Turkey Organized Industrial Zones Project

Abstract*

The development objective of Organized Industrial Zones Project is to increase the efficiency, environmental sustainability and competitiveness of select Organized Industrial Zones (OIZs) in Turkey. This project has two main components. 1) The first component, Supporting the infrastructure and the enabling environment for OIZ sustainability, competitiveness and efficiency, includes the following sub-components: (i) Supporting investments in basic...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The PDO is to increase the efficiency, environmental sustainability and competitiveness of select Organized Industrial Zones (OIZs) in Turkey.

Key Details

Project Details

  • P171645

  • Active

  • Stefka Slavova , Fatma Akcollu Oguz

  • Republic of Turkey

  • Turkiye

  • October 14, 2019

  • (as of board presentation)

    January 25, 2021

  • July 20, 2021

  • US$ 300.00 million

  • Ministry of Industry and Technology

  • Europe and Central Asia

  • 2021

  • US$ 300.00 million

  • N/A

  • February 23, 2024

  • December 31, 2026

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
International Bank for Reconstruction and Development 300.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 300.00
IDA Commitment N/A
IBRD + IDA Commitment 300.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 300.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jan 25, 2021 IBRD-92050 Loan Commitment 300,000,000.00
Aug 15, 2023 IBRD-92050 Int Charges 30,524.09
Feb 15, 2023 IBRD-92050 Int Charges 336,524.94
Feb 15, 2023 IBRD-92050 Int Charges 7,719.05
Feb 22, 2023 IBRD-92050 Loan Disb 531,550.00
Dec 19, 2022 IBRD-92050 Loan Disb -941,347.44
Dec 19, 2022 IBRD-92050 Loan Disb 941,347.44
Aug 15, 2022 IBRD-92050 Int Charges 315,368.60
Aug 15, 2022 IBRD-92050 Int Charges 974.76
Feb 15, 2022 IBRD-92050 Int Charges 213,965.34
Feb 15, 2022 IBRD-92050 Int Charges 357,081.94
Feb 15, 2022 IBRD-92050 Int Charges 400.90
Nov 1, 2021 IBRD-92050 Loan Disb 1,157,150.00
Apr 18, 2024 IBRD-92050 Loan Disb 800,700.00
Aug 29, 2024 IBRD-92050 Loan Disb 5,548,750.00
Aug 15, 2024 IBRD-92050 Int Charges 337,009.70
Aug 15, 2024 IBRD-92050 Int Charges 103,142.63
Nov 3, 2023 IBRD-92050 Loan Disb 638,580.00
Sep 8, 2023 IBRD-92050 Loan Disb 1,605,150.00
Aug 15, 2023 IBRD-92050 Int Charges 337,278.70
Feb 15, 2024 IBRD-92050 Int Charges 334,187.16
Feb 15, 2024 IBRD-92050 Int Charges 79,001.21
Sep 15, 2021 IBRD-92050 Fee Charges 740,105.80

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2025-01-14
Progress towards achievement of PDO Moderately Satisfactory 2025-01-14
Procurement Moderately Satisfactory 2025-01-14
Financial Management Satisfactory 2025-01-14
Monitoring and Evaluation Satisfactory 2025-01-14
Overall Implementation Progress (IP) Moderately Satisfactory 2025-01-14

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Water savings from OIZ green investmentsValue0.000.006628000.00
    DateJanuary 25, 2021December 21, 2023December 31, 2026
    Comment
  • Energy savings from OIZ both basic and green infrastructure investmentsValue0.000.0016579.68
    DateJanuary 25, 2021December 21, 2023December 31, 2026
    Comment
  • Annual reduction in CO2 emissions due to supported investmentsValue0.000.0018434.00
    DateJanuary 25, 2021December 21, 2023December 31, 2026
    Comment
  • Share of OIZs that attract new investmentsValue0.000.0030.00
    DateJanuary 25, 2021December 21, 2023December 31, 2026
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of laws/standards/regulations or amendments to current regulations enacted to support Green OIZ developmentValue0.000.001.00
    DateJanuary 25, 2021December 21, 2023December 31, 2026
    Comment
  • Number of firms that benefit from OIZ basic and/or green infrastructure investmentsValue0.000.001000.00
    DateJanuary 25, 2021December 21, 2023December 31, 2026
    Comment
  • Number of OIZs certified as Green OIZsValue0.000.0010.00
    DateJanuary 25, 2021December 21, 2023December 31, 2026
    Comment
  • Renewable energy generated due to OIZ green infrastructure investmentsValue0.000.0032600.00
    DateJanuary 25, 2021December 21, 2023December 31, 2026
    Comment
  • Number of firms reporting that they benefit from improved OIZ basic, green and competitiveness infrastructureValue0.000.001000.00
    DateJanuary 25, 2021December 21, 2023December 31, 2026
    Comment
  • Wastewater treated in new/upgraded facilitiesValue0.000.0029200000.00
    DateJanuary 25, 2021December 21, 2023December 31, 2026
    Comment
  • Number of firms reporting that they understand the benefits of certified Green OIZsValue0.000.00700.00
    DateJanuary 25, 2021December 21, 2023December 31, 2026
    Comment
  • Number of employees trained in the innovation centers and model factoriesValue0.000.002160.00
    DateJanuary 25, 2021December 21, 2023December 31, 2026
    Comment
  • Proportion of private sector investments facilitated in OIZs as compared to disbursed loan for infrastructure developmentValue0.000.003.00
    DateJanuary 25, 2021December 21, 2023December 31, 2026
    Comment
  • Number of collaborative projects supported between OIZ firms and academia/research establishmentsValue0.000.0010.00
    DateJanuary 25, 2021December 21, 2023December 31, 2026
    Comment
  • The establishment of a database/system to track, collect and disaggregate gender-related dataValueNoNoYes
    DateJanuary 25, 2021December 21, 2023December 31, 2026
    Comment