Bamako Urban Resilience Project

Abstract*

This operation covers both the CERC restructuring and the AF to replenish the components that finance the CERC activities. The project is restructured through the reallocation of fund to the CERC component from undisbursed proceeds of the project to address the flood response needs. Through this AF, financing will be provided back to most of the components that are financing the flood emergency response interventions under the CERC. The proposed US$50...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

Improve access to urban waste management, sanitation and water services, increase resilience to flooding in certain vulnerable areas of the District of Bamako and targeted neighboring communes, strengthen urban management capacities, and provide immediate and effective response to an eligible crisis or emergency.

Key Details

Project Details

  • P171658

  • Active

  • Eduardo Ereno Blanchet , Mare Lo, Karamoko Sanogo

  • Republic of Mali

  • Mali

  • February 11, 2020

  • (as of board presentation)

    November 30, 2022

  • June 8, 2023

  • US$ 250.00 million

  • Ministry of Urban, Housing, Land, Territorial Administration and Population

  • Western and Central Africa

  • 2023

  • US$ 250.00 million

  • N/A

  • December 18, 2023

  • December 31, 2028

  • TBD

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 250.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 250.00
IBRD + IDA Commitment 250.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 250.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jun 3, 2024 IDA-72230 Loan Disb 1,659,273.00
Feb 2, 2024 IDA-72230 Loan Disb 422,533.38
Dec 28, 2023 IDA-72230 Loan Disb -439,848.12
Jun 3, 2024 IDA-72230 Loan Disb 184,153.16
Jul 19, 2024 IDA-72230 Loan Disb 131,092.77
Jun 8, 2023 IDA-72230 Loan Disb 3,149,408.50
Jun 30, 2023 IDA-72230 Loan Disb 489,740.62
Apr 18, 2024 IDA-72240 Int Charges 194,684.81
Jul 19, 2024 IDA-72240 Loan Disb 266,158.00
Jun 3, 2024 IDA-72240 Loan Disb 373,886.62
Jun 3, 2024 IDA-72240 Loan Disb 3,368,827.00
Nov 30, 2022 IDA-72230 Loan Commitment 100,000,000.00
Nov 30, 2022 IDA-72240 Loan Commitment 150,000,000.00
Sep 15, 2023 IDA-72240 Loan Disb 7,726,190.00
Apr 18, 2024 IDA-72240 Int Charges 158,775.23
Jul 16, 2024 IDA-72240 Loan Disb 301,216.28
Sep 15, 2023 IDA-72240 Loan Disb -7,726,190.00
Jun 30, 2023 IDA-72240 Loan Disb 833,882.70
Jun 30, 2023 IDA-72240 Loan Disb 6,618,116.50
Oct 16, 2023 IDA-72240 Int Charges 72,019.74
Oct 16, 2023 IDA-72240 Int Charges 236,509.45
Apr 18, 2024 IDA-72240 Int Charges 106.76
Jun 8, 2023 IDA-72240 Loan Disb 412,300.25
Jun 8, 2023 IDA-72240 Fee Charges 412,300.25

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Procurement Moderately Satisfactory 2024-11-25
Financial Management Moderately Satisfactory 2024-11-25
Project Management Satisfactory 2024-11-25
Progress towards achievement of PDO Satisfactory 2024-11-25
Monitoring and Evaluation Satisfactory 2024-11-25
Overall Implementation Progress (IP) Moderately Satisfactory 2024-11-25

