Financier | Commitments |
---|---|
Korea Trust Fund to Support Transitions | 1.35 |
P170730
Closed
Pamornrat Tansanguanwong , Patrick Barron
Hilal Ahmar Foundation
May 7, 2019
(as of board presentation)
November 14, 2019
November 15, 2019
US$ 1.35 million
Hilal Ahmar Foundation
2020
US$ 1.35 million
N/A
Substantial
June 30, 2021
Yes
BANK APPROVED
December 15, 2021
Financier | Commitments |
---|---|
Korea Trust Fund to Support Transitions | 1.35 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 1.35 |
Total Project Cost** | 1.35 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Satisfactory | 2021-01-26 |
Progress towards achievement of PDO | Moderately Satisfactory | 2021-01-26 |
Overall | Moderable | 2021-01-26 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: 12-23-2021 |
---|---|
Outcomes | Highly Satisfactory |
Risk to Development Outcome | |
Bank Performance | Highly Satisfactory |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
At least 70 percent of core Individual project beneficiaries (former combatants) satisfied with the program approach and services provided | Value | 0.00 | 70.00 | 99.00 |
Date | November 30, 2019 | June 30, 2021 | June 30, 2021 | |
Comment |
Scalable case management system established for provision of services and opportunities to ex-combatants | Value | No case management system | Operational CMS documented in manuals | CMS established |
Date | November 30, 2019 | June 30, 2021 | June 30, 2021 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Livelihood prospects of IPBs increased through access to opportunities and services provided by the project | Value | 0.00 | 80.00 | 99.00 |
Date | November 30, 2019 | June 30, 2021 | June 30, 2021 | |
Comment |
At least 70 percent of core IPBs takes part in project supported or other relevant community development activities | Value | 0.00 | 70.00 | 88.00 |
Date | November 30, 2019 | June 30, 2021 | June 30, 2021 | |
Comment |
Coordinated services provided to all IPBs referred to government institutions | Value | 0.00 | 80.00 | 100.00 |
Date | November 30, 2019 | June 30, 2021 | June 30, 2021 | |
Comment |
Government adherence to the agreed principles and standard operating procedures | Value | 0.00 | 100.00 | 100.00 |
Date | November 30, 2019 | June 30, 2021 | June 30, 2021 | |
Comment |
At least 70 percent majority of population in villages satisfied with program approach | Value | 0.00 | 70.00 | 100.00 |
Date | November 30, 2019 | June 30, 2021 | June 30, 2021 | |
Comment |