Financier | Commitments |
---|---|
FRANCE: French Agency for Development | 62.50 |
International Bank for Reconstruction and Development | 62.50 |
P170868
Active
Tamara Mihaljcic , Daniel Pulido, Mercedes Gutierrez Ferrandiz
Republic of Serbia
Serbia
November 18, 2019
(as of board presentation)
March 17, 2021
September 24, 2021
US$ 125.00 million
Serbia Railways Infrastructure,Ministry of Construction, Transport and Infrastructure,Railways Directorate,Serbia Voz,Serbia Cargo
2021
US$ 125.00 million
N/A
Substantial
December 31, 2026
No
BANK APPROVED
October 23, 2023
Financier | Commitments |
---|---|
FRANCE: French Agency for Development | 62.50 |
International Bank for Reconstruction and Development | 62.50 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 62.50 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 62.50 |
Lending Instrument | |
---|---|
Grant Amount | 62.50 |
Total Project Cost** | 125.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 17, 2021 | IBRD-92210 | Loan Commitment | 62,500,000.00 |
Jun 15, 2023 | IBRD-92210 | Int Charges | 53,656.19 |
Dec 15, 2022 | IBRD-92210 | Int Charges | 4,627.94 |
Dec 12, 2023 | IBRD-92210 | Loan Disb | 1,079,600.00 |
Dec 15, 2023 | IBRD-92210 | Int Charges | 77,427.60 |
Dec 15, 2023 | IBRD-92210 | Int Charges | 65,796.48 |
Jun 15, 2024 | IBRD-92210 | Int Charges | 373.84 |
Jun 15, 2024 | IBRD-92210 | Int Charges | 62,696.21 |
Jun 15, 2024 | IBRD-92210 | Int Charges | 21.98 |
Jun 15, 2024 | IBRD-92210 | Int Charges | 103,251.45 |
Jun 15, 2024 | IBRD-92210 | Loan Repay | 245,507.33 |
Jun 18, 2024 | IBRD-92210 | Loan Disb | 2,679,500.00 |
Jun 15, 2022 | IBRD-92210 | Int Charges | 574.22 |
Dec 15, 2022 | IBRD-92210 | Loan Disb | 2,124,900.00 |
Dec 15, 2021 | IBRD-92210 | Int Charges | 62,524.93 |
Dec 15, 2021 | IBRD-92210 | Int Charges | 36.84 |
Dec 23, 2021 | IBRD-92210 | Loan Disb | 1,132,400.00 |
Jun 15, 2022 | IBRD-92210 | Int Charges | 65,226.96 |
Oct 5, 2021 | IBRD-92210 | Fee Charges | 147,829.88 |
Oct 5, 2021 | IBRD-92210 | Loan Disb | 147,829.88 |
Jun 15, 2023 | IBRD-92210 | Int Charges | 64,701.46 |
Dec 15, 2022 | IBRD-92210 | Int Charges | 66,415.25 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2024-12-03 |
Project Management | Satisfactory | 2024-12-03 |
Monitoring and Evaluation | Satisfactory | 2024-12-03 |
Progress towards achievement of PDO | Satisfactory | 2024-12-03 |
Financial Management | Satisfactory | 2024-12-03 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-12-03 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
PrDO: Increase national freight rail market share by 10 percent ton-km (from 22.5 percent to 24.74 percent of the market) | Value | 22.50 | 22.50 | 24.74 |
Date | December 31, 2019 | October 13, 2023 | December 31, 2032 | |
Comment |
PrDO: Reduce fatality rates on the rail network by 23 percent (fatalities per train-kilometers) (from 3.56 to 2.74 fatalities per train-kilometers) | Value | 3.56 | 3.56 | 2.74 |
Date | December 31, 2019 | October 13, 2023 | December 31, 2032 | |
Comment |
Phase 1: Improve financial transparency in IZS, SC, SV, and RD | Value | No | No | Yes |
Date | September 1, 2020 | October 13, 2023 | December 31, 2032 | |
Comment |
Phase 1: Increase average train speeds on rehabilitated sections (kmh) | Value | 82.00 | 82.00 | 100.00 |
Date | September 1, 2020 | October 13, 2023 | December 31, 2032 | |
Comment |
Contingency plan under Safety Management System is operationalized | Value | No | No | Yes |
Date | September 1, 2020 | October 13, 2023 | December 31, 2032 | |
Comment |
Reduce accidents at level crossings per year by 25 percent (from 43 to 32 crashes per year) | Value | 43.00 | 43.00 | 32.00 |
Date | December 31, 2019 | October 13, 2023 | December 31, 2032 | |
Comment |
New hiring/recruitment procedures are based on the HR strategy | Value | No | No | Yes |
Date | September 1, 2020 | October 13, 2023 | December 31, 2032 | |
Comment |
PrDO: Increase the national passenger rail market share by 30 percent (pass-km) (from 3.5 percent to 4.63 percent of the market) | Value | 3.50 | 3.50 | 4.63 |
Date | December 31, 2019 | October 13, 2023 | December 31, 2032 | |
Comment |
PrDO: Safety risk assessment operationalized and implemented | Value | No | No | Yes |
Date | September 24, 2020 | October 13, 2023 | December 31, 2032 | |
Comment |
IZS rehabilitation plans are based on outputs from Asset Management System | Value | No | No | Yes |
Date | September 1, 2020 | October 13, 2023 | December 31, 2032 | |
Comment |
