Skip to Main Navigation

Strengthen Ethiopia’s Adaptive Safety Net

Development Objective

The Project development objectives are (a) to expand geographic coverage and enhance service delivery of Ethiopia’s adaptive rural safety net to improve the well-being of extremely poor and vulnerable households in drought prone communities, and (b) in case of an Eligible Early Response Financing Event (“Eligible ERF Event”), respond promptly and effectively to it.

Key Details

Project Details

  • P172479

  • Active

  • Christabel Dadzie , Margaux Vinez, Roman Gebremedhin

  • Federal Democratic Republic of Ethiopia

  • Ethiopia

  • January 28, 2020

  • (as of board presentation)

    November 25, 2020

  • March 2, 2021

  • US$ 2671.26 million

  • Third Party Implementer in areas of High Risk of Ongoing Conflict,Ministry of Agriculture

  • Eastern and Southern Africa

  • 2021

  • US$ 1498.50 million

  • N/A

  • February 8, 2024

  • December 31, 2025

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
UK: British Department for International Development (DFID) 281.00
Free-standing Single Purpose Trust Fund 150.00
US: Agency for International Development (USAID) 430.00
IRELAND, Govt. of 55.00
IDA Credit 200.00
Borrower/Recipient 590.00
EC: European Commission 70.00
IDA Grant 312.50

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 512.50
IBRD + IDA Commitment 512.50
Lending Instrument
Grant Amount 986.00
Total Project Cost** 2671.26

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 26, 2023 IDA-67980 Loan Disb 17,003,658.00
Jun 2, 2023 IDA-67980 Loan Disb 1,867,810.00
Aug 8, 2023 IDA-67980 Loan Disb 19,909,976.00
Jun 1, 2023 IDA-67980 Loan Disb 6,743,102.50
Nov 25, 2020 IDA-D7450 Loan Commitment 312,500,000.00
Nov 25, 2020 IDA-67980 Loan Commitment 200,000,000.00
Feb 12, 2024 IDA-67980 Loan Disb 8,482,176.00
Mar 28, 2024 IDA-E3060 Loan Commitment 200,000,000.00
Sep 20, 2022 IDA-E1230 Loan Commitment 350,000,000.00
Sep 10, 2021 IDA-D9030 Loan Commitment 37,500,000.00
Jan 10, 2022 IDA-D7450 Loan Disb 65,020,000.00
Feb 1, 2022 IDA-D9030 Loan Disb 36,603,816.00
Apr 6, 2022 IDA-D7450 Loan Disb 63,961,948.00
Mar 31, 2022 IDA-D7450 Loan Disb 10,000,000.00
Nov 1, 2021 IDA-D7450 Loan Disb 50,793,632.00
Jan 25, 2023 IDA-E1230 Loan Disb 103,389,896.00
Feb 16, 2023 IDA-E1230 Loan Disb 65,000,000.00
May 15, 2023 IDA-D9030 Loan Disb 156,104.55
May 16, 2023 IDA-E1230 Loan Disb 172,410,096.00
Aug 16, 2023 IDA-E1230 Loan Disb 6,671,000.00
Aug 9, 2023 IDA-E1230 Loan Disb 1,806,201.00
Sep 16, 2021 IDA-D7450 Loan Disb 1,500,000.00
Jul 9, 2021 IDA-D7450 Loan Disb 21,485,466.00
Apr 20, 2021 IDA-D7450 Loan Disb 100,000,000.00
Apr 15, 2024 IDA-67980 Int Charges 4,053.23
Apr 15, 2024 IDA-67980 Int Charges 4,053.23
Apr 15, 2024 IDA-67980 Int Charges 358,097.60
Apr 15, 2024 IDA-67980 Int Charges 358,097.60
Oct 30, 2023 IDA-67980 Int Charges 1,289.82
Oct 30, 2023 IDA-67980 Int Charges 1,289.82
Oct 30, 2023 IDA-67980 Int Charges 256,173.80
Oct 30, 2023 IDA-67980 Int Charges 256,173.80
Jun 24, 2024 IDA-67980 Loan Disb 460,915.00
Jun 24, 2024 IDA-67980 Loan Disb 40,739,268.00
Jul 28, 2022 IDA-67980 Loan Disb 3,482,151.50
Apr 25, 2022 IDA-67980 Loan Disb 35,796,592.00
Apr 28, 2023 IDA-67980 Int Charges 176,311.55
Apr 28, 2023 IDA-67980 Int Charges 176,311.55
Apr 27, 2023 IDA-67980 Loan Disb 7,224,600.00
Apr 15, 2023 IDA-67980 Int Charges 4,297.65
Apr 15, 2023 IDA-67980 Int Charges 4,297.65
Nov 2, 2022 IDA-67980 Loan Disb 9,804,743.00
Oct 15, 2022 IDA-67980 Int Charges 124,993.16
Oct 15, 2022 IDA-67980 Int Charges 124,993.16

