North Macedonia: Local Roads Connectivity Project

Abstract*

The project will finance rehabilitation of municipal roads, estimated at about 450 km, to provide better connectivity to market and services for municipal beneficiaries, and support both central and local government to build their capacity to better manage their local road assets. The project will also finance implementation support, CERC component, and front-end fee.

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objectives are: 1) to improve government capacity to manage local roads and improve access to markets and services; and 2) to provide immediate and effective response to an eligible crisis or emergency.

Key Details

Project Details

  • P170267

  • Active

  • Wenyu Jia

  • Republic of North Macedonia

  • North Macedonia

  • August 21, 2019

  • (as of board presentation)

    December 18, 2019

  • February 24, 2020

  • US$ 78.00 million

  • Ministry of Transport and Communications

  • Europe and Central Asia

  • 2020

  • US$ 78.00 million

  • N/A

  • Substantial

  • September 30, 2026

  • No

  • BANK APPROVED

  • March 1, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 78.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 78.00
IDA Commitment N/A
IBRD + IDA Commitment 78.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 78.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Sep 1, 2020 IBRD-90340 Int Charges 96,143.47
Sep 1, 2020 IBRD-90340 Int Charges 11,813.29
Mar 1, 2021 IBRD-90340 Int Charges 73.42
Sep 15, 2023 IBRD-92100 Int Charges 1,939.58
Sep 15, 2023 IBRD-92100 Int Charges 49,564.85
Mar 1, 2021 IBRD-90340 Int Charges 47,356.44
Mar 15, 2024 IBRD-92100 Int Charges 50,051.63
Mar 15, 2024 IBRD-92100 Int Charges 2,251.15
Mar 15, 2024 IBRD-92100 Loan Repay 6,296.36
Dec 18, 2019 IBRD-90340 Loan Commitment 78,000,000.00
Mar 4, 2021 IBRD-92100 Loan Commitment 44,800,000.00
Mar 1, 2021 IBRD-90340 Int Charges 60,169.86
Sep 1, 2020 IBRD-90340 Int Charges 5,149.95
Mar 1, 2021 IBRD-90340 Int Charges 243.65
Feb 24, 2020 IBRD-90340 Loan Disb 189,358.75
Feb 24, 2020 IBRD-90340 Fee Charges 189,358.75
Oct 3, 2022 IBRD-90340 Loan Disb 1,473,589.40
Dec 27, 2022 IBRD-90340 Loan Disb 3,262,610.50
Sep 1, 2022 IBRD-90340 Int Charges 24,548.59
Sep 1, 2022 IBRD-90340 Int Charges 54,361.20
Mar 1, 2022 IBRD-90340 Int Charges 31,647.92
Mar 1, 2022 IBRD-90340 Int Charges 45,047.11
Aug 5, 2022 IBRD-90340 Loan Disb 49,633.34
Mar 14, 2022 IBRD-90340 Loan Disb 3,715,483.50
Jun 24, 2022 IBRD-90340 Loan Disb 681,777.00
Sep 1, 2023 IBRD-90340 Int Charges 17,334.07
Sep 1, 2023 IBRD-90340 Int Charges 1,242,918.50
Jul 6, 2023 IBRD-90340 Loan Disb 1,448,591.50
Apr 3, 2023 IBRD-90340 Loan Disb 1,449,233.60
Mar 1, 2023 IBRD-90340 Int Charges 21,736.51
Mar 1, 2023 IBRD-90340 Int Charges 543,120.50
Mar 1, 2023 IBRD-90340 Int Charges 8.15
Mar 1, 2023 IBRD-90340 Int Charges 1.41
Mar 1, 2024 IBRD-90340 Int Charges 562.01
Feb 12, 2024 IBRD-90340 Loan Disb -107,671.32
Dec 12, 2023 IBRD-90340 Loan Disb 5,291,195.50
Jun 3, 2024 IBRD-90340 Loan Disb 2,543,568.20
Mar 1, 2024 IBRD-90340 Int Charges 8,418.34
Mar 1, 2024 IBRD-90340 Int Charges 12,628.39
Mar 1, 2024 IBRD-90340 Int Charges 1,545,118.90
Mar 15, 2023 IBRD-92100 Int Charges 45,398.20
Mar 15, 2023 IBRD-92100 Int Charges 997.88
Sep 13, 2022 IBRD-92100 Fee Charges 94,160.38
Sep 13, 2022 IBRD-92100 Loan Disb 94,160.38
Jun 10, 2020 IBRD-90340 Loan Disb 113,655.00
Jun 23, 2020 IBRD-90340 Loan Disb 17,231,560.00
Jul 17, 2020 IBRD-90340 Loan Disb 608,779.30
Sep 29, 2020 IBRD-90340 Loan Disb 15,723,449.00
Sep 1, 2021 IBRD-90340 Int Charges 34,027.79
Sep 1, 2021 IBRD-90340 Int Charges 51,283.74
Dec 11, 2020 IBRD-90340 Loan Disb 12,122,500.00
Oct 6, 2020 IBRD-90340 Loan Disb 7,804,384.00
Aug 27, 2020 IBRD-90340 Loan Disb 563,697.70
Aug 27, 2020 IBRD-90340 Loan Disb 643,808.06
Sep 1, 2020 IBRD-90340 Int Charges 12.59