Increase network utilization by 5 percent (from 8.10 and to 8.5 daily train-kilometers per network track kilometer) | Value | 8.10 | 8.10 | 8.50 |
Date | December 31, 2019 | October 13, 2023 | December 31, 2032 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Phase 1: Action plan for IRS implementation delivered | Value | No | No | Yes |
Date | September 1, 2020 | October 13, 2023 | December 31, 2027 | |
Comment |
Phase 1: Legal and regulatory instruments developed to modernize RD's role as regulator | Value | No | No | Yes |
Date | September 1, 2020 | October 13, 2023 | December 31, 2027 | |
Comment |
Phase 1: Number of level crossings upgraded | Value | 0.00 | 0.00 | 150.00 |
Date | September 1, 2020 | October 13, 2023 | December 31, 2027 | |
Comment |
Phase 1: IRS demonstration project implemented and documented | Value | No | No | Yes |
Date | September 1, 2020 | October 13, 2023 | December 31, 2027 | |
Comment |
Phase 1: Recommendations delivered for IZS, SC and SV to adopt commercially oriented, independent, and modern management | Value | No | No | Yes |
Date | September 1, 2020 | October 13, 2023 | December 31, 2027 | |
Comment |
Phase 1: Number of measurement stations installed | Value | 0.00 | 0.00 | 4.00 |
Date | September 1, 2020 | October 13, 2023 | December 31, 2027 | |
Comment |
Phase 1: SMS action plan is delivered | Value | No | No | Yes |
Date | September 1, 2020 | October 13, 2023 | December 31, 2027 | |
Comment |
Phase 1: Recommendations delivered for SC to adopt modernized business processes | Value | No | No | Yes |
Date | September 1, 2020 | October 13, 2023 | December 31, 2027 | |
Comment |
Phase 1: Selected SMS and resilience interventions are implemented | Value | No | No | Yes |
Date | September 1, 2020 | October 13, 2023 | December 31, 2027 | |
Comment |
Phase 1: HR strategies for RD, IZS, SC and SV delivered and implemented | Value | No | No | Yes |
Date | September 1, 2020 | October 13, 2023 | December 31, 2027 | |
Comment |
Phase 1: Second stage of main railway station in Belgrade center constructed | Value | No | No | Yes |
Date | September 1, 2020 | October 13, 2023 | December 31, 2027 | |
Comment |
Phase 1: Training programs in RD, IZS, SC and SV implemented | Value | No | No | Yes |
Date | September 1, 2020 | October 13, 2023 | December 1, 2027 | |
Comment |
Phase 1: Delivery of a plan for achieving integration of components of asset management system | Value | No | No | Yes |
Date | September 1, 2020 | October 13, 2023 | December 31, 2027 | |
Comment |
Phase 1: Study on integration of railways with territorial development delivered | Value | No | No | Yes |
Date | September 1, 2020 | October 13, 2023 | December 31, 2027 | |
Comment |
Phase 1: PhD scholarships in rail-related subjects awarded to females | Value | 0.00 | 0.00 | 3.00 |
Date | September 1, 2020 | October 13, 2023 | December 31, 2027 | |
Comment |
Phase 1: Delivery of fully functioning asset management system | Value | No | No | Yes |
Date | September 1, 2020 | October 13, 2023 | December 31, 2027 | |
Comment |
Phase 1: Pilot projects on integrated rail-territorial development implemented | Value | No | No | Yes |
Date | September 1, 2020 | October 13, 2023 | December 31, 2027 | |
Comment |
Phase 1: Gender Action Plans adopted by RD, IZS, SC and SV | Value | No | No | Yes |
Date | September 1, 2020 | October 13, 2023 | December 31, 2027 | |
Comment |
Phase 1: Equipment for maintenance and rehabilitation of railway assets operational | Value | No | No | Yes |
Date | November 20, 2020 | October 13, 2023 | December 31, 2026 | |
Comment |
Phase 1: Study on modal shift delivered | Value | No | No | Yes |
Date | September 1, 2020 | October 13, 2023 | December 31, 2027 | |
Comment |
Phase 1: Percentage of beneficiaries reporting project established effective engagement processes | Value | 0.00 | 0.00 | 70.00 |
Date | September 1, 2020 | October 13, 2023 | December 31, 2027 | |
Comment |
Phase 1: Analysis and road map for ownership structure of SC delivered | Value | No | No | Yes |
Date | September 1, 2020 | October 13, 2023 | December 31, 2027 | |
Comment |
Phase 1: Software for Timetable construction for IZS implemented | Value | No | No | Yes |
Date | November 20, 2020 | October 13, 2023 | December 31, 2026 | |
Comment |
Phase 1: Number of staff trained in safety risk assessment in RD, IZS, and SV | Value | 0.00 | 0.00 | 10.00 |
Date | September 24, 2020 | October 13, 2023 | December 31, 2027 | |
Comment |
Phase 1: Km of tracks rehabilitated | Value | 0.00 | 0.00 | 37.10 |
Date | September 1, 2020 | October 13, 2023 | December 31, 2027 | |
Comment |