Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 148.80 |
P169996
Active
Sudipto Sarkar , Verena Schaidreiter
ILLER BANKASI ANONIM SIRKETI (ILBANK)
October 2, 2019
(as of board presentation)
March 31, 2020
May 13, 2021
US$ 296.76 million
ILLER BANKASI ANONIM SIRKETI (ILBANK)
2020
US$ 148.80 million
N/A
June 21, 2024
December 31, 2026
No
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 148.80 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 148.80 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 148.80 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 296.76 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 31, 2020 | IBRD-90770 | Loan Commitment | 148,800,000.00 |
Jul 15, 2024 | IBRD-90770 | Int Charges | 351,134.72 |
Sep 10, 2021 | IBRD-90770 | Loan Disb | 3,904,230.00 |
May 13, 2021 | IBRD-90770 | Loan Disb | 408,399.88 |
May 13, 2021 | IBRD-90770 | Fee Charges | 408,399.88 |
Jan 15, 2022 | IBRD-90770 | Int Charges | 63,545.66 |
Jan 15, 2022 | IBRD-90770 | Int Charges | 698.52 |
Jan 15, 2022 | IBRD-90770 | Int Charges | 191,585.88 |
Jan 15, 2022 | IBRD-90770 | Int Charges | 15,925.92 |
Jul 15, 2022 | IBRD-90770 | Int Charges | 163,374.06 |
Jul 15, 2022 | IBRD-90770 | Int Charges | 18,768.96 |
Jul 15, 2023 | IBRD-90770 | Int Charges | 172,086.42 |
Jul 15, 2023 | IBRD-90770 | Int Charges | 286,908.38 |
Jan 15, 2023 | IBRD-90770 | Int Charges | 947.90 |
Jan 15, 2023 | IBRD-90770 | Int Charges | 2,973.25 |
Jan 15, 2023 | IBRD-90770 | Int Charges | 168,577.30 |
Jan 15, 2023 | IBRD-90770 | Int Charges | 122,842.18 |
May 22, 2024 | IBRD-90770 | Loan Disb | 8,670,400.00 |
Jan 15, 2024 | IBRD-90770 | Int Charges | 170,623.30 |
Jan 15, 2024 | IBRD-90770 | Int Charges | 358,101.75 |
Jul 15, 2024 | IBRD-90770 | Int Charges | 164,577.22 |
Jun 29, 2022 | IBRD-90770 | Loan Disb | 8,416,800.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2024-12-18 |
Project Management | Moderately Satisfactory | 2024-12-18 |
Procurement | Satisfactory | 2024-12-18 |
Monitoring and Evaluation | Satisfactory | 2024-12-18 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-12-18 |
Financial Management | Satisfactory | 2024-12-18 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People benefitting from safely managed drinking water services in the selected municipalities as a result of the project | Value | 0.00 | 75662.00 | 1950193.00 |
Date | January 16, 2020 | June 26, 2024 | December 31, 2024 | |
Comment |
People benefitting from safely managed drinking water services in the selected municipalities (out of which female) | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
People benefitting from safely managed drinking water services in the selected municipalities (out of which host community) | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
People benefitting from safely managed drinking water services in the selected municipalities (out of which refugees) | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
People benefitting from safely managed sanitation services in the selected municipalities as a result of the project | Value | 0.00 | 63083.00 | 2402023.00 |
Date | January 16, 2020 | June 26, 2024 | December 31, 2024 | |
Comment |
People benefitting from safely managed sanitation services in the selected municipalities (out of which female) | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
People benefitting from safely managed sanitation services in the selected municipalities (out of which host community) | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
People benefitting from safely managed sanitation services in the selected municipalities (out of which refugees) | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
People benefitting from safely managed solid waste services in the selected municipalities as a result of the project | Value | 0.00 | 0.00 | 320685.00 |
Date | January 16, 2020 | June 26, 2024 | December 31, 2024 | |
Comment |
People benefitting from safely managed solid waste services in the selected municipalities (out of which female) | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
People benefitting from safely managed solid waste services in the selected municipalities (out of which host community) | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
People benefitting from safely managed solid waste services in the selected municipalities (out of which refugees) | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Water supply network constructed, rehabilitated and/or extended | Value | 0.00 | 80.30 | 2062.00 |
Date | January 16, 2020 | June 26, 2024 | December 31, 2024 | |
Comment |
Number of municipal authorities and SKIs provided with capacity building support through the Project | Value | 0.00 | 0.00 | 5.00 |
Date | January 16, 2020 | June 26, 2024 | December 31, 2024 | |
Comment |
Water treatment plants constructed or rehabilitated | Value | 0.00 | 0.00 | 1.00 |
Date | January 16, 2020 | June 26, 2024 | December 31, 2024 | |
Comment |
Number of municipal authorities and SKIs that have prepared a Performance Improvement Action Plan through the project | Value | 0.00 | 2.00 | 4.00 |
Date | January 16, 2020 | June 26, 2024 | December 31, 2024 | |
Comment |
Water reservoirs constructed or rehabilitated | Value | 0.00 | 0.00 | 43.00 |
Date | January 16, 2020 | June 26, 2024 | December 31, 2024 | |
Comment |
Grievances registered related to delivery of municipal services that are actually addressed and recorded | Value | 0.00 | 100.00 | 90.00 |
Date | January 16, 2020 | June 26, 2024 | December 31, 2024 | |
Comment |
Water pumping stations constructed or rehabilitated | Value | 0.00 | 0.00 | 16.00 |
Date | January 16, 2020 | June 26, 2024 | December 31, 2024 | |
Comment |
Percentage of women’s needs and investment choices that were implemented by selected municipalities and SKIs | Value | 0.00 | 0.00 | 70.00 |
Date | March 31, 2020 | June 26, 2024 | December 31, 2024 | |
Comment |
Sewerage network constructed, rehabilitated and/or extended | Value | 0.00 | 13.00 | 495.00 |
Date | January 16, 2020 | June 26, 2024 | December 31, 2024 | |
Comment |
Wastewater treatment plants constructed or rehabilitated | Value | 0.00 | 0.00 | 7.00 |
Date | January 16, 2020 | June 26, 2024 | December 31, 2024 | |
Comment |
Landfills constructed or rehabilitated | Value | 0.00 | 0.00 | 1.00 |
Date | January 16, 2020 | June 26, 2024 | December 31, 2024 | |
Comment |
Satisfaction rate of female users of environmental infrastructure services and facilities provided by the project | Value | 0.00 | 0.00 | 70.00 |
Date | March 31, 2020 | June 26, 2024 | December 31, 2024 | |
Comment |