Financier | Commitments |
---|---|
SWITZERLAND, Gov. of: Fed. Off. for For. Eeo. Affrs. (FOFEA) | 3.30 |
International Bank for Reconstruction and Development | 75.00 |
Albania NWSSSM | 3.00 |
Borrower/Recipient | 60.00 |
P170891
Active
Camilo Lombana Cordoba , Sven Schlumpberger
Republic of Albania
January 29, 2020
(as of board presentation)
May 12, 2022
May 10, 2023
US$ 141.30 million
National Agency of Water Supply, Sewerage and Waste Infrastructure (AKUM),Ministry of Infrastructure and Energy
2022
US$ 81.30 million
N/A
Substantial
December 31, 2027
Yes
BANK APPROVED
June 5, 2024
Financier | Commitments |
---|---|
SWITZERLAND, Gov. of: Fed. Off. for For. Eeo. Affrs. (FOFEA) | 3.30 |
International Bank for Reconstruction and Development | 75.00 |
Albania NWSSSM | 3.00 |
Borrower/Recipient | 60.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 75.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 75.00 |
Lending Instrument | |
---|---|
Grant Amount | 6.30 |
Total Project Cost** | 141.30 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jul 15, 2023 | IBRD-93730 | Int Charges | 78,528.44 |
Sep 8, 2023 | IBRD-93730 | Loan Disb | 2,889,270.00 |
May 10, 2023 | IBRD-93730 | Loan Disb | 184,292.64 |
May 10, 2023 | IBRD-93730 | Fee Charges | 184,292.64 |
Jan 15, 2024 | IBRD-93730 | Int Charges | 1,061.31 |
May 12, 2022 | IBRD-93730 | Loan Commitment | 75,000,000.00 |
Jan 15, 2024 | IBRD-93730 | Int Charges | 89,974.09 |
Jan 15, 2024 | IBRD-93730 | Int Charges | 51,543.66 |
Jul 15, 2024 | IBRD-93730 | Int Charges | 87,388.66 |
Jul 15, 2024 | IBRD-93730 | Int Charges | 71,348.89 |
Jan 15, 2024 | IBRD-93730 | Int Charges | 83.24 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2025-01-17 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-01-17 |
Monitoring and Evaluation | Satisfactory | 2025-01-17 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
New Business Plan guideline for tariff reviews approved by ERRU | Value | No | No | Yes |
Date | February 7, 2022 | September 14, 2022 | January 29, 2027 | |
Comment |
Minimum number of new functional connections providing safe and reliable water services in vulnerable households | Value | 0.00 | 0.00 | 3000.00 |
Date | November 9, 2020 | September 14, 2022 | December 31, 2027 | |
Comment |
Improved financial viability of the WSS sector (as reflected in National Aggregated Score for Direct Operating Cost Coverage) | Value | 81.20 | 60.00 | 91.20 |
Date | November 9, 2020 | September 14, 2022 | December 31, 2027 | |
Comment |
Improved sector financing instruments and incentives for improved performance adopted | Value | No | No | Yes |
Date | February 7, 2022 | September 14, 2022 | December 31, 2027 | |
Comment |
People provided with access to improved water sources | Value | 0.00 | 0.00 | 40000.00 |
Date | November 9, 2020 | September 14, 2022 | December 31, 2027 | |
Comment |
Improved continuity of water supply services (number of urban areas with minimum 18 hours of water supply) | Value | 15.00 | 15.00 | 35.00 |
Date | November 9, 2020 | September 14, 2022 | December 31, 2027 | |
Comment |
Percentage of Utilities meeting at least 75 percent of their targets in Performance Agreements | Value | 0.00 | 0.00 | 90.00 |
Date | December 30, 2022 | September 14, 2022 | December 31, 2027 | |
Comment |
People provided with access to improved water sources - Female (RMS requirement) | Value | 0.00 | 0.00 | 20000.00 |
Date | May 10, 2023 | May 10, 2023 | January 29, 2027 | |
Comment |
People provided with access to improved water sources - rural | Value | 0.00 | 0.00 | 32000.00 |
Date | May 10, 2023 | May 10, 2023 | January 29, 2027 | |
Comment |
People provided with access to improved water sources - urban | Value | 0.00 | 0.00 | 8000.00 |
Date | May 10, 2023 | May 10, 2023 | January 29, 2027 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
National Certification Program launched | Value | No | No | Yes |
Date | February 7, 2022 | September 9, 2022 | December 31, 2027 | |
Comment |
Guidelines for on-site sanitation issued by AKUM | Value | No | No | Yes |
Date | February 7, 2022 | September 9, 2022 | December 31, 2027 | |
Comment |
Percentage of WSS Utilities submitting Business Plans to ERRU for approval | Value | 0.00 | 0.00 | 60.00 |
Date | February 7, 2022 | September 9, 2022 | December 31, 2025 | |
Comment |
Utility Corporate Governance and Citizen Engagement requirements approved (PAP measure) | Value | No | No | Yes |
Date | February 7, 2022 | September 9, 2022 | December 31, 2027 | |
Comment |
Number of WSS Utilities/Municipalities undertaking community outreach and WASH IEC and behavior change communication (BCC) campaigns with households of Roma minorities and other vulnerable groups | Value | 0.00 | 0.00 | 5.00 |
Date | November 9, 2020 | September 9, 2022 | December 31, 2026 | |
Comment |
Percentage of WSS Utilities receiving investment allocation based on eligibility and performance | Value | 0.00 | 0.00 | 60.00 |
Date | February 7, 2022 | September 9, 2022 | December 31, 2025 | |
Comment |
New Performance Monitoring/Benchmarking system established and operationalized (and annual report with key KPIs in public domain) | Value | No | No | Yes |
Date | February 7, 2022 | September 9, 2022 | December 31, 2027 | |
Comment |
Percentage of WSS utilities with agreed operational staff certified as per regulations on certification | Value | 0.00 | 0.00 | 70.00 |
Date | February 7, 2022 | September 9, 2022 | December 31, 2027 | |
Comment |
Number of energy efficiency audits undertaken in WSS Utilities | Value | 0.00 | 0.00 | 12.00 |
Date | February 7, 2022 | September 9, 2022 | December 31, 2027 | |
Comment |
Number of WSS utilities/municipalities from within the 10 largest energy consumers with at least 20% energy savings in their operation of the services | Value | 0.00 | 0.00 | 5.00 |
Date | February 7, 2022 | September 9, 2022 | December 31, 2027 | |
Comment |
Share of newly created and existing management positions filled by women through internal promotion or external recruitment among utilities participating in the Program | Value | 35.00 | 0.00 | 40.00 |
Date | November 9, 2020 | September 9, 2022 | December 31, 2027 | |
Comment |
At least 1 WSS Utility aggregation process supported under the Program | Value | No | No | Yes |
Date | December 16, 2020 | September 9, 2022 | December 31, 2027 | |
Comment |