Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 370.00 |
National Government | 103.56 |
P172399
Active
Kathrine Kelm , Maria Quinones, Sarah Antos
Republic of the Philippines
November 15, 2019
(as of board presentation)
June 26, 2020
October 9, 2020
US$ 473.56 million
Department of Agrarian Reform
2020
US$ 370.00 million
N/A
High
December 31, 2027
No
BANK APPROVED
March 4, 2024
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 370.00 |
National Government | 103.56 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 370.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 370.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 473.56 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Jun 29, 2023 | IBRD-91410 | Loan Disb | 58,467,116.00 |
Nov 22, 2023 | IBRD-91410 | Loan Disb | -126,347,024.00 |
Dec 15, 2023 | IBRD-91410 | Int Charges | 3,584,940.00 |
Dec 15, 2023 | IBRD-91410 | Int Charges | 311,007.10 |
Dec 15, 2023 | IBRD-91410 | Int Charges | 36,098.60 |
Dec 15, 2022 | IBRD-91410 | Int Charges | 503,901.50 |
Dec 15, 2022 | IBRD-91410 | Int Charges | 428,698.20 |
Dec 15, 2021 | IBRD-91410 | Int Charges | 118,233.30 |
Dec 15, 2021 | IBRD-91410 | Int Charges | 442,641.44 |
Dec 15, 2021 | IBRD-91410 | Int Charges | 14,648.79 |
Jun 15, 2024 | IBRD-91410 | Int Charges | 440,740.53 |
Dec 15, 2021 | IBRD-91410 | Int Charges | 3,001.46 |
Nov 22, 2023 | IBRD-91410 | Loan Disb | 126,347,024.00 |
Jun 26, 2020 | IBRD-91410 | Loan Commitment | 370,000,000.00 |
Jun 15, 2024 | IBRD-91410 | Int Charges | 3,699,440.80 |
Apr 6, 2022 | IBRD-91410 | Loan Disb | 7,037,842.00 |
May 20, 2021 | IBRD-91410 | Loan Disb | 16,854,356.00 |
Jun 15, 2021 | IBRD-91410 | Int Charges | 458,113.70 |
Nov 6, 2020 | IBRD-91410 | Fee Charges | 925,000.00 |
Dec 15, 2020 | IBRD-91410 | Int Charges | 237,568.30 |
Nov 28, 2022 | IBRD-91410 | Loan Disb | 43,987,708.00 |
Jun 15, 2022 | IBRD-91410 | Int Charges | 436,848.34 |
Jun 15, 2022 | IBRD-91410 | Int Charges | 151,306.02 |
Jun 15, 2024 | IBRD-91410 | Int Charges | 81,466.30 |
Jun 12, 2024 | IBRD-91410 | Loan Disb | 23,268,768.00 |
Jun 15, 2024 | IBRD-91410 | Int Charges | 220,642.14 |
Jul 8, 2024 | IBRD-91410 | Loan Disb | -5,838,809.00 |
Jul 8, 2024 | IBRD-91410 | Loan Disb | 5,838,809.00 |
Jun 15, 2023 | IBRD-91410 | Int Charges | 5,121.85 |
Jun 15, 2023 | IBRD-91410 | Int Charges | 2,014,761.50 |
Jun 15, 2023 | IBRD-91410 | Int Charges | 376,615.47 |
Jun 15, 2023 | IBRD-91410 | Int Charges | 141,319.88 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Unsatisfactory | 2025-02-09 |
Monitoring and Evaluation | Satisfactory | 2025-02-09 |
Financial Management | Satisfactory | 2025-02-09 |
Monitoring and Evaluation | Satisfactory | 2025-02-09 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-02-09 |
Progress towards achievement of PDO | Moderately Satisfactory | 2025-02-09 |
Project Management | Moderately Satisfactory | 2025-02-09 |
Financial Management | Moderately Satisfactory | 2025-02-09 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2025-02-09 |
Procurement | Moderately Unsatisfactory | 2025-02-09 |
Project Management | Moderately Satisfactory | 2025-02-09 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2025-02-09 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Eligible collective titles (CLOAs) with a validated list of ARBs | Value | 0.00 | 60.58 | 80.00 |
Date | December 31, 2020 | November 15, 2023 | December 31, 2024 | |
Comment |
Eligible Individual titles issued | Value | 0.00 | 8.88 | 80.00 |
Date | December 31, 2020 | November 15, 2023 | December 31, 2024 | |
Comment |
Including individual titles in target areas with ownership, co-ownership, and marital property rights issued to females | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Establishment of improved rules and regulations for parcelization | Value | No | No | Yes |
Date | December 31, 2020 | November 15, 2023 | December 31, 2024 | |
Comment |
Project staff that received technical training | Value | 0.00 | 100.00 | 100.00 |
Date | December 31, 2020 | November 15, 2023 | December 31, 2024 | |
Comment |
M&E system developed and operational | Value | No | Yes | Yes |
Date | December 31, 2020 | November 15, 2023 | December 31, 2024 | |
Comment |
Collective CLOA Document Management System developed and operational | Value | No | No | Yes |
Date | January 31, 2020 | November 15, 2023 | December 31, 2024 | |
Comment |
Number of project provinces implementing the GRM strategy | Value | 0.00 | 76.00 | 76.00 |
Date | December 31, 2020 | November 15, 2023 | December 31, 2024 | |
Comment |
Percent of female project staff that receive training | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
CLOA Document Management System generates monitoring reports (gender disaggregated) | Value | No | No | Yes |
Date | December 31, 2020 | November 15, 2023 | December 31, 2024 | |
Comment |
ARBs informed of their rights and the procedures of the parcelization process (gender disaggregated) | Value | 0.00 | 64.91 | 100.00 |
Date | December 31, 2020 | November 15, 2023 | December 31, 2024 | |
Comment |
Percent of female ARBs informed of their rights | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Married ARBs with female spouses’ name on the title | Value | 0.00 | 46.38 | 40.00 |
Date | December 31, 2020 | November 15, 2023 | December 31, 2024 | |
Comment |