Indonesia Mass Transit Project

Abstract*

Indonesia, the world's fourth most populous country, is becoming increasingly urban. Today over half of the population lives in cities; by 2045, the centenary of Indonesia's independence, nearly three-quarters will. In 2016, Indonesia had 14 cities with a population greater than 1 million and 12 cities with a population between 500,000 and 1 million. Rapid urbanization is increasing the importance of cities as living space for people and economic...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve urban mobility and accessibility on high priority corridors in selected urban areas of Indonesia and strengthen institutional capacity for mass transit development.

Key Details

Project Details

  • P169548

  • Active

  • Nupur Gupta , Amilia Aldian

  • Republic of Indonesia

  • Indonesia

  • April 15, 2020

  • (as of board presentation)

    May 20, 2022

  • September 21, 2022

  • US$ 364.00 million

  • Ministry of Transportation

  • East Asia and Pacific

  • 2022

  • US$ 224.00 million

  • N/A

  • Substantial

  • June 30, 2027

  • No

  • BANK APPROVED

  • October 26, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 224.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 224.00
IDA Commitment N/A
IBRD + IDA Commitment 224.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 364.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 20, 2022 IBRD-93400 Loan Commitment 223,996,592.00
Dec 13, 2023 IBRD-93400 Loan Disb 1,237,000.00
Nov 14, 2022 IBRD-93400 Fee Charges 559,991.50
Nov 28, 2022 IBRD-93400 Loan Disb 2,700,000.00
Jul 1, 2023 IBRD-93400 Int Charges 628.77
Jul 1, 2023 IBRD-93400 Int Charges 12,509.69
Jul 1, 2023 IBRD-93400 Int Charges 274,347.12
Jul 1, 2023 IBRD-93400 Int Charges 71,633.33
Jul 1, 2024 IBRD-93400 Int Charges 273,571.38
Jul 1, 2024 IBRD-93400 Int Charges 127,195.03
Jul 1, 2024 IBRD-93400 Int Charges 4,530.47
Jul 2, 2024 IBRD-93400 Loan Disb 1,345,000.00
Jul 1, 2024 IBRD-93400 Int Charges 160.98
Jan 1, 2024 IBRD-93400 Int Charges 1,475.97
Jan 1, 2024 IBRD-93400 Int Charges 278,733.34
Jan 1, 2024 IBRD-93400 Int Charges 86,352.04
Jan 1, 2023 IBRD-93400 Int Charges 192,683.36

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Moderately Satisfactory 2025-04-01
Monitoring and Evaluation Moderately Satisfactory 2025-04-01
Overall Implementation Progress (IP) Moderately Unsatisfactory 2025-04-01
Progress towards achievement of PDO Moderately Satisfactory 2025-04-01
Procurement Moderately Satisfactory 2025-04-01
Financial Management Moderately Satisfactory 2025-04-01

