Financier | Commitments |
---|---|
IDA Grant | 60.00 |
P171976
Active
Marolla Haddad , C. Myers
Ministère de l'Economie et des Finances d'Haïti
Haiti
December 3, 2019
(as of board presentation)
October 9, 2020
November 26, 2020
US$ 60.00 million
Ministère des Travaux Publics, Transports et Communications
2021
US$ 60.00 million
N/A
February 8, 2024
October 15, 2026
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 60.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 60.00 |
IBRD + IDA Commitment | 60.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 60.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 3, 2022 | IDA-D7240 | Loan Disb | 69,263.97 |
Aug 29, 2022 | IDA-D7240 | Loan Disb | 220,798.44 |
Mar 3, 2022 | IDA-D7240 | Loan Disb | 152,690.50 |
Dec 20, 2022 | IDA-D7240 | Loan Disb | 104,786.81 |
Apr 5, 2023 | IDA-D7240 | Loan Disb | 102,020.73 |
Oct 31, 2022 | IDA-D7240 | Loan Disb | 72,983.26 |
May 12, 2023 | IDA-D7240 | Loan Disb | 191,826.62 |
Feb 17, 2023 | IDA-D7240 | Loan Disb | 350,345.66 |
Dec 5, 2023 | IDA-D7240 | Loan Disb | 89,491.80 |
Sep 22, 2023 | IDA-D7240 | Loan Disb | 888,163.20 |
Jul 3, 2023 | IDA-D7240 | Loan Disb | 76,000.15 |
Jun 10, 2024 | IDA-D7240 | Loan Disb | 210,203.40 |
Nov 14, 2023 | IDA-D7240 | Loan Disb | 264,483.25 |
Nov 27, 2023 | IDA-D7240 | Loan Disb | 258,219.12 |
Aug 27, 2024 | IDA-D7240 | Loan Disb | 493,619.62 |
Apr 1, 2024 | IDA-D7240 | Loan Disb | 853,973.60 |
Jan 24, 2024 | IDA-D7240 | Loan Disb | 258,219.12 |
Jun 5, 2024 | IDA-D7240 | Loan Disb | 408,293.53 |
Feb 6, 2024 | IDA-D7240 | Loan Disb | 179,993.10 |
May 6, 2024 | IDA-D7240 | Loan Disb | 308,841.72 |
Oct 9, 2020 | IDA-D7240 | Loan Commitment | 60,000,000.00 |
Dec 21, 2020 | IDA-D7240 | Loan Disb | 1,250,000.00 |
Jun 24, 2021 | IDA-D7240 | Loan Disb | 78,536.32 |
Dec 15, 2021 | IDA-D7240 | Loan Disb | 102,764.49 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2024-12-09 |
Project Management | Moderately Satisfactory | 2024-12-09 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-12-09 |
Procurement | Moderately Satisfactory | 2024-12-09 |
Financial Management | Moderately Satisfactory | 2024-12-09 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-12-09 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People provided with access to the Internet | Value | 0.00 | 374.00 | 2400000.00 |
Date | May 13, 2020 | December 4, 2023 | October 1, 2025 | |
Comment |
Percentage of newly built or upgraded infrastructure that is resilient to shocks | Value | 0.00 | 0.00 | 100.00 |
Date | July 14, 2020 | December 4, 2023 | October 1, 2026 | |
Comment |
Number of people that benefitted from new access to Internet service. | Value | 0.00 | 0.00 | 900000.00 |
Date | May 13, 2020 | December 4, 2023 | October 1, 2026 | |
Comment |
Mean down time per month of connectivity services provided under this project | Value | 5256.00 | 5256.00 | 52.56 |
Date | May 13, 2020 | December 4, 2023 | October 1, 2026 | |
Comment |
Number of people that benefitted from the improved Internet service. | Value | 0.00 | 374.00 | 1800000.00 |
Date | May 13, 2020 | December 4, 2023 | October 1, 2026 | |
Comment |
People provided with access to the Internet - Female | Value | 0.00 | 0.00 | 750000.00 |
Date | ||||
Comment |
Broadband penetration over mobile and fixed network providing high speed broadband services | Value | 35.00 | 70.00 | 50.00 |
Date | May 13, 2020 | December 4, 2023 | October 1, 2026 | |
Comment |
Mobile broadband penetration | Value | 35.00 | 35.00 | 45.00 |
Date | ||||
Comment |
Fixed broadband penetration | Value | 1.50 | 2.50 | 5.00 |
Date | June 30, 2020 | December 4, 2023 | October 1, 2026 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Amount of private sector investment in the sector due to the project | Value | 0.00 | 0.00 | 20000000.00 |
Date | May 1, 2020 | December 4, 2023 | October 1, 2026 | |
Comment |
Number of sectoral policies/legislation/regulations reviewed and consulted on by stakeholders | Value | 0.00 | 0.00 | 5.00 |
Date | May 1, 2020 | December 4, 2023 | October 1, 2026 | |
Comment |
Number of institutions connected through the project | Value | 0.00 | 15.00 | 1300.00 |
Date | May 14, 2020 | December 4, 2023 | October 1, 2026 | |
Comment |
Number of people trained through the digital skills program | Value | 0.00 | 84.00 | 30000.00 |
Date | May 1, 2020 | December 4, 2023 | October 1, 2026 | |
Comment |
Percentage of users of digital broadband services reporting satisfaction with the service | Value | 0.00 | 81.00 | 65.00 |
Date | December 31, 2020 | December 4, 2023 | October 30, 2026 | |
Comment |
Percentage of women completing general digital literacy training | Value | 0.00 | 0.00 | 50.00 |
Date | ||||
Comment |
Quality of Service and resilience: Fixed broadband download speed in Mbps | Value | 5.00 | 5.00 | 24.00 |
Date | May 13, 2020 | December 4, 2023 | October 1, 2026 | |
Comment |
Percentage of women completing cybersecurity training | Value | 0.00 | 0.00 | 30.00 |
Date | ||||
Comment |
Quality of Service and resilience: Mobile broadband download speed in Mbps | Value | 5.00 | 5.00 | 15.00 |
Date | May 13, 2020 | December 4, 2023 | October 1, 2026 | |
Comment |
Percentage of women completing advanced technical training | Value | 0.00 | 0.00 | 30.00 |
Date | ||||
Comment |
Development of national broadband strategy with a gender lens | Value | No | No | Yes |
Date | July 13, 2020 | December 4, 2023 | October 1, 2026 | |
Comment |
Cybersecurity Capacity Maturity Model assessment undertaken | Value | No | Yes | Yes |
Date | May 13, 2020 | December 4, 2023 | October 1, 2026 | |
Comment |
Digital economy strategy with an integrated gender and resilience lens | Value | No | No | Yes |
Date | July 13, 2020 | December 4, 2023 | October 1, 2026 | |
Comment |