Southern Waterway Corridors and Logistics Development Project

Abstract*

The project will upgrade two key waterways, to allow increased cargo volumes in larger vessels to navigate on corridors connecting the four largest ports in southern Viet Nam. This will reduce transport costs, time, GHG emissions, and accidents. The project will increase the waterways capacity of an East–West Corridor and North–South Corridor, connecting the Can Tho port, the main port in Mekong Delta, the key Dong Nai manufacturing center, the Ho...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective is to improve the capacity, efficiency and safety of the transport infrastructure of the East-West and North-South Waterway Logistics Corridors.

Key Details

Project Details

  • P169954

  • Active

  • Yin Lam , Chi Nguyen

  • Socialist Republic of Viet Nam

  • Viet Nam

  • March 29, 2019

  • (as of board presentation)

    June 21, 2024

  • N/A

  • US$ 168.00 million

  • Ministry of Transport

  • East Asia and Pacific

  • 2024

  • US$ 107.00 million

  • N/A

  • May 26, 2022

  • December 15, 2029

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 107.00
Borrower/Recipient 55.20

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 107.00
IBRD + IDA Commitment 107.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 168.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 21, 2024 IDA-75770 Loan Commitment 107,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Satisfactory 2025-03-11
Overall Implementation Progress (IP) Satisfactory 2025-03-11
Progress towards achievement of PDO Satisfactory 2025-03-11
Procurement Satisfactory 2025-03-11
Project Management Satisfactory 2025-03-11
Financial Management Satisfactory 2025-03-11

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

No data available.