Maputo Urban Transformation Project

Abstract*

The development objective of Maputo Urban Transformation Project for Mozambique is to improve urban infrastructure and strengthen institutional capacity for sustainable urbanization in Maputo. This project has five components. 1) The first component, Informal Settlement Upgrade, aims to support the CMM to implement the Integrated Informal Settlements Upgrading Program in the most vulnerable neighborhoods of Maputo City, and has the following sub-components:...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To improve urban infrastructure and strengthen institutional capacity for sustainable urbanization in Maputo.

Key Details

Project Details

  • P171449

  • Active

  • Emily Owen , Nicholas Callender

  • Republic of Mozambique

  • Mozambique

  • December 14, 2019

  • (as of board presentation)

    December 10, 2020

  • March 17, 2021

  • US$ 100.00 million

  • N/A

  • High

  • April 30, 2028

  • No

  • BANK APPROVED

  • April 3, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 100.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 100.00
IBRD + IDA Commitment 100.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 100.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 10, 2020 IDA-D7490 Loan Commitment 100,000,000.00
Feb 7, 2024 IDA-E2880 Loan Commitment 50,000,000.00
Mar 17, 2021 IDA-D7490 Loan Disb 2,000,000.00
Oct 14, 2021 IDA-D7490 Loan Disb 838,019.40
Sep 9, 2021 IDA-D7490 Loan Disb 553,596.40
Jun 17, 2021 IDA-D7490 Loan Disb 338,091.34
Jun 11, 2024 IDA-D7490 Loan Disb 14,000,000.00
Mar 7, 2022 IDA-D7490 Loan Disb 3,888,728.50
Nov 9, 2022 IDA-D7490 Loan Disb 3,308,900.00
Feb 22, 2023 IDA-D7490 Loan Disb -1,911,050.50
Feb 22, 2023 IDA-D7490 Loan Disb 1,911,050.50
Sep 12, 2023 IDA-D7490 Loan Disb 4,739,449.00
Jun 7, 2021 IDA-D7490 Loan Disb 538,993.60

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Moderately Satisfactory 2024-12-20
Overall Implementation Progress (IP) Moderately Satisfactory 2024-12-20
Procurement Moderately Satisfactory 2024-12-20
Project Management Moderately Satisfactory 2024-12-20
Progress towards achievement of PDO Satisfactory 2024-12-20
Financial Management Satisfactory 2024-12-20

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • 1. People benefiting from improved urban infrastructure in selected informal settlements in MaputoValue0.00193676.00264084.00
    DateDecember 31, 2020December 18, 2023December 31, 2025
    Comment
  • 4. Increased municipal own source revenues from urbanization revenuesValue0.0039.00200.00
    DateDecember 31, 2020May 22, 2023December 31, 2025
    Comment
  • Of which 50 percent are womenValue0.00100712.00132042.00
    DateDecember 31, 2020December 18, 2023December 31, 2025
    Comment
  • 2. Area benefited from reduced flooding in the city center of MaputoValue0.000.0010.00
    DateDecember 31, 2020December 18, 2023December 31, 2025
    Comment
  • 3. Improved safe disposal of solid waste in Maputo’s sanitary landfillValue0.000.001000.00
    DateDecember 31, 2020December 18, 2023December 31, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • 5. Neighborhoods benefited from Municipal Covid-19 Response Interventions to reduce the risk of transmissionValue0.0020.0020.00
    DateDecember 31, 2020December 18, 2023December 31, 2025
    Comment
  • 10. Increased discharge capacity of the drainage system in the higher areas of the city centerValue0.000.0035.00
    DateDecember 31, 2020December 18, 2023December 31, 2025
    Comment
  • 15. Rights of way physically demarcated in KaTembe Municipal DistrictsValue0.000.0030.00
    DateDecember 31, 2020December 18, 2023December 31, 2025
    Comment
  • 19. Increased number of people engaged in participatory municipal governance spacesValue0.00492.00100.00
    DateDecember 31, 2020December 18, 2023December 31, 2025
    Comment
  • 6. Area benefited from improved drainage with climate resilient standards in the selected informal settlementsValue0.000.0015.00
    DateDecember 31, 2020December 18, 2023December 31, 2025
    Comment
  • 11. Increased retention and infiltration capacity of the drainage system in the city centerValue0.000.0020000.00
    DateDecember 31, 2020December 18, 2023December 31, 2025
    Comment
  • 16. Areas for future urban development (unidades executivas) provided with climate resilient trunk urban infrastructure in KaTembeValue0.000.002.00
    DateDecember 31, 2020December 18, 2023December 31, 2025
    Comment
  • Of which 50 percent are womenValue0.000.0025.00
    Date
    Comment
  • 7. People provided with access to safely managed sanitation in selected informal settlementsValue0.000.0040000.00
    DateDecember 31, 2020December 18, 2023December 31, 2025
    Comment
  • 12. Reduced impact of climate change during high tides on the drainage system of the city centerValue0.000.004.00
    DateDecember 31, 2020December 18, 2023December 31, 2025
    Comment
  • 17. New urbanized plots for low income families built in KaTembeValue0.000.001500.00
    DateDecember 31, 2020December 18, 2023December 31, 2025
    Comment
  • 20. Municipal e-government services expandedValue0.000.004.00
    DateDecember 31, 2020December 18, 2023December 31, 2025
    Comment
  • 13. Vulnerable people benefited from municipal socioeconomic inclusion programs in the city center.Value0.000.00500.00
    DateDecember 31, 2020December 18, 2023December 31, 2025
    Comment
  • 18. Strengthening the solid waste management sector in MaputoValueN/AN/AVolume of waste reused or recycled improved
    DateDecember 31, 2020December 18, 2023December 31, 2025
    Comment
  • 21. Municipal administrative processes and acts decentralized to districtsValue0.002.004.00
    DateDecember 31, 2020December 18, 2023December 31, 2025
    Comment
  • Of which 50 percent are womenValue0.000.000.00
    Date
    Comment
  • 8. Roads rehabilitated with solar powered street lighting in selected informal settlementsValue0.000.007.00
    DateDecember 31, 2020December 18, 2023December 31, 2025
    Comment
  • 22. Complaints filled through the grievance redress mechanism (GRM) successfully resolvedValue0.00100.00100.00
    DateDecember 31, 2020December 18, 2023December 31, 2025
    Comment
  • Of which 60 percent are female benefitiariesValue0.000.00120.00
    Date
    Comment
  • 9. Land tenure regularizationValue0.0080.006500.00
    DateDecember 31, 2020December 18, 2023December 31, 2025
    Comment
  • 14. Property tax reformValueElectronic property tax billing system and propertN/AN/A
    DateDecember 31, 2020December 18, 2023December 31, 2025
    Comment