The proposed US$24.58 million GEF grant will support the Ministry of Environment (MMA) and the Ministry of Agriculture, Livestock and Food Supply (MAPA) to jointly promote a Sustainable Landscape Management (SLM) approach on areas with highly intensified agriculture and pasture lands that have negative impacts on environmental assets with national and global relevance, such as major freshwater-producing basins and important endemic species. The approach...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

To increase the area under sustainable land management and promote the integration of food systems and sustainable landscapes, conservation of biodiversity and recovery of degraded areas in selected beef cattle and soybean landscapes.

Key Details

Project Details

  • P172497

  • Active

  • Leonardo Bichara Rocha , Maria Lange

  • IICA

  • Brazil

  • April 10, 2020

  • (as of board presentation)

    November 4, 2022

  • N/A

  • US$ 24.58 million

  • Ministério do Meio Ambiente (MMA),Ministério da Agricultura, Pecuária e Abastecimento (MAPA)

  • Latin America and Caribbean

  • 2023

  • US$ 24.58 million

  • N/A

  • February 19, 2024

  • November 30, 2027

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Global Environment Facility (GEF) 24.58

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment N/A
IBRD + IDA Commitment N/A
Lending Instrument
Grant Amount 24.58
Total Project Cost** 24.58

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Monitoring and Evaluation Moderately Satisfactory 2025-02-09
Overall Implementation Progress (IP) Moderately Satisfactory 2025-02-09
Financial Management Satisfactory 2025-02-09
Procurement Moderately Satisfactory 2025-02-09
Project Management Moderately Satisfactory 2025-02-09

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Area of landscape under improved practicesValue0.000.00578000.00
    DateSeptember 22, 2020February 19, 2024June 30, 2026
    Comment
  • Area of landscapes under improved management to benefit biodiversityValue0.000.0078000.00
    DateAugust 30, 2022February 19, 2024August 30, 2027
    Comment
  • Area of land restoredValue0.000.0049800.00
    DateSeptember 22, 2020February 19, 2024June 30, 2026
    Comment
  • Greenhouse gas emissions avoided and carbon sequesteredValue0.000.0019822929.00
    DateSeptember 22, 2020February 19, 2024August 31, 2026
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Direct beneficiaries satisfied with technical assistance received under the projectValue0.000.0080.00
    DateSeptember 22, 2020February 19, 2024June 30, 2026
    Comment
  • Participants in distance education activities receiving information on sustainable agriculture practices - WomenValue0.000.001500.00
    DateSeptember 22, 2022February 19, 2024August 31, 2026
    Comment
  • Participants attending project events, seminars, field days, and other meetingsValue0.000.002730.00
    DateAugust 22, 2022February 19, 2024September 30, 2027
    Comment
  • Environmental and social risk management plan strengthened and adopted by the projectValueNoNoYes
    DateSeptember 22, 2020February 19, 2024June 30, 2026
    Comment
  • Area of landscapes under sustainable land management in production systemsValue0.000.00500000.00
    DateSeptember 22, 2020February 19, 2024August 31, 2026
    Comment
  • Area of forest and forest land restoredValue0.000.009800.00
    DateSeptember 22, 2020February 19, 2024June 30, 2026
    Comment
  • Number of direct beneficiaries of project activitiesValue0.000.0010500.00
    DateAugust 22, 2022February 19, 2024September 30, 2027
    Comment
  • Actors trained and participating in project activities under the scope of the Regional ConsortiaValue0.000.00270.00
    DateSeptember 22, 2020February 19, 2024August 31, 2026
    Comment
  • Farmers and rural workers who receive information on sustainable agriculture practicesValue0.000.002500.00
    DateSeptember 22, 2020February 19, 2024August 31, 2026
    Comment
  • Area of degraded agricultural lands restoredValue0.000.0040000.00
    DateSeptember 22, 2020February 19, 2024June 30, 2026
    Comment
  • Number of direct beneficiaries of project activities - WomenValue0.000.003675.00
    DateAugust 22, 2022February 19, 2024September 30, 2027
    Comment
  • Records of knowledge generated by the project on selected platformsValue0.000.0025.00
    DateSeptember 22, 2020February 19, 2024August 31, 2026
    Comment
  • Farmers and rural workers who receive information on sustainable agriculture practices - WomenValue0.000.00750.00
    DateSeptember 22, 2022February 19, 2024August 31, 2026
    Comment
  • Participants in distance education activities receiving information on sustainable agriculture practicesValue0.000.005000.00
    DateSeptember 22, 2020February 19, 2024August 31, 2026
    Comment
  • Project knowledge management annual eventsValue0.000.005.00
    DateSeptember 22, 2020February 19, 2024August 31, 2026
    Comment
  • Consortia created or strengthened by the projectValue0.000.009.00
    DateSeptember 22, 2020February 19, 2024August 31, 2026
    Comment