Lima Metropolitano BRT North Extension

Abstract*

The proposed Project is the continuation of Lima Transport Project (P035740) financed by the Bank and implemented from 2003 to 2010. The area of influence of the Project is comprised by four districts in the North Lima: Independencia, Comas, Los Olivos and Carabayllo. This project will benefit: (a) 1,460,000 residents of four districts in North Lima; and (b) result in 150,653 trips per day in North Lima. Low-income users living in the area of influence...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective (PDO) is to improve urban mobility and accessibility to jobs in the area of influence of the Metropolitano BRT North Extension.

Key Details

Project Details

  • P170595

  • Closed

  • Felipe Targa Rodriguez , Yang Chen

  • Republic of Peru

  • Peru

  • May 3, 2019

  • (as of board presentation)

    January 30, 2020

  • June 19, 2020

  • US$ 123.00 million

  • Metropolitan Municipality of Lima with the assistance of EMAPE

  • Latin America and Caribbean

  • 2020

  • US$ 93.00 million

  • N/A

  • March 22, 2024

  • April 30, 2024

  • No

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Borrower/Recipient 30.00
International Bank for Reconstruction and Development 93.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 93.00
IDA Commitment N/A
IBRD + IDA Commitment 93.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 123.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jul 15, 2022 IBRD-90400 Int Charges 8,085.72
Jul 15, 2023 IBRD-90400 Int Charges 112,860.62
Jul 15, 2022 IBRD-90400 Int Charges 52,245.16
Jul 15, 2022 IBRD-90400 Int Charges 240,063.20
Jan 15, 2022 IBRD-90400 Int Charges 68,785.90
Jan 15, 2022 IBRD-90400 Int Charges 871.98
Jan 15, 2022 IBRD-90400 Int Charges 1,851.03
Jan 15, 2022 IBRD-90400 Int Charges 84,177.28
Sep 6, 2022 IBRD-90400 Loan Disb 3,645,993.00
Oct 11, 2022 IBRD-90400 Loan Disb 32,373,564.00
Aug 30, 2020 IBRD-90400 Fee Charges 232,500.00
Jan 15, 2021 IBRD-90400 Int Charges 105,497.58
Dec 18, 2020 IBRD-90400 Loan Disb 40,708.94
Dec 29, 2020 IBRD-90400 Loan Disb 10,657,093.00
Jul 1, 2021 IBRD-90400 Loan Disb 9,093,534.00
Jul 15, 2021 IBRD-90400 Int Charges 1,248.09
Jul 15, 2021 IBRD-90400 Int Charges 3,005.83
Jul 15, 2021 IBRD-90400 Int Charges 101,160.18
Jul 15, 2021 IBRD-90400 Int Charges 41,415.35
Dec 8, 2021 IBRD-90400 Loan Disb 31,066,150.00
Jan 15, 2024 IBRD-90400 Int Charges 2,566,450.20
Jan 15, 2024 IBRD-90400 Int Charges 37,107.67
Jan 15, 2024 IBRD-90400 Int Charges 7,003.66
Jan 15, 2024 IBRD-90400 Loan Repay 5,603,569.50
Dec 29, 2023 IBRD-90400 Loan Disb -0.26
Jan 30, 2020 IBRD-90400 Loan Commitment 93,000,000.00
Jul 15, 2024 IBRD-90400 Loan Repay 6,057,280.50
Jul 15, 2024 IBRD-90400 Int Charges 34,591.24
Jul 15, 2024 IBRD-90400 Int Charges 2,600,120.50
Jul 15, 2024 IBRD-90400 Int Charges 711.34
Jul 15, 2023 IBRD-90400 Int Charges 7,590.79
Jul 15, 2023 IBRD-90400 Int Charges 2,297,923.00
Dec 29, 2023 IBRD-90400 Loan Disb 6,122,956.50
Jan 15, 2023 IBRD-90400 Int Charges 57,717.75
Jan 15, 2023 IBRD-90400 Int Charges 28,552.98
Jan 15, 2023 IBRD-90400 Int Charges 1,425,616.90
Jul 15, 2023 IBRD-90400 Loan Repay 5,603,569.50
Jul 15, 2022 IBRD-90400 Int Charges 14,212.86

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Unsatisfactory 2023-11-08
Procurement Moderately Satisfactory 2023-11-08
Monitoring and Evaluation Satisfactory 2023-11-08
Overall Implementation Progress (IP) Moderately Satisfactory 2023-11-08
Counterpart Funding Satisfactory 2023-11-08
Financial Management Unsatisfactory 2023-11-08
Project Management Moderately Satisfactory 2023-11-08

