Skip to Main Navigation

Serbia Railway Sector Modernization

Abstract*

Phase 1 will focus on upgrading existing rail infrastructure and establishing the enabling environment for further corporatization of the railway companies and operationalization of sector reforms. This will be achieved through implementation of the following three components: 1. Component 1. Infrastructure Investments and Asset Management (US$ 107.5) 2. Component 2. Institutional Strengthening and Project Management (US$ 10.14) 3. Component 3. Railway...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Phase 1 Project Development Objective: To enhance the efficiency and safety of existing railway assets and improve governance and institutional capacity of the railway sector.

Key Details

Project Details

  • P170868

  • Active

  • Tamara Mihaljcic , Daniel Pulido, Mercedes Gutierrez Ferrandiz

  • Republic of Serbia

  • Serbia

  • November 18, 2019

  • (as of board presentation)

    March 17, 2021

  • September 24, 2021

  • US$ 125.00 million

  • Serbia Railways Infrastructure,Ministry of Construction, Transport and Infrastructure,Railways Directorate,Serbia Voz,Serbia Cargo

  • Europe and Central Asia

  • 2021

  • US$ 125.00 million

  • N/A

  • Substantial

  • December 31, 2026

  • No

  • BANK APPROVED

  • October 23, 2023

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
FRANCE: French Agency for Development 62.50
International Bank for Reconstruction and Development 62.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 62.50
IDA Commitment N/A
IBRD + IDA Commitment 62.50
Lending Instrument
Grant Amount 62.50
Total Project Cost** 125.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Mar 17, 2021 IBRD-92210 Loan Commitment 62,500,000.00
Jun 15, 2023 IBRD-92210 Int Charges 53,656.19
Dec 15, 2022 IBRD-92210 Int Charges 4,627.94
Dec 12, 2023 IBRD-92210 Loan Disb 1,079,600.00
Dec 15, 2023 IBRD-92210 Int Charges 77,427.60
Dec 15, 2023 IBRD-92210 Int Charges 65,796.48
Jun 15, 2024 IBRD-92210 Int Charges 373.84
Jun 15, 2024 IBRD-92210 Int Charges 62,696.21
Jun 15, 2024 IBRD-92210 Int Charges 21.98
Jun 15, 2024 IBRD-92210 Int Charges 103,251.45
Jun 15, 2024 IBRD-92210 Loan Repay 245,507.33
Jun 18, 2024 IBRD-92210 Loan Disb 2,679,500.00
Jun 15, 2022 IBRD-92210 Int Charges 574.22
Dec 15, 2022 IBRD-92210 Loan Disb 2,124,900.00
Dec 15, 2021 IBRD-92210 Int Charges 62,524.93
Dec 15, 2021 IBRD-92210 Int Charges 36.84
Dec 23, 2021 IBRD-92210 Loan Disb 1,132,400.00
Jun 15, 2022 IBRD-92210 Int Charges 65,226.96
Oct 5, 2021 IBRD-92210 Fee Charges 147,829.88
Oct 5, 2021 IBRD-92210 Loan Disb 147,829.88
Jun 15, 2023 IBRD-92210 Int Charges 64,701.46
Dec 15, 2022 IBRD-92210 Int Charges 66,415.25

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2024-12-03
Project Management Satisfactory 2024-12-03
Monitoring and Evaluation Satisfactory 2024-12-03
Progress towards achievement of PDO Satisfactory 2024-12-03
Financial Management Satisfactory 2024-12-03
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-03