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Average travel time for public transport users from Stasiun Cimindi to Intersection Jl. Jendral Ahmad Yani/Jl. Kiaracondong on the BBMA BRT corridor (minutes)Value50.0050.0040.00
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Establishment of an institutional structures to manage mass transit at the national level and sub-national levelsValueNo dedicated unit within MoT and no operating entiNo dedicated unit within MoT and no operating entiFunctional institutional arrangements at national
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Average travel time for public transport users from Pinang Baris to Amplas on the Mebidang BRT corridor (minutes)Value83.0083.0062.00
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Establishment of an institutional structure (a dedicated equipped unit within MoT) to manage mass transit at the national levelValueNo dedicated unit within MoT to manage urban mobilNo dedicated unit within MoT to manage urban mobilDedicated equipped unit within MoT to manage urban
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Average daily passenger ridership per weekday on the BBMA BRT (number of passengers)Value0.000.0060000.00
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Establishment of institutional structures (BRT Management Entity) to plan and manage mass transit systems in BBMAValuePartially functional Transit Agency to plan and maPartially functional Transit Agency to plan and ma
    DateOctober 1, 2021July 25, 2023December 31, 2027
    Comment
  • Average daily passenger ridership per weekday on the Mebidang BRT (number of passengers)Value0.000.0090000.00
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Establishment of institutional structures (BRT Management Entity) to plan and manage mass transit systems in MebidangValueNo Operating Agency to plan and manage mass transiNo Operating Agency to plan and manage mass transiFunctional BRT Management Entity to plan and manag
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Jobs accessible by public transport within 90 minutes commuting period in BBMA (percentage)Value21.0021.0025.00
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Women employed in BBMA BRT operations at both managerial and crew levels (percentage)Value0.000.0015.00
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Jobs accessible by public transport within 90 minutes commuting period in Mebidang (percentage)Value40.0040.0046.00
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Women employed in Mebidang BRT operations at both managerial and crew levels (percentage)Value0.000.0015.00
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Users satisfaction with public transport services (with a focus on safety and security) along BBMA BRT corridor (percentage)Value48.0048.0075.00
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Female users satisfaction with public transport services (with a focus on safety and security) along BBMA BRT corridor (percentage)Value40.0040.000.00
    Date
    Comment
  • Users satisfaction with public transport services (with a focus on safety and security) along Mebidang BRT corridor (percentage)Value58.0058.0075.00
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Female users satisfaction with public transport services (with a focus on safety and security) along Mebidang BRT corridor (percentage)Value56.0055.000.00
    Date
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Indonesia Mass Transit Project Design FinalisedValueNoNoYes
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Constructed BBMA BRT corridor (kilometer)Value0.000.0020.00
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Number of metropolitan areas beyond BBMA and Mebidang benefited from project preparation assistance (number)Value0.000.002.00
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Constructed Mebidang BRT corridor (kilometer)Value0.000.0021.00
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • BRT ITS implemented and functional in BBMAValueNoNoYes
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Designs for sub-national level institutional arrangements in BBMA and Mebidang finalizedValueNoNoYes
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Development of guidelines and manuals in relevant areas (number)Value1.001.004.00
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • BRT fare collection system implemented and function in BBMAValueNoNoYes
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • BRT passenger information and bus managements systems implemented and function in BBMAValueNoNoYes
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • BRT ITS implemented and functional in MebidangValueNoNoYes
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • BRT fare collection system implemented and function in MebidangValueNoNoYes
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • BRT passenger information and bus managements systems implemented and function in MebidangValueNoNoYes
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Pedestrians/walkway infrastructure rehabilitated in BBMA (kilometer)Value0.000.0020.00
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Pedestrians/walkway infrastructure rehabilitated in Mebidang (kilometer)Value0.000.0021.00
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Road safety audit conducted on BBMA and Mebidang BRT corridors at project, design, construction and post-construction phasesValueNoNoYes
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Road safety audit conducted on BBMA BRT corridors at project design phaseValueNoNoYes
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Road safety audit conducted on Mebidang BRT corridors at project design phaseValueNoNoYes
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Road safety audit conducted on BBMA BRT corridors at project construction phaseValueNoNoYes
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Road safety audit conducted on Mebidang BRT corridors at project construction phaseValueNoNoYes
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Road safety audit conducted on BBMA BRT corridors at project post-construction phaseValueNoNoYes
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Road safety audit conducted on Mebidang BRT corridors at project post-construction phaseValueNoNoYes
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Designs for resilience against flooding events developed and incorporated into BBMA BRT design (infrastructure and vehicle specification)ValueNoNoYes
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Designs for resilience against flooding events developed and incorporated into Mebidang BRT design (infrastructure and vehicle specification)ValueNoNoYes
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Gender and disable-friendly station designs in BBMA BRTValueNoNoYes
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment
  • Gender and disable-friendly station designs in Mebidang BRTValueNoNoYes
    DateOctober 1, 2021July 25, 2023June 30, 2027
    Comment