Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 150.00 |
P169403
Closed
Luis Triveno Chan Jan
Republic of Indonesia
June 20, 2019
(as of board presentation)
June 19, 2019
June 30, 2020
US$ 150.00 million
Ministry of Public Works and Housing
2019
US$ 150.00 million
N/A
June 24, 2024
December 31, 2024
No
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 150.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 150.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 150.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 150.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 9, 2022 | IBRD-89790 | Loan Disb | 12,200,000.00 |
Aug 19, 2022 | IBRD-89790 | Loan Disb | 4,700,000.00 |
Mar 15, 2022 | IBRD-89790 | Int Charges | 2,406.72 |
Mar 15, 2022 | IBRD-89790 | Int Charges | 157,879.10 |
Mar 15, 2022 | IBRD-89790 | Int Charges | 113,879.17 |
Mar 15, 2022 | IBRD-89790 | Int Charges | 747.95 |
Sep 15, 2023 | IBRD-89790 | Int Charges | 2,328.09 |
Sep 15, 2023 | IBRD-89790 | Int Charges | 41,953.33 |
Sep 15, 2023 | IBRD-89790 | Int Charges | 104,663.03 |
Sep 15, 2023 | IBRD-89790 | Int Charges | 1,880,854.50 |
Mar 15, 2023 | IBRD-89790 | Int Charges | 845,183.60 |
Jun 19, 2019 | IBRD-89790 | Loan Commitment | 150,000,000.00 |
Aug 3, 2023 | IBRD-89790 | Loan Disb | 19,600,000.00 |
Mar 15, 2023 | IBRD-89790 | Int Charges | 869.18 |
Mar 15, 2023 | IBRD-89790 | Int Charges | 6,110.32 |
Mar 15, 2023 | IBRD-89790 | Int Charges | 139,195.55 |
May 10, 2023 | IBRD-89790 | Loan Disb | 18,000,000.00 |
Feb 10, 2023 | IBRD-89790 | Loan Disb | 10,300,000.00 |
Aug 2, 2024 | IBRD-89790 | Loan Disb | 2,400,000.00 |
Mar 15, 2024 | IBRD-89790 | Int Charges | 5,772.60 |
May 15, 2024 | IBRD-89790 | Loan Disb | 1,300,000.00 |
Oct 20, 2023 | IBRD-89790 | Loan Disb | 24,000,000.00 |
Feb 15, 2024 | IBRD-89790 | Loan Disb | 24,000,000.00 |
Mar 15, 2024 | IBRD-89790 | Int Charges | 132,352.95 |
Mar 15, 2024 | IBRD-89790 | Int Charges | 49,001.41 |
Mar 15, 2024 | IBRD-89790 | Int Charges | 3,585,232.00 |
Feb 23, 2021 | IBRD-89790 | Loan Disb | 8,600,000.00 |
Mar 15, 2021 | IBRD-89790 | Int Charges | 43,032.78 |
Mar 15, 2021 | IBRD-89790 | Int Charges | 181,156.75 |
Mar 15, 2021 | IBRD-89790 | Int Charges | 15,237.72 |
Nov 2, 2020 | IBRD-89790 | Loan Disb | 3,650,000.00 |
Sep 3, 2020 | IBRD-89790 | Fee Charges | 375,000.00 |
Sep 2, 2021 | IBRD-89790 | Loan Disb | 8,400,000.00 |
Sep 15, 2021 | IBRD-89790 | Int Charges | 171,512.31 |
Sep 15, 2021 | IBRD-89790 | Int Charges | 4,220.81 |
Sep 15, 2021 | IBRD-89790 | Int Charges | 1,178.08 |
Sep 15, 2021 | IBRD-89790 | Int Charges | 70,777.78 |
Jun 9, 2021 | IBRD-89790 | Loan Disb | 2,000,000.00 |
Sep 15, 2022 | IBRD-89790 | Int Charges | 159,626.70 |
Sep 15, 2022 | IBRD-89790 | Int Charges | 229,218.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2024-06-25 |
Procurement | Moderately Satisfactory | 2024-06-25 |
Project Management | Satisfactory | 2024-06-25 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-06-25 |
Financial Management | Moderately Satisfactory | 2024-06-25 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-06-25 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Targeted people having safer housing completed and occupied | Value | 0.00 | 6.00 | 90.00 |
Date | June 19, 2019 | May 31, 2024 | December 31, 2024 | |
Comment |
Served people having strengthened public facilities | Value | 0.00 | 17.00 | 100.00 |
