Financier | Commitments |
---|---|
IDA Grant | 100.00 |
P171664
Active
Laurent Corthay
Republic of Mozambique
June 6, 2020
(as of board presentation)
May 11, 2021
July 22, 2021
US$ 100.00 million
Ministry of Economy and Finance
2021
US$ 100.00 million
N/A
Substantial
September 30, 2027
TBD
BANK APPROVED
February 21, 2024
Financier | Commitments |
---|---|
IDA Grant | 100.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 100.00 |
IBRD + IDA Commitment | 100.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 100.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 11, 2021 | IDA-D8100 | Loan Commitment | 100,000,000.00 |
Jul 22, 2021 | IDA-D8100 | Loan Disb | 400,000.00 |
Feb 21, 2024 | IDA-D8100 | Loan Disb | 1,477,867.90 |
May 28, 2024 | IDA-D8100 | Loan Disb | 1,292,997.50 |
Jun 25, 2024 | IDA-D8100 | Loan Disb | 775,750.75 |
Jun 24, 2024 | IDA-D8100 | Loan Disb | 3,000,000.00 |
Jul 1, 2024 | IDA-D8100 | Loan Disb | 602,197.30 |
Jun 28, 2022 | IDA-D8100 | Loan Disb | 76,111.88 |
Feb 2, 2022 | IDA-D8100 | Loan Disb | 197,002.30 |
Jan 18, 2022 | IDA-D8100 | Loan Disb | 4,638.50 |
Jan 18, 2022 | IDA-D8100 | Loan Disb | 12,107.40 |
Mar 16, 2023 | IDA-D8100 | Loan Disb | 105,840.90 |
Sep 5, 2023 | IDA-D8100 | Loan Disb | 57,027.14 |
Jun 26, 2023 | IDA-D8100 | Loan Disb | 412,569.60 |
May 30, 2023 | IDA-D8100 | Loan Disb | 539,570.40 |
Jun 6, 2023 | IDA-D8100 | Loan Disb | 28,513.57 |
Nov 10, 2023 | IDA-D8100 | Loan Disb | 848,110.20 |
Nov 1, 2021 | IDA-D8100 | Loan Disb | 5,600,000.00 |
Jun 30, 2022 | IDA-D8100 | Loan Disb | 28,502.13 |
Jun 1, 2022 | IDA-D8100 | Loan Disb | 236,264.95 |
Apr 29, 2024 | IDA-D8100 | Loan Disb | 2,765,527.20 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2025-03-21 |
Procurement | Satisfactory | 2025-03-21 |
Financial Management | Satisfactory | 2025-03-21 |
Monitoring and Evaluation | Moderately Satisfactory | 2025-03-21 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-03-21 |
Project Management | Satisfactory | 2025-03-21 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Change in sales growth of firms supported by the project | Value | 0.00 | 0.00 | 20.00 |
Date | March 31, 2021 | August 4, 2022 | March 31, 2027 | |
Comment |
Change in sales growth of women-owned/led firms supported by the project | Value | 0.00 | 0.00 | 20.00 |
Date | ||||
Comment |
Change in sales growth of firms in Cabo Delgado province supported by the project | Value | 0.00 | 0.00 | 20.00 |
Date | ||||
Comment |
Number of new, better paying, or better quality jobs (as defined in methodology) by the firms supported by the project | Value | 0.00 | 0.00 | 5000.00 |
Date | March 31, 2021 | August 4, 2022 | March 31, 2027 | |
Comment |
Number of new, better paying, or better quality jobs by the women-owned/led firms supported by the project | Value | 0.00 | 0.00 | 1500.00 |
Date | ||||
Comment |
Number of new, better paying, or better quality jobs by the firms in Cabo Delgado province supported by the project | Value | 0.00 | 0.00 | 500.00 |
Date | ||||
Comment |
Implemented reforms supporting private sector development | Value | 0.00 | 1.00 | 2.00 |
Date | March 31, 2021 | June 9, 2023 | March 31, 2027 | |
Comment |
Value of private sector investment leveraged by direct activities of the project | Value | 0.00 | 0.00 | 20000000.00 |
Date | March 31, 2020 | August 4, 2022 | March 31, 2027 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of digital platforms supported by the project | Value | 0.00 | 0.00 | 5.00 |
Date | March 31, 2021 | August 4, 2022 | March 31, 2027 | |
Comment |
Firms benefiting from private sector initiatives | Value | 0.00 | 0.00 | 10100.00 |
Date | March 31, 2021 | August 4, 2022 | March 31, 2027 | |
Comment |
Number of unique users in digital platforms supported by the project | Value | 0.00 | 0.00 | 500.00 |
Date | March 31, 2021 | August 4, 2022 | March 31, 2027 | |
Comment |
Number of women-owned/led firms benefiting from the project interventions | Value | 0.00 | 0.00 | 4700.00 |
Date | ||||
Comment |
Number of productive infrastructure investments supported by the project that apply harmonized climate resilience standards | Value | 0.00 | 0.00 | 3.00 |
Date | March 31, 2021 | August 4, 2022 | March 31, 2027 | |
Comment |
Number of firms in Cabo Delgado province benefiting from project interventions | Value | 0.00 | 0.00 | 2000.00 |
Date | ||||
Comment |
Number of institutions capacitated with support from the project | Value | 0.00 | 4.00 | 4.00 |
Date | March 31, 2021 | August 4, 2022 | March 31, 2027 | |
Comment |
Number of firms benefiting from skills interventions for upstream linkages | Value | 0.00 | 0.00 | 1000.00 |
Date | ||||
Comment |
Number of coordination platforms on economic linkages supported by the project | Value | 0.00 | 0.00 | 1.00 |
Date | March 31, 2021 | August 4, 2022 | March 31, 2027 | |
Comment |
Number of firms benefiting from quality standards upgrading for upstream linkages | Value | 0.00 | 0.00 | 300.00 |
Date | ||||
Comment |
Grievances addressed within the stipulated service standards | Value | 0.00 | 100.00 | 100.00 |
Date | March 31, 2021 | August 4, 2022 | March 31, 2027 | |
Comment |
Number of firms benefiting from matching grants or competitive grants | Value | 0.00 | 0.00 | 300.00 |
Date | ||||
Comment |
Number of firms supported by the project for consumption linkages | Value | 0.00 | 0.00 | 9000.00 |
Date | ||||
Comment |
Grievances addressed within the stipulated service standards | Value | 0.00 | 100.00 | 100.00 |
Date | March 31, 2021 | August 4, 2022 | March 31, 2027 | |
Comment |
Number of beneficiary firms having increase in sales (generated through the economic linkages programs in the project) | Value | 0.00 | 0.00 | 2500.00 |
Date | March 31, 2021 | August 4, 2022 | March 31, 2027 | |
Comment |
Number of firms with increased number of clients (generated through the economic linkages programs in the project) | Value | 0.00 | 0.00 | 2000.00 |
Date | March 31, 2021 | August 4, 2022 | March 31, 2027 | |
Comment |