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • People provided with improved urban living conditionsValue0.000.0080000.00
    DateApril 8, 2021March 23, 2023December 29, 2028
    Comment
  • Area protected from a flooding event with a 10-year return periodValue0.000.00350.00
    DateApril 8, 2021March 23, 2023December 29, 2028
    Comment
  • A digital platform (skills, data and tools) is used to inform critical urban planning activities and investment studies in the project areasValueNoNoYes
    DateApril 8, 2021March 23, 2023December 29, 2028
    Comment
  • People provided with improved urban living conditions - Female (RMS requirement)Value0.000.000.00
    Date
    Comment
  • People provided with improved access to Solid Waste Management servicesValue0.000.001500000.00
    DateApril 8, 2021March 23, 2023December 29, 2028
    Comment
  • those who are femaleValue0.000.000.00
    Date
    Comment
  • People provided with access to improved sanitation servicesValue0.000.00250000.00
    DateApril 8, 2021March 23, 2023December 29, 2028
    Comment
  • People provided with access to improved sanitation services - Female (RMS requirement)Value0.000.000.00
    Date
    Comment
  • People provided with access to improved water sourcesValue0.000.00175000.00
    DateApril 8, 2021March 23, 2023December 29, 2028
    Comment
  • People provided with access to improved water sources - Female (RMS requirement)Value0.000.000.00
    Date
    Comment
  • Beneficiaries that feel project investments reflected their needsValue0.000.0080.00
    DateApril 8, 2021March 23, 2023December 29, 2028
    Comment
  • Percentage of female beneficiariesValue0.000.000.00
    Date
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Transfer points built and functionalValue0.000.0025.00
    DateApril 8, 2021March 23, 2023December 29, 2028
    Comment
  • Length of primary/secondary drainage network rehabilitatedValue0.000.0010.00
    DateApril 8, 2021March 24, 2023December 28, 2029
    Comment
  • Elected representatives and key staff of the Grand Bamako having followed a minimum package of training according to the training plan to be prepared by the Grand Bamako AuthorityValue0.000.00100.00
    DateApril 8, 2021March 23, 2023December 29, 2028
    Comment
  • Improved household latrines constructed under the projectValue0.000.0020000.00
    DateApril 8, 2021March 23, 2023December 29, 2028
    Comment
  • Solid waste recycled or disposed at sanitary landfills in the project areaValue0.000.00250000.00
    DateApril 8, 2021March 23, 2023December 29, 2028
    Comment
  • Settlement area upgradedValue0.000.00500.00
    DateApril 8, 2021March 24, 2023December 29, 2028
    Comment
  • Improved latrines in public institutions constructed or rehabilitated under the projectValue0.000.00800.00
    DateApril 8, 2021March 23, 2023December 29, 2028
    Comment
  • Urban planning and investment studies completed with the use of a digital information systemValue0.000.003.00
    DateFebruary 5, 2021March 23, 2023December 29, 2028
    Comment
  • Local development plans / investment programs in place as a result of the projectValue0.000.0020.00
    DateApril 8, 2021March 23, 2023December 29, 2028
    Comment
  • Number of students provided with access to appropriate sanitation facilities in their schools under the projectValue0.000.0050000.00
    DateApril 8, 2021March 23, 2023December 29, 2028
    Comment
  • Operational drainage O&M strategyValueNoNoYes
    DateFebruary 5, 2021March 24, 2023December 29, 2028
    Comment
  • People benefiting from capacity building and trainingValue0.000.001500.00
    DateApril 8, 2021March 23, 2023December 29, 2028
    Comment
  • Increase in local governments' own revenuesValue0.000.0015.00
    DateFebruary 5, 2021March 23, 2023December 29, 2028
    Comment
  • Local initiatives supported by the projectValue0.000.0080.00
    DateApril 8, 2021March 24, 2023December 28, 2029
    Comment
  • New Fecal Sludge Treatment Plants constructed under the projectValue0.000.002.00
    DateApril 8, 2021March 23, 2023December 29, 2028
    Comment
  • of which womenValue0.000.000.00
    Date
    Comment
  • Share of local governments’ budgets allocated and spent on routine maintenanceValue10.000.0015.00
    DateFebruary 5, 2021March 24, 2023December 29, 2028
    Comment
  • of which led by womenValue0.000.000.00
    Date
    Comment
  • Number of people trained in digital and geospatial technologiesValue0.000.00100.00
    DateApril 8, 2021March 24, 2023December 29, 2028
    Comment
  • Jobs created in solid waste management and urban micro-projectsValue0.000.00570.00
    DateApril 8, 2021March 24, 2023December 28, 2029
    Comment
  • New piped household water connections that are resulting from the project interventionValue0.000.0015000.00
    DateApril 8, 2021March 23, 2023December 29, 2028
    Comment
  • Water storage capacity constructed under the projectValue0.000.0016000.00
    DateApril 8, 2021March 23, 2023December 29, 2028
    Comment
  • of which womenValue0.000.00228.00
    DateApril 8, 2021March 24, 2023December 29, 2028
    Comment
  • of which womenValue0.000.0050.00
    DateApril 8, 2021March 24, 2023December 29, 2028
    Comment
  • Length of water networks constructed under the projectValue0.000.00300.00
    DateApril 8, 2021March 23, 2023December 29, 2028
    Comment