Financier | Commitments |
---|---|
IDA Credit | 45.00 |
P170860
Active
Joanna Moody , Malaika Becoulet
Saint Lucia
June 30, 2019
(as of board presentation)
May 28, 2020
October 16, 2020
US$ 45.00 million
Saint Lucia Air and Sea Ports Authority
2020
US$ 45.00 million
N/A
Moderate
June 30, 2027
Yes
BANK APPROVED
January 4, 2024
Financier | Commitments |
---|---|
IDA Credit | 45.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 45.00 |
IBRD + IDA Commitment | 45.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 45.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 28, 2020 | IDA-66530 | Loan Commitment | 45,000,000.00 |
Oct 8, 2021 | IDA-66530 | Int Charges | 3,870.06 |
Oct 8, 2021 | IDA-66530 | Int Charges | 3,870.06 |
May 11, 2021 | IDA-66530 | Loan Disb | 765,505.30 |
Apr 1, 2022 | IDA-66530 | Int Charges | 4,975.80 |
Apr 1, 2022 | IDA-66530 | Int Charges | 4,975.80 |
Apr 5, 2023 | IDA-66530 | Int Charges | 207.20 |
Apr 5, 2023 | IDA-66530 | Int Charges | 207.20 |
Apr 5, 2023 | IDA-66530 | Int Charges | 17,340.15 |
Apr 5, 2023 | IDA-66530 | Int Charges | 17,340.15 |
Oct 5, 2022 | IDA-66530 | Int Charges | 4,975.80 |
Oct 5, 2022 | IDA-66530 | Int Charges | 4,975.80 |
Dec 14, 2022 | IDA-66530 | Loan Disb | 1,993,419.90 |
Sep 23, 2022 | IDA-66530 | Loan Disb | 717,230.70 |
Aug 15, 2023 | IDA-66530 | Loan Disb | 72,934.59 |
Nov 30, 2023 | IDA-66530 | Loan Disb | 1,975,316.80 |
Sep 15, 2023 | IDA-66530 | Loan Disb | 1,402,611.60 |
Aug 18, 2023 | IDA-66530 | Loan Disb | 447,020.30 |
Apr 3, 2024 | IDA-66530 | Int Charges | 1,625.66 |
Apr 3, 2024 | IDA-66530 | Int Charges | 1,625.66 |
Apr 3, 2024 | IDA-66530 | Int Charges | 43,722.72 |
Apr 3, 2024 | IDA-66530 | Int Charges | 43,722.72 |
Oct 3, 2023 | IDA-66530 | Int Charges | 22,595.04 |
Oct 3, 2023 | IDA-66530 | Int Charges | 22,595.04 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2024-12-21 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-12-21 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-12-21 |
Project Management | Moderately Satisfactory | 2024-12-21 |
Financial Management | Satisfactory | 2024-12-21 |
Procurement | Moderately Unsatisfactory | 2024-12-21 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
UVF runway in compliance with additional ICAO standards/requirements | Value | 0.00 | 0.00 | 4.00 |
Date | March 31, 2020 | June 15, 2023 | June 30, 2027 | |
Comment |
Change in discharge capacity of the runway drainage system at UVF | Value | 0.00 | 0.00 | 100.00 |
Date | March 31, 2020 | June 15, 2023 | June 30, 2027 | |
Comment |
Modernization of air navigation systems and oversight | Value | 0.00 | 0.00 | 3.00 |
Date | March 31, 2020 | June 15, 2023 | June 30, 2027 | |
Comment |
Regional change in airspace area covered by globally standardized air traffic monitoring system | Value | 0.00 | 0.00 | 100.00 |
Date | March 31, 2020 | June 15, 2023 | June 30, 2027 | |
Comment |
Regional capacity building program on air traffic control and management prepared and endorsed | Value | No | No | Yes |
Date | March 31, 2020 | June 15, 2023 | June 30, 2027 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
UVF runway rehabilitated | Value | 0.00 | 0.00 | 100.00 |
Date | October 22, 2019 | June 15, 2023 | June 30, 2027 | |
Comment |
ILS approach installed for UVF Runway | Value | No | No | Yes |
Date | March 31, 2020 | June 15, 2023 | June 30, 2027 | |
Comment |
Air Traffic Controllers trained on updated equipment and aeronautical charts | Value | No | No | Yes |
Date | March 31, 2020 | June 15, 2023 | June 30, 2026 | |
Comment |
Percentage of grievances received by project staff that are addressed according to the agreed GRM procedures and the results communicated back to the involved stakeholders | Value | 0.00 | 0.00 | 100.00 |
Date | March 31, 2020 | June 15, 2023 | June 30, 2027 | |
Comment |
Shoulders constructed along the UVF runway | Value | 0.00 | 0.00 | 100.00 |
Date | March 31, 2020 | June 15, 2023 | June 30, 2027 | |
Comment |
ADS-B monitors installed for UVF and SLU | Value | No | No | Yes |
Date | March 31, 2020 | June 15, 2023 | June 30, 2027 | |
Comment |
Number of stakeholder meetings held to discuss the decisions and/or actions taken based on beneficiaries’ feedback. | Value | 0.00 | 2.00 | 12.00 |
Date | March 31, 2020 | June 15, 2023 | June 30, 2027 | |
Comment |
Percentage of female participants of training | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
LED lighting system installed for UVF runway | Value | No | No | Yes |
Date | March 31, 2020 | June 15, 2023 | June 30, 2027 | |
Comment |
Number in Saint Lucia-based aircraft equipped with ADS-B | Value | 0.00 | 0.00 | 3.00 |
Date | March 31, 2020 | June 15, 2023 | June 30, 2027 | |
Comment |
Gap analysis conducted on airport operational capacity | Value | No | No | Yes |
Date | March 31, 2020 | June 15, 2023 | June 30, 2027 | |
Comment |
Runway End Safety Areas constructed on the UVF runway | Value | 0.00 | 0.00 | 100.00 |
Date | March 31, 2020 | June 15, 2023 | June 30, 2027 | |
Comment |
UVF Aeronautical Charts updated | Value | No | No | Yes |
Date | March 31, 2020 | December 7, 2023 | June 30, 2027 | |
Comment |
Change in number of women hired for middle-skilled jobs by SLASPA | Value | 0.00 | 0.00 | 50.00 |
Date | March 31, 2020 | June 15, 2023 | June 30, 2027 | |
Comment |
Airfield drainages improved at UVF | Value | No | No | Yes |
Date | March 31, 2020 | June 15, 2023 | June 30, 2027 | |
Comment |
Semi-annual meetings held with stakeholders to discuss their suggestions and related actions taken by the project | Value | 0.00 | 5.00 | 12.00 |
Date | March 31, 2020 | December 14, 2023 | June 30, 2027 | |
Comment |
Airfield resilience plan prepared for UVF | Value | No | No | Yes |
Date | March 31, 2020 | June 15, 2023 | June 30, 2027 | |
Comment |
Share of women included in the medium-skills training | Value | 0.00 | 0.00 | 30.00 |
Date | March 31, 2020 | June 15, 2023 | June 30, 2027 | |
Comment |
Firefighters control room upgraded at UVF | Value | No | No | Yes |
Date | March 31, 2020 | June 15, 2023 | June 30, 2027 | |
Comment |
Annual passenger volume of UVF | Value | 830000.00 | 830000.00 | 1000000.00 |
Date | December 31, 2018 | June 15, 2023 | June 30, 2027 | |
Comment |