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2025-03-12
Procurement Moderately Unsatisfactory 2025-03-12
Financial Management Moderately Satisfactory 2025-03-12
Monitoring and Evaluation Moderately Satisfactory 2025-03-12
Overall Implementation Progress (IP) Moderately Satisfactory 2025-03-12
Project Management Moderately Satisfactory 2025-03-12
Procurement Moderately Satisfactory 2025-03-12
Project Management Moderately Satisfactory 2025-03-12
Progress towards achievement of PDO Moderately Satisfactory 2025-03-12
Financial Management Moderately Satisfactory 2025-03-12
Monitoring and Evaluation Moderately Satisfactory 2025-03-12
Overall Implementation Progress (IP) Moderately Satisfactory 2025-03-12

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • New woredas in which PSNP systems have been established and are being used for core PSNP paymentsValue0.0077.0070.00
    DateJune 30, 2020December 22, 2023June 30, 2025
    Comment
  • Percentage of payments made to core beneficiary households according to the program's performance standards for timelinessValue55.0077.0080.00
    DateJune 30, 2020December 22, 2023June 30, 2025
    Comment
  • Average number of months that PSNP households report experiencing food shortages in the past 12 monthsValue1.802.801.30
    DateJune 5, 2020December 22, 2023June 30, 2025
    Comment
  • Percentage of shock responsive transfers made to shock response beneficiaries according to the program's 45 days performance standards for timelinessValue0.0078.0065.00
    DateJune 30, 2020December 22, 2023June 30, 2025
    Comment
  • Impact on beneficiaries' per capita monthly total consumption expenditureValue5.605.6010.00
    DateJune 30, 2020December 22, 2023June 30, 2025
    Comment
  • Percentage of beneficiary households reporting use of harmful coping strategiesValue16.0053.0012.00
    DateJune 30, 2020December 22, 2023June 30, 2025
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of woredas using MIS for key program functionsValue0.000.00455.00
    DateJune 10, 2020December 22, 2023May 30, 2025
    Comment
  • Number of person months of shock responsive transfers assistance providedValue5,700,0003500000No target
    DateMay 21, 2020December 22, 2023June 30, 2025
    Comment
  • Percentage of GoE contribution to core PSNP financingValue15.0027.0032.00
    DateJune 4, 2020December 22, 2023June 30, 2025
    Comment
  • Preparation and adoption of a Geographic Expansion and Caseload Allocation PlanValueNo planNo updates made.Periodically updated plan in place
    DateMay 21, 2020December 22, 2023June 30, 2025
    Comment
  • Total cumulative area of land treated through area enclosures, rangeland management, soil and water conservation, forage and forestry activitiesValue0.00950523.702000000.00
    DateJuly 1, 2020December 22, 2023June 30, 2025
    Comment
  • Number of woredas with Phase 2 of MIS rolled out which reflects PSNP 5 design changesValue0.000.00455.00
    DateMay 21, 2020December 22, 2023June 30, 2025
    Comment
  • Key shock responsive systems established and operationalValueNoEDRMC prepared and published the EW dashboard and Early Warning dashboard published and Drought Resp
    DateMay 21, 2020December 22, 2023June 30, 2025
    Comment
  • Number of beneficiary households that have been assessed using a PMT for program exitValue0.000.00275000.00
    DateJune 10, 2020December 22, 2023June 30, 2025
    Comment
  • Percentage of annual public works planned following the GoE’s national watershed /rangeland guideline – TotalValue82.0070.8095.00
    DateJune 4, 2020December 22, 2023June 30, 2025
    Comment
  • HighlandsValue92.0060.3095.00
    DateMay 21, 2020December 22, 2023May 30, 2025
    Comment
  • Disaster Risk Financing Strategy prepared and adoptedValueNoNoYes
    DateMay 29, 2020December 22, 2023June 30, 2025
    Comment
  • Number of beneficiary households with complete information in the registryValue0.0092240.002200000.00
    DateJune 10, 2020December 22, 2023June 30, 2025
    Comment
  • LowlandsValue62.0083.7095.00
    DateMay 29, 2020December 22, 2023May 30, 2025
    Comment
