Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 250.00 |
Global Partnership for Education Fund | 14.25 |
P171316
Active
Maria Bendini , Marcela Silveyra de la Garza
Republic of El Salvador
October 9, 2019
(as of board presentation)
March 19, 2020
November 5, 2021
US$ 250.00 million
Ministry of Education
2020
US$ 264.25 million
N/A
May 14, 2024
June 30, 2026
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 250.00 |
Global Partnership for Education Fund | 14.25 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 250.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 250.00 |
Lending Instrument | |
---|---|
Grant Amount | 14.25 |
Total Project Cost** | 250.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 8, 2022 | IBRD-90670 | Loan Disb | 1,532,200.00 |
Dec 15, 2023 | IBRD-90670 | Int Charges | 1,147.20 |
Dec 15, 2023 | IBRD-90670 | Int Charges | 304,005.90 |
Dec 15, 2023 | IBRD-90670 | Int Charges | 5,499.18 |
Jun 15, 2023 | IBRD-90670 | Int Charges | 2,759.95 |
Jun 15, 2023 | IBRD-90670 | Int Charges | 60,756.69 |
Jun 15, 2023 | IBRD-90670 | Int Charges | 248,198.05 |
Jun 15, 2023 | IBRD-90670 | Int Charges | 60,756.69 |
Feb 23, 2024 | IBRD-90670 | Loan Disb | 4,607,977.00 |
Oct 18, 2023 | IBRD-90670 | Loan Disb | 16,730,531.00 |
Dec 15, 2023 | IBRD-90670 | Int Charges | 63,848.82 |
Jun 15, 2024 | IBRD-90670 | Int Charges | 165,825.06 |
Jun 15, 2024 | IBRD-90670 | Int Charges | 119,582.09 |
Jun 25, 2024 | IBRD-90670 | Loan Disb | 19,063,462.00 |
Jun 15, 2024 | IBRD-90670 | Int Charges | 6,646.38 |
Jun 15, 2024 | IBRD-90670 | Int Charges | 165,825.06 |
Jun 15, 2024 | IBRD-90670 | Int Charges | 739,222.06 |
Jul 5, 2024 | IBRD-90670 | Loan Disb | -42,559,168.00 |
Dec 15, 2022 | IBRD-90670 | Int Charges | 310,359.28 |
Dec 15, 2022 | IBRD-90670 | Int Charges | 292.99 |
Dec 15, 2022 | IBRD-90670 | Int Charges | 42,206.98 |
Dec 15, 2022 | IBRD-90670 | Int Charges | 292.99 |
Dec 15, 2022 | IBRD-90670 | Int Charges | 73.46 |
Nov 5, 2021 | IBRD-90670 | Fee Charges | 625,000.00 |
Nov 5, 2021 | IBRD-90670 | Loan Disb | 625,000.00 |
Jun 15, 2022 | IBRD-90670 | Int Charges | 3,886.47 |
Jun 15, 2022 | IBRD-90670 | Int Charges | 310,791.28 |
Jun 15, 2022 | IBRD-90670 | Int Charges | 750.00 |
Jun 15, 2022 | IBRD-90670 | Int Charges | 243,479.95 |
Jun 15, 2022 | IBRD-90670 | Int Charges | 4,636.47 |
Jul 5, 2024 | IBRD-90670 | Loan Disb | 42,559,168.00 |
Mar 19, 2020 | IBRD-90670 | Loan Commitment | 250,000,000.00 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Satisfactory | 2024-12-21 |
Financial Management | Satisfactory | 2024-12-21 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-12-21 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-12-21 |
Procurement | Moderately Satisfactory | 2024-12-21 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2024-12-21 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
PDO 1: ECCE teachers with improved teaching practices | Value | The baseline will be collected in Year 2. | Piloting and adaptation of instrument for assessin | The target will be set when the baseline is collec |
Date | January 31, 2020 | May 11, 2024 | June 30, 2026 | |
Comment |
PDO 2: ECCE official centers supported by the Project with safe physical learning environments and meeting quality conditions to promote learning | Value | 0.00 | 0.00 | 114.00 |
Date | January 31, 2020 | May 11, 2024 | June 30, 2026 | |
Comment |
PDO 3: ECCE centers accredited through the structural quality standards accreditation system | Value | No Structural Quality Standards (SQS), no SQS accr | Structural Quality Standards (SQS) under developme | 140 ECCE centers accredited through the SQS system |
Date | January 31, 2020 | May 11, 2024 | June 30, 2026 | |
Comment |
PDO 1.1. ECCE teachers improve their gender-equality attittudes and behaviors | Value | The baseline will be collected in year 2. | Piloting and adaptation of instrument for assessin | The target will be set when the baseline is collec |
Date | January 31, 2020 | May 11, 2024 | June 30, 2026 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
IRI 5: ECCE teacher and principal training plans aligned with the ECDLS and new curriculum ready for delivery. | Value | Current training plan | Performance standards for teachers and principals | ECCE teacher and principal training plan ready for |
