Strengthening Public Financial Management Oversight and Accountability Institutions in Iraq

Abstract*

The project has 3 components and 6 sub-components. The first two components support specific Government reform commitments and benefit lead government institutions/departments acting as the official WBG-EU counterpart for project implementation. Component 3 provides project management and implementation support. Component I : Enhancing Fiscal Accountability: consists of three sub-components: Sub-component I.1. on Payroll reporting and oversight Sub-component...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective is to strengthen institutions and mechanisms of fiscal accountability and oversight at federal and regional levels.

Key Details

Project Details

  • P170704

  • Closed

  • Winston Cole , Mona El-Chami, Salam Almaroof

  • Government of Iraq,Federal Board of Supreme Audit,Iraq Council of Representatives,Kurdistan Parliament,KRG Board of Supreme Audit

  • Iraq

  • October 7, 2019

  • (as of board presentation)

    October 30, 2020

  • June 17, 2021

  • US$ 12.50 million

  • Federal Ministry of Planning,KRG Ministry of Planning,General Secretariat of the Council of Minister,Federal Ministry of Finance

  • Middle East and North Africa

  • 2021

  • US$ 12.50 million

  • N/A

  • July 15, 2024

  • September 13, 2023

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Strengthening PFM Oversight and Accountability Institutions 12.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 12.50
Total Project Cost** 12.50

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Moderately Satisfactory 2023-05-23
Progress towards achievement of PDO Moderately Unsatisfactory 2023-05-23
Financial Management Moderately Unsatisfactory 2023-05-23
Overall Implementation Progress (IP) Moderately Unsatisfactory 2023-05-23
Procurement Moderately Unsatisfactory 2023-05-23
Project Management Moderately Satisfactory 2023-05-23

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT: 03-13-2024
OutcomesHighly Unsatisfactory
Risk to Development Outcome
Bank PerformanceUnsatisfactory
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

INDICATORICR REVIEW: 05-30-2024PROJECT PERFORMANCE ASSESSMENT REPORT:
Outcome RatingHighly Unsatisfactory N/a
Risk To Development OutcomeN/a
Bank PerformanceUnsatisfactoryN/a
Borrower PerformanceN/a
Government PerformanceN/a
Implementing AgencyN/a
Icr QualitySubstantialN/a
M&e QualityNegligibleN/a

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Piloting of centralized payroll management information systemValueNoYesNo
    DateOctober 2, 2020September 13, 2023February 28, 2023
    Comment
  • Increased rating on budget transparency.Value9.0020.009.00
    DateOctober 2, 2020September 13, 2023February 28, 2023
    Comment
  • Completion of risk-based external audit reports.Value0.002.001.00
    DateOctober 2, 2020September 13, 2023February 28, 2023
    Comment
  • Progress in implementing Extractive Industry Transparency Initiative 2019 standards.ValueNoYesYes
    DateOctober 2, 2020September 13, 2023February 28, 2023
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Gender-based budgetingValueNoYesNo
    DateOctober 2, 2020September 13, 2023October 29, 2021
    Comment
  • Strengthening revenue and social auditing.ValueNoYesNo
    DateOctober 2, 2020September 13, 2023October 29, 2021
    Comment
  • Public participation in budget processValue0.0010.000.00
    DateOctober 2, 2020September 13, 2023October 29, 2021
    Comment