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT:
Outcomes
Risk to Development Outcome
Bank Performance
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 03-07-2025PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingModerately Unsatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceModerately UnsatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityModestN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • In-vehicle travel time for public transport users between Terminal Chimpu Ocllo and Terminal NaranjalValue31.0031.000.00
    DateMay 31, 2021September 30, 2023
    Comment
  • Average number of jobs reachable by public transportation within a 60-minute, one-way commute in the area of influence of the Metropolitano BRT North Extension (number)Value156595.00156595.000.00
    DateMay 31, 2021September 30, 2023
    Comment
  • Passengers’ trips per day in the Metropolitano BRT North Extension, differentiated by socioeconomic levels and genderValue0.000.0030000.00
    DateMay 31, 2021September 30, 2023December 31, 2021
    Comment
  • Low-income passengers as % of total validations entering the northern terminals of the Metropolitano BRT systemValue31.0031.000.00
    Date
    Comment
  • Women passengers per day as % of total validations on the Metropolitano BRT North Extension (feeder and trunk buses)Value0.000.000.00
    Date
    Comment
  • Women passengers shifting from informal transport modes to the Metropolitano BRT North Extension, as % of total surveyed womenValue0.000.000.00
    Date
    Comment
  • Users satisfied with the service in the northern BRT extension (coverage, reliability, safety, personal security), differentiated by socioeconomic level and genderValue56.0035.000.00
    DateMay 31, 2021September 30, 2023
    Comment
  • Change in % of women passengers satisfied with service in terms of safety, securityValue0.000.000.00
    Date
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Improved the capacity of Protransporte's bus scheduling task teamValueNoNo
    DateMay 31, 2021September 30, 2023
    Comment
  • Physical progress in building segregated BRT lanes on the Metropolitano BRT North ExtensionValue0.0099.900.00
    DateJune 12, 2019September 30, 2023
    Comment
  • Diagnosis and improvement of service plans, route scheduling, and bus dispatch services completedValueNoNo
    Date
    Comment
  • Roads constructedValue0.0010.200.00
    DateMay 31, 2021September 30, 2023
    Comment
  • Roads constructed - non-ruralValue0.000.000.00
    Date
    Comment
  • State-of-the-art software and methodology for scheduling feeder and trunk services implementedValueNoNo
    Date
    Comment
  • Enhanced M&E framework for monitoring operational performance indicators on the Metropolitano BRTValueNoNo
    DateMay 31, 2021September 30, 2023
    Comment
  • Physical progress in constructing passenger stations on the Metropolitano BRT North ExtensionValue0.0099.900.00
    DateJune 12, 2019September 30, 2023
    Comment
  • Operational efficiencies implementedValue0.000.000.00
    DateMay 31, 2021September 30, 2023
    Comment
  • Passenger stations that provide access for people with disabilitiesValue0.000.000.00
    Date
    Comment
  • Updated and upgraded feeder-route service planValue0.000.000.00
    DateMay 31, 2021September 30, 2023
    Comment
  • Physical progress in constructing pedestrian bridges on the Metropolitano BRT North ExtensionValue0.00100.000.00
    DateMay 31, 2021September 30, 2023
    Comment
  • Updated trunk service planValue0.000.000.00
    DateMay 31, 2021September 30, 2023
    Comment
  • Construction of U-turns on the Metropolitano BRT North ExtensionValue0.003.000.00
    DateMay 31, 2021September 30, 2023
    Comment
  • Implementation plan for an expanded, integrated and improved the fare collection system on the entire Metropolitano BRT systemValueNoNo
    DateMay 31, 2021September 30, 2023
    Comment
  • Physical progress of expanding a bus depot on the Metropolitano BRT North ExtensionValue0.0098.000.00
    DateMay 31, 2021September 30, 2023
    Comment
  • Integration and expansion of the existing Metropolitano BRT fare collection system with the North Extension (including feeder routes) completedValueNoNo
    Date
    Comment
  • Carriageway-km covered by installing infrastructure and/or equipment designed to reduce speedsValue0.0010.200.00
    DateMay 31, 2021September 30, 2023
    Comment
  • Share of personalized smart cards as % of total active smart cards for the Metropolitano BRT systemValue0.000.000.00
    Date
    Comment
  • Integrated the Metropolitano BRT North Extension to the BRT system based on the preoperational planValueNoNo
    DateMay 31, 2021September 30, 2023
    Comment
  • Citizens reporting satisfaction with key aspects of consultation process, disintegrated by genderValue0.000.000.00
    DateMay 31, 2021September 30, 2023
    Comment
  • Harmonized Response Protocol to address cases of sexual harassment in the Metropolitano BRT being used by ProtransporteValueNoYes
    DateMay 31, 2021September 30, 2023
    Comment
  • Women employed in the Metropolitano BRTValue13.0013.000.00
    DateMay 31, 2021September 30, 2023
    Comment
  • Construction workers in the Metropolitano BRT North Extension that have signed the code of conduct and attended the code of conducttrainingValue0.00100.000.00
    DateMay 31, 2021September 30, 2023
    Comment
  • Implementation the environmental management measures for the project’s green areas following the specifications of the approved final Vegetation Management PlanValueNoYes
    DateMay 31, 2021September 30, 2023
    Comment