Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 78.00 |
P170267
Active
Wenyu Jia
Republic of North Macedonia
August 21, 2019
(as of board presentation)
December 18, 2019
February 24, 2020
US$ 78.00 million
Ministry of Transport and Communications
2020
US$ 78.00 million
N/A
Substantial
September 30, 2026
No
BANK APPROVED
March 1, 2024
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 78.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 78.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 78.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 78.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 1, 2020 | IBRD-90340 | Int Charges | 96,143.47 |
Sep 1, 2020 | IBRD-90340 | Int Charges | 11,813.29 |
Mar 1, 2021 | IBRD-90340 | Int Charges | 73.42 |
Sep 15, 2023 | IBRD-92100 | Int Charges | 1,939.58 |
Sep 15, 2023 | IBRD-92100 | Int Charges | 49,564.85 |
Mar 1, 2021 | IBRD-90340 | Int Charges | 47,356.44 |
Mar 15, 2024 | IBRD-92100 | Int Charges | 50,051.63 |
Mar 15, 2024 | IBRD-92100 | Int Charges | 2,251.15 |
Mar 15, 2024 | IBRD-92100 | Loan Repay | 6,296.36 |
Dec 18, 2019 | IBRD-90340 | Loan Commitment | 78,000,000.00 |
Mar 4, 2021 | IBRD-92100 | Loan Commitment | 44,800,000.00 |
Mar 1, 2021 | IBRD-90340 | Int Charges | 60,169.86 |
Sep 1, 2020 | IBRD-90340 | Int Charges | 5,149.95 |
Mar 1, 2021 | IBRD-90340 | Int Charges | 243.65 |
Feb 24, 2020 | IBRD-90340 | Loan Disb | 189,358.75 |
Feb 24, 2020 | IBRD-90340 | Fee Charges | 189,358.75 |
Oct 3, 2022 | IBRD-90340 | Loan Disb | 1,473,589.40 |
Dec 27, 2022 | IBRD-90340 | Loan Disb | 3,262,610.50 |
Sep 1, 2022 | IBRD-90340 | Int Charges | 24,548.59 |
Sep 1, 2022 | IBRD-90340 | Int Charges | 54,361.20 |
Mar 1, 2022 | IBRD-90340 | Int Charges | 31,647.92 |
Mar 1, 2022 | IBRD-90340 | Int Charges | 45,047.11 |
Aug 5, 2022 | IBRD-90340 | Loan Disb | 49,633.34 |
Mar 14, 2022 | IBRD-90340 | Loan Disb | 3,715,483.50 |
Jun 24, 2022 | IBRD-90340 | Loan Disb | 681,777.00 |
Sep 1, 2023 | IBRD-90340 | Int Charges | 17,334.07 |
Sep 1, 2023 | IBRD-90340 | Int Charges | 1,242,918.50 |
Jul 6, 2023 | IBRD-90340 | Loan Disb | 1,448,591.50 |
Apr 3, 2023 | IBRD-90340 | Loan Disb | 1,449,233.60 |
Mar 1, 2023 | IBRD-90340 | Int Charges | 21,736.51 |
Mar 1, 2023 | IBRD-90340 | Int Charges | 543,120.50 |
Mar 1, 2023 | IBRD-90340 | Int Charges | 8.15 |
Mar 1, 2023 | IBRD-90340 | Int Charges | 1.41 |
Mar 1, 2024 | IBRD-90340 | Int Charges | 562.01 |
Feb 12, 2024 | IBRD-90340 | Loan Disb | -107,671.32 |
Dec 12, 2023 | IBRD-90340 | Loan Disb | 5,291,195.50 |
Jun 3, 2024 | IBRD-90340 | Loan Disb | 2,543,568.20 |
Mar 1, 2024 | IBRD-90340 | Int Charges | 8,418.34 |
Mar 1, 2024 | IBRD-90340 | Int Charges | 12,628.39 |
Mar 1, 2024 | IBRD-90340 | Int Charges | 1,545,118.90 |
Mar 15, 2023 | IBRD-92100 | Int Charges | 45,398.20 |
Mar 15, 2023 | IBRD-92100 | Int Charges | 997.88 |
Sep 13, 2022 | IBRD-92100 | Fee Charges | 94,160.38 |
Sep 13, 2022 | IBRD-92100 | Loan Disb | 94,160.38 |
Jun 10, 2020 | IBRD-90340 | Loan Disb | 113,655.00 |
Jun 23, 2020 | IBRD-90340 | Loan Disb | 17,231,560.00 |
Jul 17, 2020 | IBRD-90340 | Loan Disb | 608,779.30 |
Sep 29, 2020 | IBRD-90340 | Loan Disb | 15,723,449.00 |
Sep 1, 2021 | IBRD-90340 | Int Charges | 34,027.79 |
Sep 1, 2021 | IBRD-90340 | Int Charges | 51,283.74 |
Dec 11, 2020 | IBRD-90340 | Loan Disb | 12,122,500.00 |
Oct 6, 2020 | IBRD-90340 | Loan Disb | 7,804,384.00 |
Aug 27, 2020 | IBRD-90340 | Loan Disb | 563,697.70 |
Aug 27, 2020 | IBRD-90340 | Loan Disb | 643,808.06 |
Sep 1, 2020 | IBRD-90340 | Int Charges | 12.59 |
Name | Review | Date |
---|---|---|
Procurement | Satisfactory | 2025-01-30 |
Financial Management | Moderately Satisfactory | 2025-01-30 |
Progress towards achievement of PDO | Satisfactory | 2025-01-30 |
Monitoring and Evaluation | Moderately Satisfactory | 2025-01-30 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-01-30 |
