Skip to Main Navigation

SPF - Support to Zimbabwe Recovery and Resilience

Abstract*

Given Zimbabwe’s non-accrual status with the World Bank, the ZIRP cannot finance government in any form and precludes any transactions through government. While ZIRP will not finance the government, the ZIRP will engage the government’s national, provincial, and local structures at the various stages to ensure close coordination and collaboration with the programs of humanitarian and developmental agencies involved in supporting cyclone recovery in...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To support the Government of Zimbabwe to i) improve Governmental coordination capacity to respond to cyclone Idai, and ii) to scale-up and institutionalize DRM capacity

Key Details

Project Details

  • P172176

  • Closed

  • Nicholas Callender

  • Ministry of Finance and Economic Development

  • Zimbabwe

  • October 23, 2019

  • (as of board presentation)

    March 28, 2020

  • May 14, 2020

  • US$ 2.00 million

  • Ministry of Finance and Economic Development

  • Eastern and Southern Africa

  • 2020

  • US$ 3.00 million

  • N/A

  • Low

  • December 31, 2022

  • No

  • BANK APPROVED

  • August 5, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Zimbabwe Reconstruction Fund (ZIMREF) 3.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 3.00
Total Project Cost** 2.00

Summary Status of World Bank Financing (US$ Millions) as of April 30, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of April 30, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Overall Implementation Progress (IP) Satisfactory 2022-12-28
Progress towards achievement of PDO Satisfactory 2022-12-28
Overall Low 2022-12-28

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Improved Government Systems & Capacity in Place for DRM at the National LevelValueNYY
    DateFebruary 28, 2020December 20, 2022December 30, 2022
    Comment
  • Improved Capacity for DRM in the Cyclone-affected ProvincesValueNYY
    DateFebruary 28, 2020December 20, 2022December 30, 2022
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • National DRM operational guidelines and SOPs produced and operationalizedValueNYY
    DateFebruary 28, 2020December 20, 2022December 30, 2022
    Comment
  • National DRM training curriculum used across GovernmentValueNYY
    DateFebruary 28, 2020December 20, 2022December 30, 2022
    Comment
  • Integrated Management Information System with electronic beneficiary registry designed and operationalizedValueNYY
    DateFebruary 28, 2020December 20, 2022December 30, 2022
    Comment
  • DRM operational guidelines and SOPs used at Provincial levelValueNNY
    DateFebruary 28, 2020December 20, 2022December 30, 2022
    Comment
  • National DRM training rolled out to district and ward-level communitiesValueNYY
    DateFebruary 28, 2020December 20, 2022December 30, 2022
    Comment
  • Beneficiary registry that includes profiles of beneficiaries in cyclone-affected districts in place and operationalValueNYY
    DateFebruary 28, 2020December 20, 2022December 30, 2022
    Comment