Financier | Commitments |
---|---|
Asian Infrastructure Investment Bank | 230.00 |
International Bank for Reconstruction and Development | 380.00 |
Borrower/Recipient | 145.00 |
P172256
Active
Puguh Imanto , Nicolas Sans , Hiroaki Yamada
Republic of Indonesia
January 30, 2020
(as of board presentation)
September 10, 2021
March 17, 2022
US$ 755.00 million
PT Perusahaan Listrik Negara (PLN)
2022
US$ 610.00 million
N/A
June 24, 2024
September 15, 2027
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Asian Infrastructure Investment Bank | 230.00 |
International Bank for Reconstruction and Development | 380.00 |
Borrower/Recipient | 145.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 380.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 380.00 |
Lending Instrument | |
---|---|
Grant Amount | 230.00 |
Total Project Cost** | 755.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Feb 1, 2023 | IBRD-92780 | Int Charges | 478,904.10 |
Aug 1, 2023 | IBRD-92780 | Int Charges | 471,095.88 |
Mar 25, 2022 | IBRD-92780 | Fee Charges | 950,000.00 |
Aug 1, 2022 | IBRD-92780 | Int Charges | 434,657.53 |
Sep 10, 2021 | IBRD-92780 | Loan Commitment | 380,000,000.00 |
May 28, 2024 | IBRD-92780 | Loan Disb | 314,680.22 |
Aug 1, 2024 | IBRD-92780 | Int Charges | 69.83 |
Aug 1, 2024 | IBRD-92780 | Int Charges | 19,701.68 |
Aug 1, 2024 | IBRD-92780 | Int Charges | 471,694.66 |
Aug 1, 2024 | IBRD-92780 | Int Charges | 1,852.11 |
Feb 1, 2024 | IBRD-92780 | Int Charges | 1,432.28 |
Feb 1, 2024 | IBRD-92780 | Int Charges | 478,561.44 |
Apr 30, 2024 | IBRD-92780 | Loan Disb | 299,669.66 |
Apr 30, 2024 | IBRD-92780 | Loan Disb | 96,662.42 |
Dec 13, 2023 | IBRD-92780 | Loan Disb | 104,245.61 |
Dec 13, 2023 | IBRD-92780 | Loan Disb | 100,037.38 |
Sep 6, 2023 | IBRD-92780 | Loan Disb | 51,700.00 |
Name | Review | Date |
---|---|---|
Monitoring and Evaluation | Satisfactory | 2024-10-27 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-10-27 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-10-27 |
Financial Management | Moderately Satisfactory | 2024-10-27 |
Procurement | Moderately Satisfactory | 2024-10-27 |
Project Management | Satisfactory | 2024-10-27 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Completion of the Java-Bali System Master Plan | Value | Java-Bali System Master Plan not yet prepared | Java-Bali System Master Plan not yet prepared | Java-Bali System Master Plan completed |
Date | June 28, 2021 | February 29, 2024 | September 30, 2027 | |
Comment |
Peaking capacity added to the Java-Bali grid from the UCPS | Value | 0.00 | 0.00 | 1040.00 |
Date | June 28, 2021 | February 29, 2024 | September 30, 2027 | |
Comment |
Satisfactory implementation of the Environmental and Social Management Plan (ESMP) for the UCPS | Value | ESMP not yet implemented | Satisfactory Implementation of ESMP | Satisfactory implementation of ESMP |
Date | June 28, 2021 | February 29, 2024 | September 30, 2027 | |
Comment |
Power storage capacity added to the Java-Bali grid from the UCPS (GWh) | Value | 0.00 | 0.00 | 1478.70 |
Date | June 28, 2021 | February 29, 2024 | September 30, 2027 | |
Comment |
Preparation of Operation and Maintenance Plan (OMP) for the UCPS | Value | OMP not yet prepared | OMP not yet prepared | OMP has been prepared |
Date | June 28, 2021 | February 29, 2024 | September 30, 2027 | |
Comment |
(iii) reduction of the GHG emission enabled by the UCPS by 2040 (MtCO2e) | Value | 0.00 | 0.00 | 7.30 |
Date | June 28, 2021 | February 29, 2024 | September 30, 2027 | |
Comment |
Satisfactory implementation of the Operation and Maintenance Plan (OMP) | Value | OMP not yet in place | OMP not yet in place | OMP has been satisfactorily implemented |
Date | June 28, 2021 | February 29, 2024 | September 30, 2027 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Construction of UCPS civil works | Value | 0.00 | 2.65 | 100.00 |
Date | June 28, 2021 | February 29, 2024 | September 30, 2027 | |
Comment |
Project–related grievances registered under the Project grievance redress mechanism and addressed | Value | 0.00 | 0.00 | 100.00 |
Date | June 28, 2021 | February 29, 2024 | September 30, 2027 | |
Comment |
Supply, erection and commissioning of equipment | Value | 0.00 | 0.00 | 100.00 |
Date | June 28, 2021 | February 29, 2024 | September 30, 2027 | |
Comment |
Matenggeng Detailed Design and Tender Documents have been completed | Value | No | No | Yes |
Date | June 28, 2021 | February 29, 2024 | September 30, 2027 | |
Comment |
Construction of the transmission line | Value | 0.00 | 0.00 | 100.00 |
Date | June 28, 2021 | February 29, 2024 | September 30, 2027 | |
Comment |
Matenggeng ESIA and LARAP have been completed | Value | No | No | Yes |
Date | June 28, 2021 | February 29, 2024 | September 30, 2027 | |
Comment |
Preparation of Emergency Preparedness Plan (EPP) | Value | An EPP up to international standard one year befor | EPP has not yet been prepared | EPP has been prepared |
Date | June 28, 2021 | February 29, 2024 | September 30, 2027 | |
Comment |
Poko Detailed Design and Tender Documents have been completed | Value | No | No | Yes |
Date | June 28, 2021 | February 29, 2024 | September 30, 2027 | |
Comment |
Preparation of an Reservoir Impoundment Plan (RIP) | Value | RIP has not yet been prepared | RIP has not yet been prepared | RIP has been prepared |
Date | June 28, 2021 | February 29, 2024 | September 30, 2027 | |
Comment |
Women in technical roles in PLN Cisokan | Value | 5.00 | 5.00 | 20.00 |
Date | June 28, 2021 | February 29, 2024 | September 30, 2027 | |
Comment |
Trial run results of the UCPS meeting PLN’s performance targets | Value | Trial run results not yet started | Trial run results not yet started | Trial run results of the UCPS completed and meetin |
Date | June 28, 2021 | February 29, 2024 | September 30, 2027 | |
Comment |
Labor-related grievances registered under the Project grievance redress mechanism | Value | 0.00 | 0.00 | 100.00 |
Date | June 28, 2021 | February 29, 2024 | September 30, 2027 | |
Comment |
Labor-related grievances registered under the Project grievance redress mechanism and addressed/resolved within the stipulated service standards for response time | Value | 0.00 | 0.00 | 100.00 |
Date | June 28, 2021 | February 29, 2024 | September 30, 2027 | |
Comment |