Project Management | Moderately Satisfactory | 2025-01-30 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of SMEs supported through the CERC (including duplications if same firms used the support in different months or both salaryand contributions support in same month) | Value | 0.00 | 26992.00 | 26992.00 |
Date | March 30, 2020 | December 14, 2023 | November 30, 2020 | |
Comment |
Municipalities utilizing simple asset management methods developed under the project | Value | 0.00 | 0.00 | 65.00 |
Date | December 31, 2019 | December 14, 2023 | December 31, 2024 | |
Comment |
National policy adopted for local roads | Value | No | No | Yes |
Date | December 31, 2019 | December 14, 2023 | July 1, 2024 | |
Comment |
Number of markets and services connected by improved, safe and resilient local roads | Value | 0.00 | 1100.00 | 200.00 |
Date | December 31, 2019 | December 14, 2023 | December 31, 2025 | |
Comment |
Beneficiary satisfaction (gender disaggregated) with project roads (percentage) | Value | N/A | 89.5% | 80 percent express satisfaction |
Date | December 31, 2019 | December 14, 2023 | December 31, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of employees supported through the CERC funding (including duplications if same employees benefited in different months or received both salary and contributions support in same month) | Value | 0.00 | 175161.00 | 175161.00 |
Date | March 30, 2020 | December 14, 2023 | November 30, 2020 | |
Comment |
Road safety audits of road rehabilitation designs | Value | 0.00 | 30.00 | 70.00 |
Date | December 31, 2019 | December 14, 2023 | December 31, 2024 | |
Comment |
Independent technical audits of planning, design, and construction | Value | No | No | Yes |
Date | December 31, 2019 | December 14, 2023 | December 30, 2022 | |
Comment |
Participating municipalities signed MoU with MoTC | Value | 0.00 | 100.00 | 100.00 |
Date | December 31, 2019 | December 14, 2023 | December 31, 2024 | |
Comment |
Community-driven infrastructure pilots implemented | Value | 0.00 | 0.00 | 5.00 |
Date | December 31, 2019 | December 14, 2023 | December 31, 2024 | |
Comment |
Municipalities using improved maintenance contracts | Value | 0.00 | 0.00 | 65.00 |
Date | December 31, 2019 | December 14, 2023 | December 31, 2024 | |
Comment |
Roads rehablitated | Value | 0.00 | 96.00 | 450.00 |
Date | December 31, 2019 | December 14, 2023 | December 31, 2024 | |
Comment |
Roads rehabilitated - rural | Value | 0.00 | 0.00 | 25.00 |
Date | ||||
Comment |
Roads rehabilitated - non-rural | Value | 0.00 | 0.00 | 25.00 |
Date | ||||
Comment |
Percentage of rehabilitated roads with newly installed empty ducts to accomodate fiber optic cable | Value | 0.00 | 13.00 | 50.00 |
Date | December 31, 2019 | December 14, 2023 | December 31, 2024 | |
Comment |
Number of women trained by the municipalities in transport sector roles | Value | 0.00 | 177.00 | 100.00 |
Date | December 31, 2019 | December 14, 2023 | December 31, 2024 | |
Comment |
Number of Roma employed in project works of whom 40 percent are Roma women | Value | 0.00 | 97.00 | 100.00 |
Date | December 31, 2019 | December 14, 2023 | December 31, 2024 | |
Comment |
National local road inventory and condition database established | Value | No | No | Yes |
Date | December 31, 2019 | December 14, 2023 | December 31, 2024 | |
Comment |
Development of climate resilient design guidelines for local and low volume roads | Value | No | No | Yes |
Date | December 31, 2019 | December 14, 2023 | December 31, 2024 | |
Comment |
Roma Men | Value | 0.00 | 86.00 | 60.00 |
Date | December 31, 2019 | December 14, 2023 | December 31, 2024 | |
Comment |
Roma women | Value | 0.00 | 11.00 | 40.00 |
Date | December 31, 2019 | December 14, 2023 | December 31, 2024 | |
Comment |
Percentage of municipalities establishing a functioning channel for citizen feedback on the transport sections of capital improvement plans | Value | 0.00 | 50.00 | 60.00 |
Date | December 31, 2019 | December 14, 2023 | December 31, 2024 | |
Comment |