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • PrDO: Increase national freight rail market share by 10 percent ton-km (from 22.5 percent to 24.74 percent of the market)Value22.5022.5024.74
    DateDecember 31, 2019October 13, 2023December 31, 2032
    Comment
  • PrDO: Reduce fatality rates on the rail network by 23 percent (fatalities per train-kilometers) (from 3.56 to 2.74 fatalities per train-kilometers)Value3.563.562.74
    DateDecember 31, 2019October 13, 2023December 31, 2032
    Comment
  • Phase 1: Improve financial transparency in IZS, SC, SV, and RDValueNoNoYes
    DateSeptember 1, 2020October 13, 2023December 31, 2032
    Comment
  • Phase 1: Increase average train speeds on rehabilitated sections (kmh)Value82.0082.00100.00
    DateSeptember 1, 2020October 13, 2023December 31, 2032
    Comment
  • Contingency plan under Safety Management System is operationalizedValueNoNoYes
    DateSeptember 1, 2020October 13, 2023December 31, 2032
    Comment
  • Reduce accidents at level crossings per year by 25 percent (from 43 to 32 crashes per year)Value43.0043.0032.00
    DateDecember 31, 2019October 13, 2023December 31, 2032
    Comment
  • New hiring/recruitment procedures are based on the HR strategyValueNoNoYes
    DateSeptember 1, 2020October 13, 2023December 31, 2032
    Comment
  • PrDO: Increase the national passenger rail market share by 30 percent (pass-km) (from 3.5 percent to 4.63 percent of the market)Value3.503.504.63
    DateDecember 31, 2019October 13, 2023December 31, 2032
    Comment
  • PrDO: Safety risk assessment operationalized and implementedValueNoNoYes
    DateSeptember 24, 2020October 13, 2023December 31, 2032
    Comment
  • IZS rehabilitation plans are based on outputs from Asset Management SystemValueNoNoYes
    DateSeptember 1, 2020October 13, 2023December 31, 2032
    Comment
  • Increase network utilization by 5 percent (from 8.10 and to 8.5 daily train-kilometers per network track kilometer)Value8.108.108.50
    DateDecember 31, 2019October 13, 2023December 31, 2032
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Phase 1: Action plan for IRS implementation deliveredValueNoNoYes
    DateSeptember 1, 2020October 13, 2023December 31, 2027
    Comment
  • Phase 1: Legal and regulatory instruments developed to modernize RD's role as regulatorValueNoNoYes
    DateSeptember 1, 2020October 13, 2023December 31, 2027
    Comment
  • Phase 1: Number of level crossings upgradedValue0.000.00150.00
    DateSeptember 1, 2020October 13, 2023December 31, 2027
    Comment
  • Phase 1: IRS demonstration project implemented and documentedValueNoNoYes
    DateSeptember 1, 2020October 13, 2023December 31, 2027
    Comment
  • Phase 1: Recommendations delivered for IZS, SC and SV to adopt commercially oriented, independent, and modern managementValueNoNoYes
    DateSeptember 1, 2020October 13, 2023December 31, 2027
    Comment
  • Phase 1: Number of measurement stations installedValue0.000.004.00
    DateSeptember 1, 2020October 13, 2023December 31, 2027
    Comment
  • Phase 1: SMS action plan is deliveredValueNoNoYes
    DateSeptember 1, 2020October 13, 2023December 31, 2027
    Comment
  • Phase 1: Recommendations delivered for SC to adopt modernized business processesValueNoNoYes
    DateSeptember 1, 2020October 13, 2023December 31, 2027
    Comment
  • Phase 1: Selected SMS and resilience interventions are implementedValueNoNoYes
    DateSeptember 1, 2020October 13, 2023December 31, 2027
    Comment
  • Phase 1: HR strategies for RD, IZS, SC and SV delivered and implementedValueNoNoYes
    DateSeptember 1, 2020October 13, 2023December 31, 2027
    Comment
  • Phase 1: Second stage of main railway station in Belgrade center constructedValueNoNoYes
    DateSeptember 1, 2020October 13, 2023December 31, 2027
    Comment
  • Phase 1: Training programs in RD, IZS, SC and SV implementedValueNoNoYes
    DateSeptember 1, 2020October 13, 2023December 1, 2027
    Comment
  • Phase 1: Delivery of a plan for achieving integration of components of asset management systemValueNoNoYes
    DateSeptember 1, 2020October 13, 2023December 31, 2027
    Comment
  • Phase 1: Study on integration of railways with territorial development deliveredValueNoNoYes
    DateSeptember 1, 2020October 13, 2023December 31, 2027
    Comment
  • Phase 1: PhD scholarships in rail-related subjects awarded to femalesValue0.000.003.00
    DateSeptember 1, 2020October 13, 2023December 31, 2027
    Comment
  • Phase 1: Delivery of fully functioning asset management systemValueNoNoYes
    DateSeptember 1, 2020October 13, 2023December 31, 2027
    Comment
  • Phase 1: Pilot projects on integrated rail-territorial development implementedValueNoNoYes
    DateSeptember 1, 2020October 13, 2023December 31, 2027
    Comment
  • Phase 1: Gender Action Plans adopted by RD, IZS, SC and SVValueNoNoYes
    DateSeptember 1, 2020October 13, 2023December 31, 2027
    Comment
  • Phase 1: Equipment for maintenance and rehabilitation of railway assets operationalValueNoNoYes
    DateNovember 20, 2020October 13, 2023December 31, 2026
    Comment
  • Phase 1: Study on modal shift deliveredValueNoNoYes
    DateSeptember 1, 2020October 13, 2023December 31, 2027
    Comment
  • Phase 1: Percentage of beneficiaries reporting project established effective engagement processesValue0.000.0070.00
    DateSeptember 1, 2020October 13, 2023December 31, 2027
    Comment
  • Phase 1: Analysis and road map for ownership structure of SC deliveredValueNoNoYes
    DateSeptember 1, 2020October 13, 2023December 31, 2027
    Comment
  • Phase 1: Software for Timetable construction for IZS implementedValueNoNoYes
    DateNovember 20, 2020October 13, 2023December 31, 2026
    Comment
  • Phase 1: Number of staff trained in safety risk assessment in RD, IZS, and SVValue0.000.0010.00
    DateSeptember 24, 2020October 13, 2023December 31, 2027
    Comment
  • Phase 1: Km of tracks rehabilitatedValue0.000.0037.10
    DateSeptember 1, 2020October 13, 2023December 31, 2027
    Comment