Caribbean Regional Air Transport Connectivity Project - Haiti

Abstract*

The objectives of the Caribbean Regional Air Transport Connectivity Project for Haiti are to: (i) improve operational safety and navigation efficiency of air transport in the Recipient’s territory; and (ii) increase the climate and disaster resilience of associated infrastructure at the Recipient’s international airports. The Project has four components. 1. PAP (IATA 3-letter code for Port-au-Prince Toussaint Louverture Airport) and CAP (IATA three-letter...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objectives of the Project (PDO) are to: (i) improve operational safety and navigation efficiency of air transport in the Recipient’s territory; and (ii) increase the climate and disaster resilience of associated infrastructure at the Recipient’s international airports.

Key Details

Project Details

  • P170907

  • Active

  • Ibrahim Kabore , Malaika Becoulet

  • Republic of Haiti

  • Haiti

  • June 6, 2019

  • (as of board presentation)

    May 28, 2020

  • August 27, 2020

  • US$ 84.00 million

  • Central Execution Unit of the Ministry of Public Works (UCE)

  • Latin America and Caribbean

  • 2020

  • US$ 84.00 million

  • N/A

  • April 30, 2024

  • June 30, 2026

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 84.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 84.00
IBRD + IDA Commitment 84.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 84.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
May 28, 2020 IDA-D6290 Loan Commitment 84,000,000.00
Jul 27, 2021 IDA-D6290 Loan Disb 22,110.33
Jul 5, 2023 IDA-E2030 Loan Commitment 12,000,000.00
Apr 17, 2024 IDA-D6290 Loan Disb 43,545.10
May 28, 2024 IDA-D6290 Loan Disb 50,286.83
Jun 7, 2024 IDA-D6290 Loan Disb 435,029.88
Aug 2, 2023 IDA-D6290 Loan Disb 348,267.60
Nov 17, 2023 IDA-D6290 Loan Disb 826,170.80
Nov 1, 2023 IDA-D6290 Loan Disb 928,300.90
Jan 3, 2024 IDA-D6290 Loan Disb 202,424.45
Jul 24, 2024 IDA-D6290 Loan Disb 945,088.50
Feb 27, 2024 IDA-D6290 Loan Disb 253,307.52
Aug 5, 2024 IDA-D6290 Loan Disb 177,536.88
Jan 24, 2022 IDA-D6290 Loan Disb 95,022.77
Mar 28, 2022 IDA-D6290 Loan Disb 138,104.19
May 12, 2022 IDA-D6290 Loan Disb 34,184.48
Mar 30, 2022 IDA-D6290 Loan Disb 215,182.44
Dec 28, 2022 IDA-D6290 Loan Disb 35,346.41
Feb 16, 2021 IDA-D6290 Loan Disb 3,000,000.00
Mar 10, 2023 IDA-D6290 Loan Disb 198,017.31
Oct 31, 2022 IDA-D6290 Loan Disb 47,707.67
Nov 15, 2022 IDA-D6290 Loan Disb 402,619.97
May 12, 2023 IDA-D6290 Loan Disb 133,269.16

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Unsatisfactory 2025-03-06
Project Management Moderately Satisfactory 2025-03-06
Financial Management Moderately Satisfactory 2025-03-06
Overall Implementation Progress (IP) Moderately Unsatisfactory 2025-03-06
Monitoring and Evaluation Satisfactory 2025-03-06
Procurement Moderately Unsatisfactory 2025-03-06