  • Strategy to fully update registry designed, developed and implementedValueNoNoYes [Data collection completed]
    DateJune 10, 2020December 22, 2023June 30, 2025
    Comment
  • Percentage of PSNP core and shock response beneficiary households aware of KACValue35.0041.0060.00
    DateJune 10, 2020December 22, 2023June 30, 2025
    Comment
  • Percentage of annual public works projects constructed according to the PSNP agreed technical standards - TotalValue86.2086.5095.00
    DateJune 4, 2020December 22, 2023June 30, 2025
    Comment
  • HighlandsValue91.0087.3095.00
    DateMay 21, 2020December 22, 2023May 30, 2025
    Comment
  • Number of core payment beneficiary households for whom a client card has been issuedValue0.000.002200000.00
    DateJune 10, 2020December 22, 2023June 30, 2025
    Comment
  • LowlandsValue75.0085.5095.00
    DateMay 21, 2020December 22, 2023June 30, 2025
    Comment
  • Performance based incentives included in the MOUs with implementing partners are enforcedValueNoNoYes
    DateMay 21, 2020December 22, 2023June 30, 2025
    Comment
  • Percentage of annual public works projects screened in accordance with ESMF – TotalValue76.0086.50100.00
    DateJune 4, 2020December 22, 2023June 30, 2025
    Comment
  • HighlandsValue91.0087.80100.00
    DateMay 21, 2020December 22, 2023May 30, 2025
    Comment
  • LowlandsValue61.0084.90100.00
    DateMay 21, 2020December 22, 2023June 30, 2025
    Comment
  • Percentage of cumulative public works projects for which arrangements for operations and maintenance are established – TotalValue64.0074.5080.00
    DateJune 4, 2020December 22, 2023June 30, 2025
    Comment
  • HighlandsValue72.0076.5080.00
    DateMay 21, 2020December 22, 2023May 30, 2025
    Comment
  • LowlandsValue46.0072.1080.00
    DateMay 21, 2020December 22, 2023May 30, 2025
    Comment
  • Number of Seqota declaration PSNP woredas with a minimum of 8 child-care centers establishedValue0.000.0030.00
    DateMay 21, 2020December 22, 2023May 30, 2025
    Comment
  • Number of children aged 1-5 years enrolled in child-care centersValue0.000.004500.00
    DateMay 21, 2020December 22, 2023May 30, 2025
    Comment
  • Core beneficiary households receiving their benefits in electronic accountsValue1037528.001016878.001500000.00
    DateMay 21, 2020December 22, 2023June 30, 2025
    Comment
  • Percentage of females who own and operate electronic accountsValue46.0047.8050.00
    DateOctober 7, 2020December 22, 2023June 30, 2025
    Comment
  • Increase in average wage rate relative to the annual general CPI increase, for cash transfers beneficiariesValue0.0097.00100.00
    DateMay 21, 2020December 22, 2023June 27, 2025
    Comment
  • Number of clients with a business plan financed through livelihood grant/credit - TotalValue0.000.00550000.00
    DateMay 21, 2020December 22, 2023June 30, 2025
    Comment
  • Off-farmValue0.000.0030250.00
    Date
    Comment
  • FemaleValue0.000.0060500.00
    Date
    Comment
  • Number of eligible beneficiaries who received livelihood grant - TotalValue0.000.00167000.00
    DateJune 10, 2020December 22, 2023June 30, 2025
    Comment
  • Off-farmValue0.000.0018370.00
    Date
    Comment
  • FemaleValue0.000.0018370.00
    Date
    Comment
  • Number of youth clients with business plans financed or enrolled in the wage employment pathwayValue0.000.00231000.00
    DateMay 21, 2020December 22, 2023June 27, 2025
    Comment
  • Number of youth who received livelihood grantValue0.000.0015431.00
    Date
    Comment
  • Beneficiaries of social safety net programsValue7997218.006986464.007997218.00
    DateJune 30, 2020December 22, 2023June 30, 2025
    Comment
  • Beneficiaries of social safety net programs - FemaleValue4131994.004131994.004131994.00
    Date
    Comment
  • Beneficiaries of Safety Nets programs - Unconditional cash transfers (number)Value1193448.00890104.001193448.00
    DateJune 30, 2020December 22, 2023June 30, 2025
    Comment
  • Beneficiaries of Safety Nets programs - Cash-for-work, food-for-work and public works (number)Value6803770.006096360.006803770.00
    DateJune 30, 2020December 22, 2023June 30, 2025
    Comment