Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 28.90 |
P170178
Active
Ciro Avitabile
Republic of Croatia
April 5, 2019
(as of board presentation)
November 30, 2021
April 20, 2022
US$ 28.90 million
Ministry of Science and Education
2022
US$ 28.90 million
N/A
February 14, 2024
June 30, 2026
No
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 28.90 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 28.90 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 28.90 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 28.90 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Nov 30, 2021 | IBRD-93030 | Loan Commitment | 28,900,000.00 |
May 15, 2024 | IBRD-93030 | Int Charges | 98,041.27 |
May 3, 2022 | IBRD-93030 | Fee Charges | 65,650.00 |
Nov 15, 2022 | IBRD-93030 | Int Charges | 16,045.89 |
Nov 15, 2022 | IBRD-93030 | Int Charges | 32,215.73 |
Nov 15, 2022 | IBRD-93030 | Int Charges | 716.87 |
Nov 30, 2022 | IBRD-93030 | Loan Disb | 2,283,398.00 |
Nov 15, 2023 | IBRD-93030 | Int Charges | 62,792.56 |
Nov 15, 2023 | IBRD-93030 | Int Charges | 30,477.29 |
May 15, 2023 | IBRD-93030 | Int Charges | 39,513.35 |
May 15, 2023 | IBRD-93030 | Int Charges | 30,264.02 |
Aug 5, 2024 | IBRD-93030 | Loan Disb | 10,948,500.00 |
Jan 29, 2024 | IBRD-93030 | Loan Disb | 2,164,600.00 |
May 15, 2024 | IBRD-93030 | Int Charges | 28,389.07 |
Jun 15, 2022 | IBRD-93030 | Loan Disb | 566,055.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2024-12-20 |
Project Management | Moderately Satisfactory | 2024-12-20 |
Monitoring and Evaluation | Satisfactory | 2024-12-20 |
Procurement | Moderately Satisfactory | 2024-12-20 |
Financial Management | Moderately Satisfactory | 2024-12-20 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-12-20 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Students benefiting from the WDS pedagogical model | Value | 0.00 | 12021.00 | 32500.00 |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |
MSE staff and school founders preparing cost-effective school network plans to scale up the WDS system | Value | 0% of MSE staff and school founders preparing cost | 0% of MSE staff and school founders preparing cost | 75% of MSE staff and school founders preparing cos |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |
Teachers in WDS demonstration schools receiving training from learning counselors | Value | 0.00 | 1000.00 | 1250.00 |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |
MSE staff participating in training on designing and implementing reforms | Value | 0.00 | 0.00 | 100.00 |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |
Schools with improved physical environment according to WDS standards | Value | 0.00 | 0.00 | 50.00 |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Legislation on teacher and staff norms revised | Value | No | Yes | Yes |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |
Standard designs developed for new modern and energy-efficient (green) schools | Value | No | Yes | Yes |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |
Working Group with the capacity and responsibility to plan and implement reforms in the MSE established | Value | No | Yes | Yes |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |
Pedagogical model documentation designed for WDS | Value | No | Yes | Yes |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |
Percentage of school founders receiving financing and guidance to prepare documentation for school infrastructure | Value | 0.00 | 40.00 | 70.00 |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |
Comprehensive communication and outreach strategy for the WDS developed | Value | No | Yes | Yes |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |
Labor supply of mothers with children aged 6-14 benefiting from WDS (hours willing to work per day and hours of childcare per day) | Value | Baseline measured at the beginning of school Year | Baseline measured at the beginning of school Year | 20% increase in average hours20% decrease in aver |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |
Mechanism to foster peer-to-peer learning on learning spaces developed and implemented | Value | No | No | Yes |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |
Number of WDS demonstration schools benefiting from infrastructure investments (Cumulative) | Value | 0.00 | 0.00 | 50.00 |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |
Percentage of project beneficiaries reporting on beneficiary surveys satisfaction with engagement processes in the development and rollout of WDS in demonstration schools | Value | 0.00 | 0.00 | 60.00 |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |
Number of principals in low-performing WDS demonstration schools participating in peer mentoring program (cumulative) | Value | 0.00 | 0.00 | 25.00 |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |
Number of school founders benefiting from capacity building and training on network planning and costing | Value | 0.00 | 0.00 | 40.00 |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |
Percentage of WDS demonstration schools joining the peer-mentoring program | Value | 0.00 | 0.00 | 20.00 |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |
Working Group produces Annual Reports including feedback from school founders on the progress of the WDS implementation | Value | Limited capacity of the Ministry to monitor implem | Limited capacity of the Ministry to monitor implem | Working Group elaborates on Annual Reports includi |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |
Share of primary schools using new education database towards learning | Value | 0.00 | 0.00 | 100.00 |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |
Impact evaluation designed and implemented | Value | No | No | Yes |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |
Students benefiting from direct interventions to enhance learning | Value | 0.00 | 12021.00 | 32500.00 |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |
Share of students participating in the WDS reporting a boost in well-being, satisfaction and motivation in student surveys | Value | 0.00 | 0.00 | 80.00 |
Date | October 29, 2021 | January 29, 2024 | June 30, 2026 | |
Comment |