First Resilient Kerala Program Development Policy Operation

Abstract*

The development objective of the First Resilient Kerala Program Development Policy Operation for India is to enhance the State of Kerala's resilience against the impacts of natural disasters and climate change. There are three unique aspects of the first state partnership that the Government of Kerala (GoK) and the World Bank have established through the operation: (i) the confluence and the combination of the two stories, (ii) strong commitment of...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Program Development Objective (PDO) is to enhance the State of Kerala's resilience against the impacts of natural disasters andclimate change.

Key Details

Project Details

  • P169907

  • Closed

  • Elif Ayhan , Balakrishna Menon Parameswaran

  • India

  • India

  • March 7, 2019

  • (as of board presentation)

    June 27, 2019

  • August 21, 2019

  • US$ 0.00 million

  • State of Kerala

  • South Asia

  • 2019

  • US$ 250.00 million

  • N/A

  • June 8, 2022

  • June 30, 2021

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 250.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 250.00
IBRD + IDA Commitment 250.00
Lending Instrument
Grant Amount N/A
Total Project Cost** N/A

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 27, 2019 IDA-64630 Loan Disb 158,035,968.00
Aug 21, 2019 IDA-64640 Loan Disb 226,000.00
Nov 15, 2019 IDA-64640 Int Charges 18,600.02
Nov 15, 2019 IDA-64640 Int Charges 608,290.80
Nov 15, 2019 IDA-64630 Int Charges 257,308.27
Nov 15, 2019 IDA-64630 Int Charges 257,308.27
Nov 15, 2019 IDA-64630 Int Charges 428,178.20
May 15, 2020 IDA-64640 Int Charges 244,505.03
May 15, 2020 IDA-64640 Int Charges 994,025.20
May 15, 2020 IDA-64630 Int Charges 661.57
May 15, 2020 IDA-64630 Int Charges 587,256.50
May 15, 2020 IDA-64630 Int Charges 587,256.50
May 15, 2020 IDA-64630 Int Charges 978,760.80
Nov 15, 2020 IDA-64640 Int Charges 679,205.30
May 15, 2021 IDA-64630 Int Charges 3,712.08
May 15, 2021 IDA-64630 Int Charges 621,518.40
May 15, 2021 IDA-64630 Int Charges 621,518.40
May 15, 2021 IDA-64630 Int Charges 1,024,064.20
May 15, 2021 IDA-64640 Int Charges 477,236.66
Nov 15, 2020 IDA-64630 Int Charges 591,730.06
Nov 15, 2020 IDA-64630 Int Charges 591,730.06
Nov 15, 2020 IDA-64630 Int Charges 21,632.18
Nov 15, 2020 IDA-64630 Int Charges 1,018,607.06
Nov 15, 2020 IDA-64630 Int Charges 21,632.18
May 15, 2024 IDA-64630 Int Charges 571,674.25
May 15, 2024 IDA-64630 Int Charges 571,674.25
May 15, 2024 IDA-64630 Int Charges 8,845.45
Jun 27, 2019 IDA-64630 Loan Commitment 159,600,000.00
Jun 27, 2019 IDA-64640 Loan Commitment 90,400,000.00
May 15, 2024 IDA-64640 Int Charges 17,825.02
May 15, 2024 IDA-64640 Int Charges 3,012,328.80
May 15, 2024 IDA-64630 Int Charges 952,790.40
May 15, 2023 IDA-64640 Int Charges 126,788.83
May 15, 2023 IDA-64640 Int Charges 2,382,522.00
Nov 15, 2023 IDA-64630 Int Charges 946,106.30
Nov 15, 2023 IDA-64640 Int Charges 2,854,802.00
Nov 15, 2023 IDA-64640 Int Charges 54,157.68
Nov 15, 2023 IDA-64630 Int Charges 13,204.01
Nov 15, 2023 IDA-64630 Int Charges 572,983.20
Nov 15, 2023 IDA-64630 Int Charges 572,983.20
May 15, 2023 IDA-64630 Int Charges 24,753.17
May 15, 2023 IDA-64630 Int Charges 580,029.10
May 15, 2023 IDA-64630 Int Charges 580,029.10
May 15, 2023 IDA-64630 Int Charges 953,348.80
May 15, 2022 IDA-64630 Int Charges 24,445.45
Nov 15, 2022 IDA-64630 Int Charges 512,557.90
Nov 15, 2022 IDA-64630 Int Charges 512,557.90
Nov 15, 2022 IDA-64630 Int Charges 923,237.25
Nov 15, 2022 IDA-64640 Int Charges 957,560.40
Nov 15, 2022 IDA-64640 Int Charges 528,618.75
Nov 15, 2022 IDA-64630 Int Charges 55,941.12
Nov 15, 2022 IDA-64630 Int Charges 55,941.12
Nov 15, 2021 IDA-64640 Int Charges 471,285.34
Nov 15, 2021 IDA-64630 Int Charges 606,929.75
Nov 15, 2021 IDA-64630 Int Charges 606,929.75
Nov 15, 2021 IDA-64630 Int Charges 236,555.31
Nov 15, 2021 IDA-64630 Int Charges 774,994.30
Nov 15, 2021 IDA-64630 Int Charges 11,522.84
May 15, 2022 IDA-64640 Int Charges 481,781.78
May 15, 2022 IDA-64630 Int Charges 550,447.20
May 15, 2022 IDA-64630 Int Charges 550,447.20
May 15, 2022 IDA-64630 Int Charges 958,154.40
May 15, 2022 IDA-64630 Int Charges 24,445.45
Aug 21, 2019 IDA-64640 Fee Charges 226,000.00
Aug 27, 2019 IDA-64640 Loan Disb 90,174,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2021-03-22
Overall Implementation Progress (IP) Satisfactory 2021-03-22
Program Management Satisfactory 2021-03-22
Monitoring and Evaluation Moderately Satisfactory 2021-03-22

