P172225
Active
Anita Shrestha , Aditi Raina
Department of Finance
April 9, 2020
(as of board presentation)
May 17, 2021
August 9, 2021
US$ 40.00 million
Department of Transportation, Communications & Infrastructure
2021
US$ 40.00 million
N/A
October 15, 2023
August 31, 2028
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Grant | 40.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 40.00 |
IBRD + IDA Commitment | 40.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 40.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Feb 4, 2022 | IDA-D7790 | Loan Disb | 64,945.85 |
May 17, 2021 | IDA-D7790 | Loan Commitment | 40,000,000.00 |
Apr 25, 2024 | IDA-D7790 | Loan Disb | 287,024.20 |
Feb 1, 2024 | IDA-D7790 | Loan Disb | 199,348.48 |
Jan 12, 2024 | IDA-D7790 | Loan Disb | 28,389.73 |
Jun 12, 2023 | IDA-D7790 | Loan Disb | 155,505.39 |
Feb 27, 2023 | IDA-D7790 | Loan Disb | 165,004.67 |
Sep 8, 2023 | IDA-D7790 | Loan Disb | 206,365.40 |
Oct 24, 2022 | IDA-D7790 | Loan Disb | 46,118.51 |
Sep 24, 2021 | IDA-D7790 | Loan Disb | 214,276.00 |
May 13, 2022 | IDA-D7790 | Loan Disb | 131,087.45 |
Aug 12, 2022 | IDA-D7790 | Loan Disb | 140,028.67 |
Jan 7, 2022 | IDA-D7790 | Loan Disb | 57,007.83 |
Nov 18, 2021 | IDA-D7790 | Loan Disb | 2,000,000.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2024-11-09 |
Financial Management | Moderately Satisfactory | 2024-11-09 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-11-09 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-11-09 |
Project Management | Moderately Satisfactory | 2024-11-09 |
Procurement | Moderately Satisfactory | 2024-11-09 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Identified planning tools being used to improve climate resilience of roads | Value | 0.00 | 0.00 | 2.00 |
Date | October 28, 2020 | September 21, 2023 | June 30, 2028 | |
Comment |
Length of road upgraded with climate resilience measures | Value | 0.00 | 0.00 | 7.30 |
Date | October 28, 2020 | September 21, 2023 | June 30, 2028 | |
Comment |
Identified enabling environment solutions implemented | Value | 0.00 | 0.00 | 6.00 |
Date | October 28, 2020 | September 21, 2023 | June 30, 2028 | |
Comment |
Number of water crossings reconstructed or rehabilitated with climate resilience measures | Value | 0.00 | 0.00 | 5.00 |
Date | October 28, 2020 | September 21, 2023 | June 30, 2027 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Road asset management system that considers climate factors in use | Value | No | No | Yes |
Date | October 28, 2020 | September 21, 2023 | June 30, 2028 | |
Comment |
Length of road rehabilitated with pavement strengthening | Value | 0.00 | 0.00 | 6.50 |
Date | October 28, 2020 | September 21, 2023 | June 30, 2028 | |
Comment |
Number of Government staff and local consultants who have achieved improvements in skills/knowledge as a result of capacity building programs compared to pre-training baseline | Value | 0.00 | 0.00 | 48.00 |
Date | October 28, 2020 | September 21, 2023 | June 30, 2028 | |
Comment |
Grievances registered related to delivery of project benefits that are addressed | Value | 0.00 | 0.00 | 75.00 |
Date | October 28, 2020 | September 21, 2023 | June 30, 2028 | |
Comment |
Vulnerability Assessment and Climate Resilient Road Strategy in use | Value | No | No | Yes |
Date | October 28, 2020 | September 21, 2023 | June 30, 2028 | |
Comment |
Length of road with improved drainage | Value | 0.00 | 0.00 | 3.90 |
Date | October 28, 2020 | September 21, 2023 | June 30, 2028 | |
Comment |
Road safety audits completed | Value | 0.00 | 1.00 | 6.00 |
Date | October 28, 2020 | September 21, 2023 | June 30, 2028 | |
Comment |
Length of road improved with spot slope stabilization | Value | 0.00 | 0.00 | 500.00 |
Date | October 28, 2020 | September 21, 2023 | June 30, 2028 | |
Comment |
Access audits completed | Value | 0.00 | 0.00 | 6.00 |
Date | October 28, 2020 | September 21, 2023 | June 30, 2028 | |
Comment |
Length of coastal protection revetment constructed and/or replenished | Value | 0.00 | 0.00 | 850.00 |
Date | October 28, 2020 | September 21, 2023 | June 30, 2028 | |
Comment |
Percentage of contractor staff trained on SEA and SH components of the Codes of Conduct | Value | 0.00 | 0.00 | 100.00 |
Date | October 28, 2020 | September 21, 2023 | June 30, 2028 | |
Comment |
Length of new vegetated coastal scour protection | Value | 0.00 | 0.00 | 850.00 |
Date | October 28, 2020 | September 21, 2023 | June 30, 2028 | |
Comment |
Reduction in the gap between percentage of men and women with driver licenses | Value | 0.00 | 0.00 | 3.00 |
Date | October 28, 2020 | September 21, 2023 | June 30, 2028 | |
Comment |
Climate resilient design packages completed | Value | 0.00 | 0.00 | 2.00 |
Date | October 28, 2020 | September 21, 2023 | June 30, 2027 | |
Comment |
Institutional and Governance Review completed | Value | No | No | Yes |
Date | October 28, 2020 | September 21, 2023 | June 30, 2028 | |
Comment |
Hydraulic designs considering hydrology, catchment area and tidal flows completed, with appropriate climate change-informed design factors applied | Value | No | No | Yes |
Date | October 28, 2020 | September 21, 2023 | June 30, 2028 | |
Comment |
Length of road upgraded using participatory design approaches | Value | 0.00 | 0.00 | 6.30 |
Date | October 28, 2020 | September 21, 2023 | June 30, 2028 | |
Comment |
?Number of direct and indirect beneficiaries having enhanced access to road transport services | Value | 0.00 | 0.00 | 63120.00 |
Date | October 30, 2020 | September 21, 2023 | June 30, 2028 | |
Comment |
Reduction in the gap between percentage of men and women employed in technical roles within DoTC&I and State transport agencies | Value | 0.00 | 0.00 | 15.00 |
Date | October 28, 2020 | September 21, 2023 | June 30, 2028 | |
Comment |