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Targeted upgrade of air navigation systems achieved at CAP and PAPValueNon-precision navigation system: No VSAT or ADS-BNon-precision navigation system: No VSAT or ADS-BElectronic navigation system in place (ADS-B imple
    DateJune 30, 2020February 13, 2024June 30, 2026
    Comment
  • Average number of days per year the discharge exceeds the capacity of the airport drainage system at PAP and CAPValue20.0020.000.00
    DateJune 30, 2020February 13, 2024June 30, 2026
    Comment
  • PAP and CAP runways in compliance with ICAO SARPsValueNoNoYes
    DateJune 30, 2020February 13, 2024January 30, 2026
    Comment
  • Average number of days per year the discharge exceeds the capacity of the airport drainage system at PAPValue10.0010.000.00
    DateJune 30, 2020February 13, 2024June 30, 2026
    Comment
  • Average number of days per year the discharge exceeds the capacity of the airport drainage system at CAPValue10.0010.000.00
    DateJune 30, 2020February 13, 2024June 30, 2026
    Comment
  • Average Runway Occupancy Time (ROT) of airplanes at PAPValue7.507.505.00
    DateJune 30, 2020February 13, 2024June 30, 2026
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Length of PAP taxiway system builtValue0.000.001460.00
    DateJune 30, 2020February 13, 2024December 31, 2024
    Comment
  • Aviation sector strategy preparedValueNoNoYes
    DateJune 30, 2020February 13, 2024June 30, 2026
    Comment
  • Additional aircraft parking apron built at PAPValue0.000.0026100.00
    DateJune 30, 2020February 13, 2024December 31, 2025
    Comment
  • Wildlife management plan prepared and implemented for PAP and CAP airportsValueNoNoYes
    DateJune 30, 2020February 13, 2024June 30, 2026
    Comment
  • Length of PAP drainage systemValue3850.003850.002450.00
    DateFebruary 28, 2020February 13, 2024June 30, 2026
    Comment
  • Length of CAP runway rehabilitatedValue0.000.002450.00
    DateJune 30, 2020February 13, 2024June 30, 2026
    Comment
  • OFNAC safety inspectors trained by a certified agencyValue0.000.0050.00
    DateJune 30, 2020February 13, 2024June 30, 2026
    Comment
  • New culverts built at CAPValue0.000.004.00
    DateFebruary 28, 2020February 13, 2024June 30, 2026
    Comment
  • Airfield Ground Lighting (AGL) for the CAP runway is installed and operationalValueNoNoYes
    DateJune 30, 2020February 13, 2024June 30, 2026
    Comment
  • Rescue Coordination Center staff trained by a certified agencyValue0.000.0050.00
    DateJune 30, 2020February 13, 2024June 30, 2026
    Comment
  • PAP RESAs implemented and consistent with ICAO SARPsValueNoNoYes
    DateJune 30, 2020February 13, 2024June 30, 2026
    Comment
  • Regional training programs attended by AAN and OFNACValue0.001.005.00
    DateJune 30, 2020February 13, 2024June 30, 2026
    Comment
  • Constructed CAP Air Traffic Control Tower (ATCT) in compliance with ICAO SARPsValueNoNoYes
    DateFebruary 28, 2020February 13, 2024June 30, 2026
    Comment
  • Grievances adequately responded to and/or resolved within the stipulated service standardsValue0.000.00100.00
    DateJune 30, 2020February 13, 2024June 30, 2026
    Comment
  • Share of women hired in medium-skill jobs by UCE-MTPC, OFNAC and AANValue0.000.0015.00
    DateJune 30, 2020February 13, 2024June 30, 2026
    Comment
  • ADS-B for CAP and PAP installed and operationalValueNoNoYes
    DateFebruary 28, 2020February 13, 2024June 30, 2026
    Comment
  • Share of women included in the medium-skills trainingValue0.0033.0030.00
    DateJune 30, 2020February 13, 2024June 30, 2026
    Comment
  • Share of infrastructure activities identified as climate resilientValue0.000.00100.00
    DateJune 30, 2020February 13, 2024March 30, 2026
    Comment
  • People with Enhanced Access to Transportation ServicesValue0.000.001900000.00
    DateJune 30, 2020February 13, 2024June 30, 2026
    Comment
  • Semi-annual meetings held with stakeholders to discuss their suggestions and related actions taken by the ProjectValue0.003.0012.00
    DateMay 29, 2020February 13, 2024June 30, 2026
    Comment