Chad Local Development and Adaptation Project

Abstract*

The project will support activities that: (i) strengthen the resilience of community livelihoods around protected areas in the Chadian Sahelo-Saharan savannah; (ii) promote sustainable and integrated agro-sylvo-pastoral production systems; (iii) improve access to drinkable water and sanitation services; and (iv) support activities that will generate income for communities in the hotspots area. Conserving biodiversity and reducing the impact of climate...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The project development objective is to improve the management of natural resources and the livelihood of populations in selected climate vulnerable areas in and around the Ouadi Rime and Ouadi Achim (OROA) reserve in Chad?.

Key Details

Project Details

  • P171611

  • Active

  • Erik Reed , Taibou Adamou Maiga

  • Republic of Chad

  • Chad

  • October 17, 2019

  • (as of board presentation)

    June 12, 2020

  • September 22, 2020

  • US$ 54.45 million

  • Ministry of Envrionment, Water and Fisheries

  • Western and Central Africa

  • 2020

  • US$ 50.00 million

  • N/A

  • Moderate

  • October 31, 2025

  • Yes

  • BANK APPROVED

  • March 21, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Grant 50.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 50.00
IBRD + IDA Commitment 50.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 54.45

Summary Status of World Bank Financing (US$ Millions) as of June 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of June 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 11, 2022 IDA-D6730 Loan Disb 93,560.67
Aug 11, 2022 IDA-D6730 Loan Disb 48,307.95
Jun 2, 2022 IDA-D6730 Loan Disb 65,845.98
Jun 2, 2022 IDA-D6730 Loan Disb 34,033.77
Feb 23, 2022 IDA-D6730 Loan Disb 335,481.90
Feb 17, 2022 IDA-D6730 Loan Disb 98,429.84
Dec 23, 2021 IDA-D6730 Loan Disb 55,775.05
Jan 24, 2022 IDA-D6730 Loan Disb 98,808.21
Dec 30, 2022 IDA-D6730 Loan Disb 169,551.27
Dec 1, 2022 IDA-D6730 Loan Disb 81,171.06
Oct 11, 2022 IDA-D6730 Loan Disb 67,494.08
Apr 28, 2023 IDA-D6730 Loan Disb 131,213.42
Sep 22, 2022 IDA-D6730 Loan Disb 153,600.00
Feb 28, 2023 IDA-D6730 Loan Disb 53,207.98
Mar 23, 2023 IDA-D6730 Loan Disb 123,088.37
Mar 7, 2023 IDA-D6730 Loan Disb 94,422.24
Jun 28, 2023 IDA-D6730 Loan Disb 202,091.48
Sep 14, 2023 IDA-D6730 Loan Disb 442,534.47
Sep 19, 2023 IDA-D6730 Loan Disb 26,206.93
Sep 12, 2023 IDA-D6730 Loan Disb 665,451.56
Sep 11, 2023 IDA-D6730 Loan Disb 194,127.10
Sep 20, 2023 IDA-D6730 Loan Disb 311,923.72
Jun 28, 2023 IDA-D6730 Loan Disb 277,757.66
Jun 28, 2023 IDA-D6730 Loan Disb 170,089.06
Nov 13, 2023 IDA-D6730 Loan Disb 224,657.55
Nov 2, 2023 IDA-D6730 Loan Disb 989,090.90
Nov 17, 2023 IDA-D6730 Loan Disb 1,715,613.80
Oct 19, 2023 IDA-D6730 Loan Disb 154,091.78
Sep 28, 2023 IDA-D6730 Loan Disb 219,722.27
Nov 15, 2023 IDA-D6730 Loan Disb 439,981.66
Sep 22, 2020 IDA-D6730 Loan Disb 1,047,384.75
Mar 24, 2021 IDA-D6730 Loan Disb 141,788.30
Mar 31, 2021 IDA-D6730 Loan Disb 156,987.40
Mar 1, 2021 IDA-D6730 Loan Disb 1,310,861.40
Nov 10, 2021 IDA-D6730 Loan Disb 59,197.01
Jun 24, 2022 IDA-D6730 Loan Disb 27,527.14
Nov 29, 2021 IDA-D6730 Loan Disb 58,740.99
Nov 29, 2021 IDA-D6730 Loan Disb 48,875.59
Nov 29, 2021 IDA-D6730 Loan Disb 104,601.20
Nov 29, 2021 IDA-D6730 Loan Disb 50,841.15
Nov 29, 2021 IDA-D6730 Loan Disb 42,361.26
Feb 23, 2022 IDA-D6730 Loan Disb 572,695.50
Feb 23, 2022 IDA-D6730 Loan Disb 550,432.44
Jun 12, 2020 IDA-D6730 Loan Commitment 50,000,000.00
Jan 9, 2024 IDA-D6730 Loan Disb 748,094.10
Jun 26, 2024 IDA-D6730 Loan Disb 384,472.44
Jul 1, 2024 IDA-D6730 Loan Disb 179,126.40
Jun 18, 2024 IDA-D6730 Loan Disb 1,081,909.50
Jun 27, 2024 IDA-D6730 Loan Disb 309,398.34
Jun 17, 2024 IDA-D6730 Loan Disb 2,238,169.50
Jun 27, 2024 IDA-D6730 Loan Disb 108,154.64
May 28, 2024 IDA-D6730 Loan Disb 289,740.78
Feb 26, 2024 IDA-D6730 Loan Disb 742,874.90
Aug 16, 2024 IDA-D6730 Loan Disb 183,624.88
Jun 6, 2024 IDA-D6730 Loan Disb 322,641.03
Aug 16, 2024 IDA-D6730 Loan Disb 208,656.12
Jul 18, 2024 IDA-D6730 Loan Disb 279,675.22
Aug 16, 2024 IDA-D6730 Loan Disb 225,766.47
Jun 2, 2022 IDA-D6730 Loan Disb 60,558.98