Date | June 19, 2019 | May 31, 2024 | December 31, 2024 | |
Comment |
Targeted people satisfied with completed housing (disaggregated by gender) | Value | 0.00 | 0.00 | 70.00 |
Date | June 19, 2019 | May 31, 2024 | December 31, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Resilient and inclusive building standards are established for the project | Value | No | No | Yes |
Date | June 19, 2019 | May 31, 2024 | December 31, 2024 | |
Comment |
Women that are aware of land or property title rights in targeted project areas | Value | 0.00 | 84.00 | 45.00 |
Date | June 19, 2019 | May 31, 2024 | December 31, 2024 | |
Comment |
Women that are aware of employment opportunities related to recovery activities in targeted project areas | Value | 0.00 | 30.00 | 35.00 |
Date | June 19, 2019 | May 31, 2024 | December 31, 2024 | |
Comment |
Women's participation in decision-making process meetings | Value | 0.00 | 30.00 | 40.00 |
Date | June 19, 2019 | May 31, 2024 | December 31, 2024 | |
Comment |
Non-CSRRP housing provided with water supply system | Value | 0.00 | 29.00 | 90.00 |
Date | August 31, 2023 | May 31, 2024 | December 31, 2024 | |
Comment |
Non-CSRRP housing provided with strengthened settlement infrastructure | Value | 0.00 | 100.00 | 90.00 |
Date | August 31, 2023 | May 31, 2024 | December 31, 2024 | |
Comment |
Number of kelurahan/village served with local scale infrastructure | Value | 0.00 | 27.00 | 27.00 |
Date | August 31, 2023 | May 31, 2024 | December 31, 2024 | |
Comment |
Housing units constructed to project's resilience standards | Value | 0.00 | 3.39 | 3.60 |
Date | June 19, 2019 | May 31, 2024 | December 31, 2024 | |
Comment |
Education facilities rehabilitated or reconstructed to project's resilience standards | Value | 0.00 | 6.00 | 18.00 |
Date | June 19, 2019 | May 31, 2024 | December 31, 2024 | |
Comment |
MIS and project website established and functioning | Value | No | Yes | Yes |
Date | June 19, 2019 | May 31, 2024 | December 31, 2024 | |
Comment |
Reconstructed houses provided with housing connection for water supply | Value | 0.00 | 22.60 | 90.00 |
Date | June 19, 2019 | May 31, 2024 | December 31, 2024 | |
Comment |
Health facilities rehabilitated or reconstructed to project's resilience standards | Value | 0.00 | 4.00 | 7.00 |
Date | June 19, 2019 | May 31, 2024 | December 31, 2024 | |
Comment |
Grievance redress mechanism established and functioning | Value | No | Yes | Yes |
Date | June 19, 2019 | May 31, 2024 | December 31, 2024 | |
Comment |
Reconstructed houses provided with sanitation system | Value | 0.00 | 22.60 | 90.00 |
Date | June 19, 2019 | May 31, 2024 | December 31, 2024 | |
Comment |
Gender- and disability-inclusive reconstructed public facilities | Value | 0.00 | 10.00 | 80.00 |
Date | June 19, 2019 | May 31, 2024 | December 31, 2024 | |
Comment |
Complaints resolved | Value | 80.00 | 99.54 | 90.00 |
Date | June 28, 2022 | May 31, 2024 | December 31, 2024 | |
Comment |
Constructed houses built in resettlement sites provided with direct access to a paved road network | Value | 0.00 | 6.00 | 90.00 |
Date | June 19, 2019 | May 31, 2024 | December 31, 2024 | |
Comment |
Other public facilities constructed to project’s resilience standards | Value | 0.00 | 1.00 | 5.00 |
Date | August 31, 2023 | May 31, 2024 | December 31, 2024 | |
Comment |