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 3.40
Total Project Cost** 2.15

Summary Status of World Bank Financing (US$ Millions) as of July 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of July 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2024-09-26
Overall Implementation Progress (IP) Satisfactory 2024-09-26

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Solar power plant and/or BESS projects ready for investments in Nusa Tenggara and Maluku regions (feasibility study and environmental and social instruments completed for four projects)Value0.000.004.00
    DateJuly 1, 2019May 30, 2022January 30, 2025
    Comment
  • New energy generation and transmission planning tool in place (contract signed with software license provider)ValueNoYesYes
    DateJuly 1, 2019June 5, 2023June 5, 2023
    Comment
  • Adequate capacity within PLN to implement its new ESMSValue0.000.004.00
    DateJanuary 31, 2023June 6, 2023April 30, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • PLN staff from the E&S team trained to implement the ESMS (2 technical workshops on E&S held)Value0.000.002.00
    DateJanuary 30, 2023June 6, 2023December 30, 2024
    Comment
  • New climate resilient infrastructure guidelines endorsed (Yes/No – endorsement letter received from PLN)ValueNoNoYes
    DateJuly 1, 2019June 6, 2023November 30, 2023
    Comment
  • PLN staff from the system planning team trained to plan for VRE through training in state-of-the-art planning tool (technical training or workshop held, 2)Value0.0020.002.00
    DateFebruary 5, 2019July 28, 2021July 28, 2021
    Comment