Kandy Multimodal Transport Terminal Development Project

Abstract*

The project is built around improving public transport within the Kandy city and integrating different modes of transport to improve efficiency and accessibility. Bus transport is considered as one of the most efficient modes of motorized public transport systems for urban mobility all over the world. It occupies minimum road space while carrying maximum passengers. The strategic transport intervention in the city of Kandy focuses on the augmentation...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective (PDO) is to enhance accessibility, efficiency, and safety for public transport users of the Kandy Multimodal Transport Terminal.

Key Details

Project Details

  • P172342

  • Active

  • Dung Hoang , Hongye Fan

  • Democratic Socialist Republic of Sri Lanka

  • Sri Lanka

  • December 3, 2019

  • (as of board presentation)

    May 18, 2020

  • May 6, 2021

  • US$ 69.33 million

  • Ministry of Highways

  • South Asia

  • 2020

  • US$ 69.33 million

  • N/A

  • February 29, 2024

  • May 31, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 69.33

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 69.33
IBRD + IDA Commitment 69.33
Lending Instrument
Grant Amount N/A
Total Project Cost** 69.33

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Aug 15, 2024 IDA-66230 Int Charges 11,965.70
Jun 20, 2024 IDA-66230 Loan Disb 1,330,209.20
Jun 20, 2024 IDA-66230 Loan Disb 305,207.47
Mar 1, 2024 IDA-66230 Loan Disb 1,119,995.50
Aug 20, 2024 IDA-66230 Loan Disb 894,804.80
Aug 26, 2024 IDA-66230 Loan Disb 300,000.00
Aug 15, 2024 IDA-66230 Loan Disb 209,448.19
Mar 11, 2024 IDA-66240 Loan Disb 3,896,502.50
Aug 8, 2024 IDA-66240 Loan Disb 197,871.27
Jun 7, 2022 IDA-66240 Loan Disb 460,000.00
Feb 15, 2022 IDA-66240 Int Charges 6,285.62
Feb 15, 2022 IDA-66240 Int Charges 44.08
May 6, 2021 IDA-66240 Loan Disb 12,500.00
May 6, 2021 IDA-66240 Fee Charges 12,500.00
Mar 18, 2024 IDA-66230 Loan Disb 1,518,409.60
Aug 15, 2021 IDA-66240 Int Charges 26.31
Aug 15, 2024 IDA-66230 Int Charges 10,439.21
Aug 15, 2022 IDA-66240 Int Charges 5,965.73
Aug 15, 2022 IDA-66240 Int Charges 1,326.59
Feb 15, 2023 IDA-66240 Int Charges 10,412.76
Feb 15, 2023 IDA-66240 Int Charges 761.36
Feb 15, 2023 IDA-66240 Int Charges 5,705.88
Aug 15, 2023 IDA-66240 Int Charges 495.45
Aug 15, 2023 IDA-66240 Int Charges 5,612.85
Aug 15, 2023 IDA-66240 Int Charges 12,895.28
Aug 15, 2024 IDA-66240 Int Charges 86.84
Aug 15, 2024 IDA-66240 Int Charges 786.07
Aug 15, 2024 IDA-66240 Int Charges 138,818.66
Aug 8, 2024 IDA-66240 Loan Disb -197,871.27
Mar 14, 2024 IDA-66240 Loan Disb 630,997.60
May 18, 2020 IDA-66230 Loan Commitment 64,333,000.00
May 18, 2020 IDA-66240 Loan Commitment 5,000,000.00
Aug 26, 2024 IDA-66240 Loan Disb -300,000.00
Feb 15, 2024 IDA-66240 Int Charges 137.40
Feb 15, 2024 IDA-66240 Int Charges 5,702.07
Feb 15, 2024 IDA-66240 Int Charges 14,979.80
Aug 15, 2021 IDA-66240 Int Charges 1,878.85
Aug 15, 2024 IDA-66230 Int Charges 10,439.21

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2025-02-11
Procurement Satisfactory 2025-02-11
Project Management Moderately Satisfactory 2025-02-11
Financial Management Satisfactory 2025-02-11
Monitoring and Evaluation Moderately Satisfactory 2025-02-11
Overall Implementation Progress (IP) Moderately Satisfactory 2025-02-11

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Availability of intermodal transfer passagesValueNoNoYes
    DateDecember 19, 2019August 29, 2023May 30, 2025
    Comment
  • Availability of designated waiting areas for passengers well-separated from bus bays and bus parking areasValueNoNoYes
    DateAugust 24, 2020August 29, 2023May 30, 2025
    Comment
  • Share of buses departing the terminal on timeValueNo timetable to monitor bus departure times at preBus departure schedules will be monitored and repoTarget of 85% buses departing on time based on the
    DateFebruary 28, 2020August 29, 2023May 30, 2025
    Comment
  • Percentage of passengers that feel safe to travel through the terminal (gender-disaggregated)ValueTo be updated during the first year of project impSurvey not conducted yetTo be determined based on the results of the initi
    DateJuly 1, 2020August 29, 2023September 30, 2025
    Comment
  • Presence of physical accommodation and facilities for people with disabilities and baggageValueNoNoYes
    DateDecember 19, 2019August 29, 2023May 30, 2025
    Comment
  • Availability of facilities inside the terminal to allow for effective social distancing and sanitationValueNoNoYes
    DateMarch 31, 2020August 29, 2023May 30, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • KMTT terminal built and in operationValueNoNoYes
    DateDecember 19, 2019August 29, 2023September 30, 2025
    Comment
  • A robust financial plan for the terminal’s operations and maintenance developedValueNoNoYes
    DateDecember 19, 2019August 29, 2023March 1, 2021
    Comment
  • Percentage of public transport users who are satisfied with the transport services of the terminal (gender-disaggregated)ValueTo be updated during the first year of project impThe baseline survey will be carried out during thiTo be determined based on the results of the initi
    DateJuly 1, 2020August 29, 2023September 30, 2025
    Comment
  • Institutional setup for the operations and maintenance of the terminal establishedValueNoNoYes
    DateDecember 19, 2019August 29, 2023June 30, 2022
    Comment
  • Percentage of grievances received related to the development of the KMTT addressed within one month of being recorded in the GRM databaseValue0.000.0090.00
    DateDecember 19, 2019August 29, 2023September 30, 2025
    Comment
  • Percentage of complaints related to terminal service provision received through the kiosk addressed within six months of being recordedValue0.000.0080.00
    DateDecember 19, 2019August 29, 2023December 20, 2024
    Comment
  • A road safety action plan developed for the Kandy cityValueNoNoYes
    DateDecember 19, 2019August 29, 2023December 31, 2024
    Comment
  • Number of women using the kiosk and/or hotline to report sexual harassment (per year)Value0.000.0080.00
    DateMarch 6, 2020August 29, 2023May 30, 2025
    Comment
  • Percentage of complaints related to sexual harassments in public transport received through the kiosk/hotline referred to relevant authorities or service providers within two weeks of being recordedValue0.000.0080.00
    DateDecember 19, 2019August 29, 2023December 20, 2024
    Comment
  • Percentage of female employment in bus transport operations at the KMTTValue3.003.0010.00
    DateMarch 5, 2020August 29, 2023September 30, 2025
    Comment