Financier | Commitments |
---|---|
Global Partnership for Social Accountability | 0.49 |
P172393
Closed
Cedric Ndizeye , Mariana Felicio
SAHA
February 13, 2020
(as of board presentation)
November 26, 2020
December 18, 2020
US$ 0.49 million
SAHA
2021
US$ 0.49 million
N/A
Low
June 30, 2025
TBD
BANK APPROVED
February 15, 2024
Financier | Commitments |
---|---|
Global Partnership for Social Accountability | 0.49 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 0.49 |
Total Project Cost** | 0.49 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Share of health service delivery issues and problems, or their determinants, identified and followed-up through the project’s collaborative social accountability mechanisms in target municipalities | Value | 7.00 | 7.00 | 40.00 |
Date | August 1, 2022 | August 1, 2022 | June 30, 2025 | |
Comment |
Share of improvements in the use and quality of health service delivery, or their determinants, through collaborative social accountability mechanisms supported by the project in target municipalities | Value | 0.00 | 0.00 | 30.00 |
Date | August 1, 2022 | August 1, 2022 | June 30, 2025 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Share of collaborative frameworks with involvement from at least 3 fit-for-purpose stakeholder groups that discuss routinely (every3 to 6 months) to address agreed upon pressing problems in the heal | Value | 7.00 | 7.00 | 40.00 |
Date | August 1, 2022 | August 1, 2022 | June 30, 2025 | |
Comment |
Share of target local civil society groups and other local target actors with increased capacities to use collaborative social accountability mechanisms for health | Value | 10.00 | 10.00 | 50.00 |
Date | August 1, 2022 | August 1, 2022 | June 30, 2025 | |
Comment |
SAHA and its project partners with improved capacity to engage meaningfully and collaboratively with other stakeholders at the municipal and central levels for the implementation of collaborative soci | Value | TBD | TBD | 40 |
Date | July 30, 2020 | October 20, 2021 | June 30, 2025 | |
Comment |
Share of civil society partnerships (SAHA and partners ) and relevant Public Sector institutions and committees (e.g.COSAN , CCDS, COGE) that engage in collaborative social accountability processes f | Value | 8.00 | 8.00 | 40.00 |
Date | August 1, 2022 | August 1, 2022 | June 30, 2025 | |
Comment |
Learn for Better Results - Number of examples where learning from the project’s monitoring and evaluation contributed to course correction/adjustment of the project’s operational strategy | Value | 0.00 | 0.00 | 2.00 |
Date | July 30, 2020 | August 1, 2022 | June 30, 2025 | |
Comment |
Stakeholders, including?target governments’ ministries and public sector institutions (PSIs), World Bank operations and/or?development partners, that indicate interest in: https://ssl.gstatic.com/ui | Value | TBD | TBD | TBD |
Date | July 30, 2020 | October 20, 2021 | June 30, 2025 | |
Comment |
Number of substantive lessons produced by the project’s collaborative social accountability processes that are taken up by target public sector institutions and development partners, as relevant in c | Value | 0.00 | 0.00 | 1.00 |
Date | July 30, 2020 | August 1, 2022 | June 30, 2025 | |
Comment |
Share of collaborative social accountability mechanisms that addressed the proximate causes of failures of effective implementationof national health and decentralization processes | Value | 10.00 | 10.00 | 40.00 |
Date | August 1, 2022 | August 1, 2022 | June 30, 2025 | |
Comment |