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Satisfactory 2025-01-30
Financial Management Moderately Satisfactory 2025-01-30
Progress towards achievement of PDO Satisfactory 2025-01-30
Monitoring and Evaluation Moderately Satisfactory 2025-01-30
Overall Implementation Progress (IP) Moderately Satisfactory 2025-01-30
Project Management Moderately Satisfactory 2025-01-30

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of SMEs supported through the CERC (including duplications if same firms used the support in different months or both salaryand contributions support in same month)Value0.0026992.0026992.00
    DateMarch 30, 2020December 14, 2023November 30, 2020
    Comment
  • Municipalities utilizing simple asset management methods developed under the projectValue0.000.0065.00
    DateDecember 31, 2019December 14, 2023December 31, 2024
    Comment
  • National policy adopted for local roadsValueNoNoYes
    DateDecember 31, 2019December 14, 2023July 1, 2024
    Comment
  • Number of markets and services connected by improved, safe and resilient local roadsValue0.001100.00200.00
    DateDecember 31, 2019December 14, 2023December 31, 2025
    Comment
  • Beneficiary satisfaction (gender disaggregated) with project roads (percentage)ValueN/A89.5%80 percent express satisfaction
    DateDecember 31, 2019December 14, 2023December 31, 2024
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of employees supported through the CERC funding (including duplications if same employees benefited in different months or received both salary and contributions support in same month)Value0.00175161.00175161.00
    DateMarch 30, 2020December 14, 2023November 30, 2020
    Comment
  • Road safety audits of road rehabilitation designsValue0.0030.0070.00
    DateDecember 31, 2019December 14, 2023December 31, 2024
    Comment
  • Independent technical audits of planning, design, and constructionValueNoNoYes
    DateDecember 31, 2019December 14, 2023December 30, 2022
    Comment
  • Participating municipalities signed MoU with MoTCValue0.00100.00100.00
    DateDecember 31, 2019December 14, 2023December 31, 2024
    Comment
  • Community-driven infrastructure pilots implementedValue0.000.005.00
    DateDecember 31, 2019December 14, 2023December 31, 2024
    Comment
  • Municipalities using improved maintenance contractsValue0.000.0065.00
    DateDecember 31, 2019December 14, 2023December 31, 2024
    Comment
  • Roads rehablitatedValue0.0096.00450.00
    DateDecember 31, 2019December 14, 2023December 31, 2024
    Comment
  • Roads rehabilitated - ruralValue0.000.0025.00
    Date
    Comment
  • Roads rehabilitated - non-ruralValue0.000.0025.00
    Date
    Comment
  • Percentage of rehabilitated roads with newly installed empty ducts to accomodate fiber optic cableValue0.0013.0050.00
    DateDecember 31, 2019December 14, 2023December 31, 2024
    Comment
  • Number of women trained by the municipalities in transport sector rolesValue0.00177.00100.00
    DateDecember 31, 2019December 14, 2023December 31, 2024
    Comment
  • Number of Roma employed in project works of whom 40 percent are Roma womenValue0.0097.00100.00
    DateDecember 31, 2019December 14, 2023December 31, 2024
    Comment
  • National local road inventory and condition database establishedValueNoNoYes
    DateDecember 31, 2019December 14, 2023December 31, 2024
    Comment
  • Development of climate resilient design guidelines for local and low volume roadsValueNoNoYes
    DateDecember 31, 2019December 14, 2023December 31, 2024
    Comment
  • Roma MenValue0.0086.0060.00
    DateDecember 31, 2019December 14, 2023December 31, 2024
    Comment
  • Roma womenValue0.0011.0040.00
    DateDecember 31, 2019December 14, 2023December 31, 2024
    Comment
  • Percentage of municipalities establishing a functioning channel for citizen feedback on the transport sections of capital improvement plansValue0.0050.0060.00
    DateDecember 31, 2019December 14, 2023December 31, 2024
    Comment