Preparation Project for Agus Pulangi Hydropower Complex for Rehabilitation

Abstract*

The Agus-Pulangi Hydropower Complex (APHC) has been the source of clean energy in Mindanao for many decades. With the increasing demand in Mindanao and the de-rating of the capacity of the superannuated APHC plants, the Government requested the World Bank to facilitate the provision of development partner funding to give the financial resources needed by the National Power Corporation (NPC) to prepare the APHC rehabilitation Project. This Preparation...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The development objective of the Preparation Project is to support the National Power Corporation in preparing the Agus-Pulangi Hydropower Complex rehabilitation project through preparation of feasibility study and tender documents.

Key Details

Project Details

  • P169280

  • Closed

  • Maria Ayuso Olmedo

  • National Power Corporation

  • Philippines

  • October 2, 2019

  • (as of board presentation)

    April 27, 2021

  • March 31, 2022

  • US$ 0.70 million

  • National Power Corporation

  • East Asia and Pacific

  • 2021

  • US$ 0.70 million

  • N/A

  • Substantial

  • September 30, 2023

  • No

  • BANK APPROVED

  • May 21, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Australia WB Trust Fund for Philippines Development 0.70

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 0.70
Total Project Cost** 0.70

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Unsatisfactory 2023-08-29
Overall Implementation Progress (IP) Unsatisfactory 2023-08-29
Overall Satisfactory 2023-08-29

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 09-30-2024
Outcomes
Risk to Development Outcome
Bank Performance
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Feasibility Study preparedValue0.001.000.00
    DateJune 24, 2020September 29, 2023August 2, 2023
    Comment
  • Tender Design preparedValue0.001.000.00
    DateJune 24, 2020September 29, 2023August 2, 2023
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Technical Specification for Tender Document preparedValue0.001.000.00
    DateJune 24, 2020June 30, 2023August 2, 2023
    Comment