Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 400.00 |
P170728
Closed
Alexandra Ortiz , Kjetil Hansen
Ministerio de Hacienda
June 18, 2019
(as of board presentation)
February 27, 2020
May 27, 2020
US$ 0.00 million
National Planning Department
2020
US$ 400.00 million
N/A
Not Applicable
December 31, 2021
BANK APPROVED
September 12, 2023
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 400.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 400.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 400.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | N/A |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 15, 2021 | IBRD-90470 | Int Charges | 0.01 |
Nov 15, 2023 | IBRD-90470 | Int Charges | 5,620,000.00 |
May 15, 2023 | IBRD-90470 | Int Charges | 5,620,000.00 |
Nov 15, 2022 | IBRD-90470 | Int Charges | 5,620,000.00 |
May 15, 2022 | IBRD-90470 | Int Charges | 5,620,000.00 |
Nov 15, 2021 | IBRD-90470 | Int Charges | 5,620,000.00 |
May 15, 2021 | IBRD-90470 | Int Charges | 5,620,000.00 |
Nov 15, 2020 | IBRD-90470 | Int Charges | 1,592,333.40 |
Nov 15, 2020 | IBRD-90470 | Int Charges | 2,989,333.20 |
May 29, 2020 | IBRD-90470 | Loan Disb | 400,000,000.00 |
May 27, 2020 | IBRD-90470 | Fee Charges | 1,000,000.00 |
Sep 24, 2020 | IBRD-90470 | Loan Disb | 400,000,000.00 |
Sep 24, 2020 | IBRD-90470 | Loan Disb | -400,000,000.00 |
Feb 27, 2020 | IBRD-90470 | Loan Commitment | 400,000,000.00 |
May 15, 2024 | IBRD-90470 | Int Charges | 5,620,000.00 |
Name | Review | Date |
---|---|---|
Program Management | Satisfactory | 2021-12-20 |
Overall Implementation Progress (IP) | Satisfactory | 2021-12-20 |
Progress towards achievement of PDO | Satisfactory | 2021-12-20 |
Monitoring and Evaluation | Satisfactory | 2021-12-20 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 01-19-2023 |
---|---|
Outcomes | Moderately Satisfactory |
Risk to Development Outcome | |
Bank Performance | Substantial |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | ICR REVIEW: 09-05-2023 | PROJECT PERFORMANCE ASSESSMENT REPORT: |
---|---|---|
Outcome Rating | Satisfactory | N/a |
Risk To Development Outcome | N/a | |
Bank Performance | Satisfactory | N/a |
Borrower Performance | N/a | |
Government Performance | N/a | |
Implementing Agency | N/a | |
Icr Quality | Substantial | N/a |
M&e Quality | N/a |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of Territorial Pacts subscribed | Value | 0.00 | 10.00 | 4.00 |
Date | May 27, 2020 | December 31, 2021 | December 31, 2021 | |
Comment |
Sub-national entities that manage their own cadaster | Value | 6.00 | 22.00 | 17.00 |
Date | May 27, 2020 | December 31, 2021 | December 31, 2021 | |
Comment |
Share of SGR resources approved for investment projects in each biannual cycle | Value | 62.60 | 82.00 | 79.80 |
Date | May 27, 2020 | December 31, 2021 | December 31, 2021 | |
Comment |
Formalized titles that grant access to land | Value | 850.00 | 17346.00 | 16171.00 |
Date | May 27, 2020 | December 31, 2021 | December 31, 2021 | |
Comment |
Amount of climate and environmental protection-related activities funded with the SGR special allocation | Value | 0.00 | 154200000.00 | 43300000.00 |
Date | May 27, 2020 | December 31, 2021 | December 31, 2021 | |
Comment |
Number of Productive Chain Development Plans formulated | Value | 1.00 | 3.00 | 3.00 |
Date | May 27, 2020 | December 31, 2021 | December 31, 2021 | |
Comment |
Percentage of the budget of the territorial governments (department and municipal governments) formulated and tracked using the newharmonized budget classification system | Value | 0.00 | 97.00 | 100.00 |
Date | May 27, 2020 | December 31, 2021 | December 31, 2021 | |
Comment |
Number of municipalities that have included the new financing instruments in their POTs | Value | 0.00 | 2.00 | 3.00 |
Date | May 27, 2020 | December 31, 2021 | December 31, 2021 | |
Comment |
Percentage of category 5 and 6 municipalities that implement merit-based processes to promote public career employments | Value | 20.00 | 61.00 | 30.00 |
Date | May 27, 2020 | December 31, 2021 | December 31, 2021 | |
Comment |
Number of territorial entities that use the methodological instruments for the incorporation of disaster risk analysis and adaptation to climate change aspects in public infrastructure projects financ | Value | 0.00 | 218.00 | 10.00 |
Date | May 27, 2020 | December 31, 2021 | December 31, 2021 | |
Comment |