Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 8.07 |
ITALY, Govt. of (Except for Dev. Coop. Dept. - MOFA) | 20.00 |
Least Developed Countries TF for Climate Change Activities | 0.60 |
Nordic Development Fund (NDF) | 6.80 |
P170376
Active
Pablo Benitez Ponce
Republic of Rwanda
Rwanda
June 14, 2019
(as of board presentation)
October 30, 2020
N/A
US$ 36.40 million
Rubavu District,City Administration of Kigali,Rwanda Environmental Management Authority,Ministry of Infrastructure,Nyagatare District,Musanze District,Local Administrative Entities Development Agency,Muhanga District,Rusizi District,Huye District
2021
US$ 35.47 million
N/A
May 18, 2024
December 31, 2025
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Global Environment Facility (GEF) | 8.07 |
ITALY, Govt. of (Except for Dev. Coop. Dept. - MOFA) | 20.00 |
Least Developed Countries TF for Climate Change Activities | 0.60 |
Nordic Development Fund (NDF) | 6.80 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 35.47 |
Total Project Cost** | 36.40 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2023-11-30 |
Financial Management | Satisfactory | 2023-11-30 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2023-11-30 |
Procurement | Moderately Satisfactory | 2023-11-30 |
Counterpart Funding | Moderately Satisfactory | 2023-11-30 |
Monitoring and Evaluation | Satisfactory | 2023-11-30 |
Project Management | Moderately Satisfactory | 2023-11-30 |