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 06-08-2022
OutcomesSubstantial
Risk to Development Outcome
Bank PerformanceSubstantial
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 04-03-2023PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingSatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceSatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Percentage of medium-term (1-3 years) resilient recovery activities implemented as per RKDP priorities and programs.Value0.0025.0625.00
    DateJune 27, 2019April 1, 2022June 30, 2021
    Comment
  • Improved river basin planning and water infrastructure operations management for climate resilience at the State level.ValueInadequate river basin planning and management funRiver basin management plans not developed for twoRiver basin management plans are developed for two
    DateJune 27, 2019April 1, 2022June 30, 2021
    Comment
  • Number of women and children benefitting from RKDP programs.Value0.003121.531000.00
    DateJune 27, 2019April 1, 2022June 30, 2021
    Comment
  • Number of agroecological zones adopting resilient and sustainable agroecological zone development plans.Value0.005.002.00
    DateJune 27, 2019April 1, 2022June 30, 2021
    Comment
  • Additional public and private financial resources are mobilized for resilient recoveryValue0.00567034308.00500000000.00
    DateJune 27, 2019April 1, 2022June 30, 2021
    Comment
  • Percentage of agriculture risk insurance uptakeValue10.0016.8020.00
    DateJune 27, 2019February 24, 2021June 30, 2021
    Comment
  • Improved capacity for emergency, disaster, and climate risk management with outreach to vulnerable communities.ValueWeak coordination capacity among key agencies to rA state-wide emergency management exercise satisfaA State-wide emergency management exercise is sati
    DateJune 27, 2019April 1, 2022June 30, 2021
    Comment
  • Number of key core road network corridors adopting performance-based management contract based on resilient standardsValue0.008.005.00
    DateJune 27, 2019April 1, 2022June 30, 2021
    Comment
  • Increased share of road sector budget allocation for the core road network from the 2018 budget allocation for the core roadsValue0.0056.0920.00
    DateJune 27, 2019April 1, 2022June 30, 2021
    Comment
  • Number of high-risk districts implementing a Kerala Land Records Modernization Mission program for single digital land record & map, providing gender disaggregated data on land ownership & transactionValue0.000.002.00
    DateJune 27, 2019April 1, 2022June 30, 2021
    Comment
  • Number of urban local bodies preparing and notifying risk-informed master plansValue0.002.002.00
    DateJune 27, 2019April 1, 2022June 30, 2021
    Comment
  • Number of urban local bodies undertaking multi-year municipal infrastructure investment planning and budgetingValue0.003.002.00
    DateJune 27, 2019April 1, 2022June 30, 2021
    Comment
  • Number of urban local bodies adopting non-revenue water reduction modelsValue0.003.002.00
    DateJune 27, 2019April 1, 2022June 30, 2021
    Comment
  • Percentage of O&M cost recovery at state level for improved water supply and sanitation servicesValue41.0057.5850.00
    DateJune 27, 2019April 1, 2022June 30, 2021
    Comment
  • Annual Performance Report is publicly disclosed by KWA.ValueNo Annual Performance Report by KWAAnnual Performance Report is publicly disclosed byAnnual Performance Report is publicly disclosed by
    DateJune 27, 2019April 1, 2022June 30, 2021
    Comment
  • Number of urban local bodies adopting cost-effective septage and sewerage programsValue0.009.005.00
    DateJune 27, 2019April 1, 2022June 30, 2021
    Comment