Date | January 31, 2020 | May 11, 2024 | June 30, 2026 | |
Comment |
IRI 19: Number of direct beneficiaries of the CERC activities | Value | 0.00 | 0.00 | 35064.00 |
Date | November 23, 2023 | May 11, 2024 | August 15, 2024 | |
Comment |
IRI 10: Pre-investment studies for all ECCE official centers intervened by the Project. | Value | 0.00 | 58.00 | 74.00 |
Date | January 31, 2020 | May 11, 2024 | June 30, 2026 | |
Comment |
IRI 1: ECCE teachers nationwide receive the new ECCE curriculum | Value | 0 teachers. | 0.00 | 8,000 ECCE teachers nationwide receive the new cur |
Date | January 31, 2020 | May 11, 2024 | June 30, 2026 | |
Comment |
IRI 13: Department directorates that have initiated the organizational transformation | Value | 0.00 | 0.00 | 14.00 |
Date | January 31, 2020 | May 11, 2024 | June 30, 2026 | |
Comment |
IRI 6: ECCE principals trained in school management and leadership aligned to the performance standards and the ECDLS. | Value | 0.00 | 0.00 | 3400.00 |
Date | January 31, 2020 | May 11, 2024 | June 30, 2026 | |
Comment |
IRI 20: Number of schools rehabilitated through the CERC | Value | 0.00 | 0.00 | 164.00 |
Date | November 23, 2023 | May 11, 2024 | August 15, 2024 | |
Comment |
IRI 2: Classrooms in ECCE official centers that receive learning materials aligned to the new curriculum. | Value | 0.00 | 0.00 | 8000.00 |
Date | January 31, 2020 | May 11, 2024 | June 30, 2026 | |
Comment |
IRI 14: School infrastructure inventory system operating for decision making | Value | Status quo | TORs prepared for infrastructure system technical | 100% of official schools nationwide with informati |
Date | January 31, 2020 | May 11, 2024 | June 30, 2026 | |
Comment |
IRI 7: ECCE teachers trained in new professional development process aligned to training standards and ECDLS. | Value | 0.00 | 0.00 | 8000.00 |
Date | January 31, 2020 | May 11, 2024 | June 30, 2026 | |
Comment |
IRI 11: Infrastructure projects for ECCE official centers completed under the Project. | Value | 0.00 | 0.00 | 114.00 |
Date | January 31, 2020 | May 11, 2024 | June 30, 2026 | |
Comment |
IRI 3: Families have received Children Literature Books and Supporting Materials to foster reading at home. | Value | 0.00 | 0.00 | 62500.00 |
Date | September 27, 2022 | May 11, 2024 | June 30, 2026 | |
Comment |
IRI 15: Teachers trained in strategies to develop students’ language and communication skills for educational transition | Value | 0.00 | 0.00 | 17000.00 |
Date | January 31, 2020 | May 11, 2024 | June 30, 2026 | |
Comment |
IRI 4: Teachers trained to improve transition from preschool to first grade | Value | 0.00 | 0.00 | 6000.00 |
Date | October 2, 2022 | May 11, 2024 | June 30, 2026 | |
Comment |
IRI 16: Grievances related to the Project recorded in the GRM system that are processed and communicated back to the concerned citizens stakeholder within 21 days | Value | 0.00 | 100.00 | 90.00 |
Date | January 31, 2020 | May 11, 2024 | June 30, 2026 | |
Comment |
IRI 12: ECCE official centers supported by the Project to reduce biosafety and WASH services' gap. | Value | 0.00 | 0.00 | 483.00 |
Date | January 31, 2020 | May 11, 2024 | June 30, 2026 | |
Comment |
Teachers recruited or trained | Value | 0.00 | 0.00 | 8000.00 |
Date | January 31, 2020 | May 11, 2024 | June 30, 2026 | |
Comment |
IRI 17: Knowing my Achievements tests revised to assure a Gender Equity Perspective and applied to the Totality of the Students from 3rd grade to 2nd year of high school in all public schools | Value | Status quo. | 18 tests have been reviewed and applied. | Review of 18 tests (mathematics and language for e |
Date | October 2, 2022 | May 11, 2024 | June 30, 2026 | |
Comment |
Teachers recruited or trained - Female (RMS requirement) | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
IRI 18: Basic education public schools design improvement plans based on the results of the standardized test “Knowing my achievements” | Value | N/A | N/A | 900 |
Date | October 17, 2023 | May 11, 2024 | June 30, 2026 | |
Comment |
Students benefiting from direct interventions to enhance learning | Value | 0.00 | 0.00 | 944565.00 |
Date | January 31, 2020 | May 11, 2024 | June 30, 2026 | |
Comment |
Students benefiting from direct interventions to enhance learning - Female | Value | 0.00 | 0.00 | 269144.00 |
Date | ||||
Comment |