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Satisfactory 2025-05-28
Procurement Moderately Satisfactory 2025-05-28
Project Management Moderately Satisfactory 2025-05-28
Financial Management Satisfactory 2025-05-28
Monitoring and Evaluation Moderately Satisfactory 2025-05-28
Progress towards achievement of PDO Satisfactory 2025-05-28

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Share of populations of key species stabilized or increased on the OROA Reserve's territoryValue0.00100.0070.00
    DateJuly 1, 2020November 15, 2023October 31, 2025
    Comment
  • People provided with access to improved water sourcesValue0.000.0010000.00
    DateJuly 1, 2020October 26, 2020October 31, 2025
    Comment
  • Terrestrial protected area under improved management for conservation and sustainable useValue0.0062360.0077950.00
    DateJuly 1, 2020November 15, 2023October 31, 2025
    Comment
  • People provided with access to improved water sources - Female (RMS requirement)Value0.000.000.00
    Date
    Comment
  • Land area under sustainable landscape management practicesValue0.00308.002000.00
    DateJuly 1, 2020November 15, 2023October 31, 2025
    Comment
  • Farmers adopting improved agricultural technologyValue0.000.00500.00
    DateJuly 1, 2020October 26, 2020October 31, 2025
    Comment
  • Farmers adopting improved agricultural technology - FemaleValue0.000.000.00
    Date
    Comment
  • Farmers adopting improved agricultural technology - maleValue0.000.000.00
    Date
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of basic infrastructure built on protected area (e.g., outposts, firebreaks, roads, watchtowers, visual delineation)Value0.000.005.00
    DateJuly 1, 2020October 26, 2020October 31, 2025
    Comment
  • Representatives in community-based decision-making and management structures that are femalesValue0.000.0050.00
    DateJuly 1, 2020October 26, 2020October 31, 2025
    Comment
  • Farmers reached with agricultural assets or servicesValue0.000.002500.00
    DateJuly 1, 2020October 26, 2020October 31, 2025
    Comment
  • Grievances registered related to delivery of project benefits that are addressedValue0.000.00100.00
    DateJuly 1, 2020October 26, 2020October 31, 2025
    Comment
  • Increased frequency and scope (% of PA area) of patrols for wildlife monitoring and protectionValue10.000.0070.00
    DateJuly 1, 2020October 26, 2020October 31, 2025
    Comment
  • Participants to training and sensibilization sessions in environment, conservation, nature-based tourism, gender, citizen engagement, WSS, WRM and CSA providedValue0.000.005000.00
    DateJuly 1, 2020October 26, 2020October 31, 2025
    Comment
  • Farmers reached with agricultural assets or services - FemaleValue0.000.000.00
    Date
    Comment
  • Policies strengthened and national legal frameworks to combat wildlife crimeValueNoNoYes
    DateJuly 1, 2020October 26, 2020October 31, 2025
    Comment
  • Number of inclusive and participatory local community SNRM committees and mechanisms operationalValue0.000.005.00
    DateJuly 1, 2020October 26, 2020October 31, 2025
    Comment
  • Number of water systems/points built/rehabilitated under delegated managementValue0.000.005.00
    DateJuly 1, 2020October 26, 2020October 31, 2025
    Comment
  • Number of Sanitation facilities constructedValue0.000.0010.00
    DateJuly 1, 2020October 26, 2020October 31, 2025
    Comment
  • Number of water resource data collection campaigns per yearValue0.000.002.00
    DateJuly 1, 2020October 26, 2020October 31, 2025
    Comment
  • % of women self-reported increased income (or increase yield) from extension servicesValue0.000.0050.00
    DateJuly 1, 2020October 26, 2020October 31, 2025
    Comment