Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 300.00 |
P171645
Active
Stefka Slavova , Fatma Akcollu Oguz
Republic of Turkey
October 14, 2019
(as of board presentation)
January 25, 2021
July 20, 2021
US$ 300.00 million
Ministry of Industry and Technology
2021
US$ 300.00 million
N/A
February 23, 2024
December 31, 2026
TBD
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 300.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 300.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 300.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 300.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jan 25, 2021 | IBRD-92050 | Loan Commitment | 300,000,000.00 |
Aug 15, 2023 | IBRD-92050 | Int Charges | 30,524.09 |
Feb 15, 2023 | IBRD-92050 | Int Charges | 336,524.94 |
Feb 15, 2023 | IBRD-92050 | Int Charges | 7,719.05 |
Feb 22, 2023 | IBRD-92050 | Loan Disb | 531,550.00 |
Dec 19, 2022 | IBRD-92050 | Loan Disb | -941,347.44 |
Dec 19, 2022 | IBRD-92050 | Loan Disb | 941,347.44 |
Aug 15, 2022 | IBRD-92050 | Int Charges | 315,368.60 |
Aug 15, 2022 | IBRD-92050 | Int Charges | 974.76 |
Feb 15, 2022 | IBRD-92050 | Int Charges | 213,965.34 |
Feb 15, 2022 | IBRD-92050 | Int Charges | 357,081.94 |
Feb 15, 2022 | IBRD-92050 | Int Charges | 400.90 |
Nov 1, 2021 | IBRD-92050 | Loan Disb | 1,157,150.00 |
Apr 18, 2024 | IBRD-92050 | Loan Disb | 800,700.00 |
Aug 29, 2024 | IBRD-92050 | Loan Disb | 5,548,750.00 |
Aug 15, 2024 | IBRD-92050 | Int Charges | 337,009.70 |
Aug 15, 2024 | IBRD-92050 | Int Charges | 103,142.63 |
Nov 3, 2023 | IBRD-92050 | Loan Disb | 638,580.00 |
Sep 8, 2023 | IBRD-92050 | Loan Disb | 1,605,150.00 |
Aug 15, 2023 | IBRD-92050 | Int Charges | 337,278.70 |
Feb 15, 2024 | IBRD-92050 | Int Charges | 334,187.16 |
Feb 15, 2024 | IBRD-92050 | Int Charges | 79,001.21 |
Sep 15, 2021 | IBRD-92050 | Fee Charges | 740,105.80 |
Name | Review | Date |
---|---|---|
Project Management | Satisfactory | 2025-01-14 |
Progress towards achievement of PDO | Moderately Satisfactory | 2025-01-14 |
Procurement | Moderately Satisfactory | 2025-01-14 |
Financial Management | Satisfactory | 2025-01-14 |
Monitoring and Evaluation | Satisfactory | 2025-01-14 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-01-14 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Water savings from OIZ green investments | Value | 0.00 | 0.00 | 6628000.00 |
Date | January 25, 2021 | December 21, 2023 | December 31, 2026 | |
Comment |
Energy savings from OIZ both basic and green infrastructure investments | Value | 0.00 | 0.00 | 16579.68 |
Date | January 25, 2021 | December 21, 2023 | December 31, 2026 | |
Comment |
Annual reduction in CO2 emissions due to supported investments | Value | 0.00 | 0.00 | 18434.00 |
Date | January 25, 2021 | December 21, 2023 | December 31, 2026 | |
Comment |
Share of OIZs that attract new investments | Value | 0.00 | 0.00 | 30.00 |
Date | January 25, 2021 | December 21, 2023 | December 31, 2026 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of laws/standards/regulations or amendments to current regulations enacted to support Green OIZ development | Value | 0.00 | 0.00 | 1.00 |
Date | January 25, 2021 | December 21, 2023 | December 31, 2026 | |
Comment |
Number of firms that benefit from OIZ basic and/or green infrastructure investments | Value | 0.00 | 0.00 | 1000.00 |
Date | January 25, 2021 | December 21, 2023 | December 31, 2026 | |
Comment |
Number of OIZs certified as Green OIZs | Value | 0.00 | 0.00 | 10.00 |
Date | January 25, 2021 | December 21, 2023 | December 31, 2026 | |
Comment |
Renewable energy generated due to OIZ green infrastructure investments | Value | 0.00 | 0.00 | 32600.00 |
Date | January 25, 2021 | December 21, 2023 | December 31, 2026 | |
Comment |
Number of firms reporting that they benefit from improved OIZ basic, green and competitiveness infrastructure | Value | 0.00 | 0.00 | 1000.00 |
Date | January 25, 2021 | December 21, 2023 | December 31, 2026 | |
Comment |
Wastewater treated in new/upgraded facilities | Value | 0.00 | 0.00 | 29200000.00 |
Date | January 25, 2021 | December 21, 2023 | December 31, 2026 | |
Comment |
Number of firms reporting that they understand the benefits of certified Green OIZs | Value | 0.00 | 0.00 | 700.00 |
Date | January 25, 2021 | December 21, 2023 | December 31, 2026 | |
Comment |
Number of employees trained in the innovation centers and model factories | Value | 0.00 | 0.00 | 2160.00 |
Date | January 25, 2021 | December 21, 2023 | December 31, 2026 | |
Comment |
Proportion of private sector investments facilitated in OIZs as compared to disbursed loan for infrastructure development | Value | 0.00 | 0.00 | 3.00 |
Date | January 25, 2021 | December 21, 2023 | December 31, 2026 | |
Comment |
Number of collaborative projects supported between OIZ firms and academia/research establishments | Value | 0.00 | 0.00 | 10.00 |
Date | January 25, 2021 | December 21, 2023 | December 31, 2026 | |
Comment |
The establishment of a database/system to track, collect and disaggregate gender-related data | Value | No | No | Yes |
Date | January 25, 2021 | December 21, 2023 | December 31, 2026 | |
Comment |