Development of Pumped Storage Hydropower in Java Bali System Project

Abstract*

The development objective of the Development of Pumped Storage Hydropower in the Java-Bali Project for Indonesia is to support Indonesia’s energy transition and decarbonization goal by: (i) developing the first large-scale pumped storage hydropower to improve power generation peaking and storage capacity of the Java-Bali grid; and (ii) strengthening PT Perusahaan Listrik Negara (Persero) (PLN’s) capacity for hydropower development and management...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective of the Project is to support Indonesia’s energy transition and decarbonization goal by: (i) developing the first large-scale pumped storage hydropower to improve power generation peaking and storage capacity of the Java-Bali grid; and (ii) strengthening PLN’s capacity for hydropower development and management.

Key Details

Project Details

  • P172256

  • Active

  • Puguh Imanto , Nicolas Sans , Hiroaki Yamada

  • Republic of Indonesia

  • Indonesia

  • January 30, 2020

  • (as of board presentation)

    September 10, 2021

  • March 17, 2022

  • US$ 755.00 million

  • PT Perusahaan Listrik Negara (PLN)

  • East Asia and Pacific

  • 2022

  • US$ 610.00 million

  • N/A

  • June 24, 2024

  • September 15, 2027

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Asian Infrastructure Investment Bank 230.00
International Bank for Reconstruction and Development 380.00
Borrower/Recipient 145.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment 380.00
IDA Commitment N/A
IBRD + IDA Commitment 380.00
Lending Instrument
Grant Amount 230.00
Total Project Cost** 755.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Feb 1, 2023 IBRD-92780 Int Charges 478,904.10
Aug 1, 2023 IBRD-92780 Int Charges 471,095.88
Mar 25, 2022 IBRD-92780 Fee Charges 950,000.00
Aug 1, 2022 IBRD-92780 Int Charges 434,657.53
Sep 10, 2021 IBRD-92780 Loan Commitment 380,000,000.00
May 28, 2024 IBRD-92780 Loan Disb 314,680.22
Aug 1, 2024 IBRD-92780 Int Charges 69.83
Aug 1, 2024 IBRD-92780 Int Charges 19,701.68
Aug 1, 2024 IBRD-92780 Int Charges 471,694.66
Aug 1, 2024 IBRD-92780 Int Charges 1,852.11
Feb 1, 2024 IBRD-92780 Int Charges 1,432.28
Feb 1, 2024 IBRD-92780 Int Charges 478,561.44
Apr 30, 2024 IBRD-92780 Loan Disb 299,669.66
Apr 30, 2024 IBRD-92780 Loan Disb 96,662.42
Dec 13, 2023 IBRD-92780 Loan Disb 104,245.61
Dec 13, 2023 IBRD-92780 Loan Disb 100,037.38
Sep 6, 2023 IBRD-92780 Loan Disb 51,700.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Satisfactory 2024-10-27
Overall Implementation Progress (IP) Moderately Satisfactory 2024-10-27
Progress towards achievement of PDO Moderately Satisfactory 2024-10-27
Financial Management Moderately Satisfactory 2024-10-27
Procurement Moderately Satisfactory 2024-10-27
Project Management Satisfactory 2024-10-27

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Completion of the Java-Bali System Master PlanValueJava-Bali System Master Plan not yet preparedJava-Bali System Master Plan not yet preparedJava-Bali System Master Plan completed
    DateJune 28, 2021February 29, 2024September 30, 2027
    Comment
  • Peaking capacity added to the Java-Bali grid from the UCPSValue0.000.001040.00
    DateJune 28, 2021February 29, 2024September 30, 2027
    Comment
  • Satisfactory implementation of the Environmental and Social Management Plan (ESMP) for the UCPSValueESMP not yet implementedSatisfactory Implementation of ESMPSatisfactory implementation of ESMP
    DateJune 28, 2021February 29, 2024September 30, 2027
    Comment
  • Power storage capacity added to the Java-Bali grid from the UCPS (GWh)Value0.000.001478.70
    DateJune 28, 2021February 29, 2024September 30, 2027
    Comment
  • Preparation of Operation and Maintenance Plan (OMP) for the UCPSValueOMP not yet preparedOMP not yet preparedOMP has been prepared
    DateJune 28, 2021February 29, 2024September 30, 2027
    Comment
  • (iii) reduction of the GHG emission enabled by the UCPS by 2040 (MtCO2e)Value0.000.007.30
    DateJune 28, 2021February 29, 2024September 30, 2027
    Comment
  • Satisfactory implementation of the Operation and Maintenance Plan (OMP)ValueOMP not yet in placeOMP not yet in placeOMP has been satisfactorily implemented
    DateJune 28, 2021February 29, 2024September 30, 2027
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Construction of UCPS civil worksValue0.002.65100.00
    DateJune 28, 2021February 29, 2024September 30, 2027
    Comment
  • Project–related grievances registered under the Project grievance redress mechanism and addressedValue0.000.00100.00
    DateJune 28, 2021February 29, 2024September 30, 2027
    Comment
  • Supply, erection and commissioning of equipmentValue0.000.00100.00
    DateJune 28, 2021February 29, 2024September 30, 2027
    Comment
  • Matenggeng Detailed Design and Tender Documents have been completedValueNoNoYes
    DateJune 28, 2021February 29, 2024September 30, 2027
    Comment
  • Construction of the transmission lineValue0.000.00100.00
    DateJune 28, 2021February 29, 2024September 30, 2027
    Comment
  • Matenggeng ESIA and LARAP have been completedValueNoNoYes
    DateJune 28, 2021February 29, 2024September 30, 2027
    Comment
  • Preparation of Emergency Preparedness Plan (EPP)ValueAn EPP up to international standard one year beforEPP has not yet been preparedEPP has been prepared
    DateJune 28, 2021February 29, 2024September 30, 2027
    Comment
  • Poko Detailed Design and Tender Documents have been completedValueNoNoYes
    DateJune 28, 2021February 29, 2024September 30, 2027
    Comment
  • Preparation of an Reservoir Impoundment Plan (RIP)ValueRIP has not yet been preparedRIP has not yet been preparedRIP has been prepared
    DateJune 28, 2021February 29, 2024September 30, 2027
    Comment
  • Women in technical roles in PLN CisokanValue5.005.0020.00
    DateJune 28, 2021February 29, 2024September 30, 2027
    Comment
  • Trial run results of the UCPS meeting PLN’s performance targetsValueTrial run results not yet startedTrial run results not yet startedTrial run results of the UCPS completed and meetin
    DateJune 28, 2021February 29, 2024September 30, 2027
    Comment
  • Labor-related grievances registered under the Project grievance redress mechanismValue0.000.00100.00
    DateJune 28, 2021February 29, 2024September 30, 2027
    Comment
  • Labor-related grievances registered under the Project grievance redress mechanism and addressed/resolved within the stipulated service standards for response timeValue0.000.00100.00
    DateJune 28, 2021February 29, 2024September 30, 2027
    Comment