Skip to Main Navigation

Abstract*

The project will be financed by the Recipient Executed Window of the Jordan MDTF and will: i) Support the reform secretariat and reform design and coordination; ii) Strenghten the PIM-PPP framework and function and iii) Strenghten the procurement framework and function. The proposed project will support the coordination and implementation of the five-year Reform Matrix – the reference plan for economic reform and growth of the Government of Jordon...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To strengthen coordination and delivery of policy reforms in Jordan with a focus on the updated Reform Matrix

Key Details

Project Details

  • P171965

  • Active

  • Jad Mazahreh

  • Ministry of Planning and International Cooperation

  • Jordan

  • August 23, 2019

  • (as of board presentation)

    November 27, 2019

  • December 7, 2019

  • US$ 6.50 million

  • Ministry of Planning and International Cooperation

  • Middle East and North Africa

  • 2020

  • US$ 15.80 million

  • N/A

  • Moderate

  • June 30, 2025

  • No

  • BANK APPROVED

  • April 24, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Trust Funds 6.50
Free-standing TFs for Bank 9.30

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 15.80
Total Project Cost** 6.50

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Satisfactory 2024-12-10
Financial Management Satisfactory 2024-12-10
Monitoring and Evaluation Satisfactory 2024-12-10
Overall Implementation Progress (IP) Satisfactory 2024-12-10
Monitoring and Evaluation Satisfactory 2024-12-10
Overall Implementation Progress (IP) Satisfactory 2024-12-10
Procurement Satisfactory 2024-12-10
Project Management Satisfactory 2024-12-10
Progress towards achievement of PDO Satisfactory 2024-12-10
Procurement Satisfactory 2024-12-10
Project Management Satisfactory 2024-12-10
Financial Management Satisfactory 2024-12-10

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of policy reforms in 12 Pillars of the updated Reform Matrix completed by MDAs with the support of the Reform SecretariatValue61.00116.0080.00
    DateApril 27, 2023March 7, 2024December 31, 2025
    Comment
  • Of which number of policy reform that benefit womenValue13.0020.0016.00
    DateApril 27, 2023March 7, 2024December 31, 2025
    Comment
  • Number of policy reforms that integrated stakeholders including citizens, business, academia feedback through stakeholder consultations organized by MDAs in partnership with the Reform SecretariatValue0.0024.0020.00
    DateApril 27, 2023March 7, 2024June 30, 2025
    Comment
  • Percentage of new public investment projects (PIPs) registered in NRIP that were included in the budget as described in PIM legal and policy framework.Value12.0050.0060.00
    DateApril 27, 2023March 7, 2024June 30, 2025
    Comment
  • Adoption of sustainable procurement policy on green procurement and/or SME including women-led SMEValueNoNoYes
    DateApril 27, 2023March 7, 2024June 30, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Share of public procurement contract award results published onlineValue0.00100.00100.00
    DateAugust 31, 2019March 7, 2024June 25, 2025
    Comment
  • Two new e-procurement modules added in one yearValueNoYesYes
    DateAugust 31, 2019March 7, 2024June 30, 2025
    Comment
  • Number of policy briefs filed by the Reform Secretariat to cabinet on policy reform implementationValue0.001.005.00
    DateApril 27, 2023March 7, 2024June 30, 2025
    Comment
  • Number of government officials trained in PIM-PPP Framework of JordanValue47.00220.00100.00
    DateApril 27, 2023March 7, 2024June 30, 2025
    Comment
  • Number of MDAs supported by the Reform Support FundValue15.0028.0020.00
    DateApril 27, 2023March 7, 2024June 30, 2025
    Comment
  • Number of technical working groups which include reform implementing MDAs operationalized by Reform SecretariatValue0.002.006.00
    DateApril 27, 2023March 7, 2024June 30, 2025
    Comment
  • Number of government officials trained on PPP project financingValue0.005.0015.00
    DateApril 27, 2023March 7, 2024June 30, 2025
    Comment
  • Percentage of the RSF disbursed to priority reform areasValue0.0036.0060.00
    DateApril 27, 2023March 7, 2024June 30, 2025
    Comment
  • The Reform Secretariat is established at MoPIC and staffed with at least 10 team membersValueNoYesYes
    DateAugust 31, 2019March 7, 2024June 30, 2025
    Comment
  • A pipeline plan for PPP projects developedValueNoNoYes
    DateApril 27, 2023March 7, 2024June 30, 2025
    Comment
  • Number of stakeholder engagement consultations organized by MDAs that involved stakeholders including civil society, businesses andacademia with support from the Reform SecretariatValue0.0074.0015.00
    DateApril 27, 2023March 7, 2024June 30, 2025
    Comment
  • The National Registry of Investment Projects (NRIP) acquired and operationalizedValueNoYesYes
    DateAugust 31, 2019March 7, 2024June 30, 2025
    Comment
  • Fiscal risk assessment guidelines issued by the Ministry of FinanceValueNoYesYes
    DateAugust 31, 2019March 7, 2024June 30, 2025
    Comment
  • Revised PPP Guidelines produced and approvedValueNoYesYes
    DateAugust 31, 2019March 7, 2024June 30, 2025
    Comment
  • Standardized project concept notes templates for public investment projects and PPP projects producedValueNoYesYes
    DateAugust 31, 2019March 7, 2024June 30, 2025
    Comment
  • Project development fund (PDF) established and operationalizedValueNoYesYes
    DateAugust 31, 2019March 7, 2024June 30, 2025
    Comment
  • Percentage of government MDAs using JONEPS for processing procurementValue4.0029.0040.00
    DateApril 27, 2023March 7, 2024June 30, 2025
    Comment
  • Adoption of the professionalization framework by the Procurement Policy CommitteeValueNoNoYes
    DateApril 27, 2023March 7, 2024June 30, 2025
    Comment
  • Number of businesses registered in JONEPSValue2874.005650.005000.00
    DateApril 27, 2023March 7, 2024June 30, 2025
    Comment