Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 200.00 |
P172548
Active
Karin Shepardson , Nobuhiko Daito
Arab Republic of Egypt
December 20, 2019
(as of board presentation)
September 30, 2020
June 9, 2021
US$ 200.00 million
Ministry of Environment
2021
US$ 200.00 million
N/A
July 12, 2024
December 31, 2026
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 200.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 200.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 200.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 200.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Oct 1, 2023 | IBRD-91660 | Int Charges | 518,938.22 |
Nov 14, 2023 | IBRD-91660 | Loan Disb | 334,845.97 |
Jan 10, 2024 | IBRD-91660 | Loan Disb | 1,128,348.60 |
Aug 22, 2024 | IBRD-91660 | Loan Disb | 815,313.30 |
Aug 22, 2024 | IBRD-91660 | Loan Disb | 17,452.43 |
Apr 1, 2024 | IBRD-91660 | Int Charges | 8,334.62 |
Aug 19, 2024 | IBRD-91660 | Loan Disb | 783,493.80 |
Mar 6, 2024 | IBRD-91660 | Loan Disb | 1,528,378.40 |
Jun 9, 2021 | IBRD-91660 | Loan Disb | 500,000.00 |
Jun 9, 2021 | IBRD-91660 | Fee Charges | 500,000.00 |
Apr 1, 2022 | IBRD-91660 | Int Charges | 1,989.04 |
Apr 1, 2022 | IBRD-91660 | Int Charges | 229,934.05 |
Apr 1, 2022 | IBRD-91660 | Int Charges | 109,255.24 |
Sep 27, 2021 | IBRD-91660 | Loan Disb | 15,000,000.00 |
Oct 1, 2021 | IBRD-91660 | Int Charges | 2,280.00 |
Nov 17, 2021 | IBRD-91660 | Loan Disb | 9,541.98 |
Nov 18, 2021 | IBRD-91660 | Loan Disb | 926.15 |
Nov 18, 2021 | IBRD-91660 | Loan Disb | 9,548.06 |
Nov 18, 2021 | IBRD-91660 | Loan Disb | 11,457.67 |
Nov 18, 2021 | IBRD-91660 | Loan Disb | 7,638.45 |
Nov 18, 2021 | IBRD-91660 | Loan Disb | 3,182.69 |
Oct 1, 2021 | IBRD-91660 | Int Charges | 259,472.61 |
Nov 28, 2022 | IBRD-91660 | Loan Disb | 221,986.36 |
Dec 1, 2022 | IBRD-91660 | Loan Disb | 22,179.03 |
Dec 30, 2021 | IBRD-91660 | Loan Disb | 3,182.69 |
Dec 30, 2021 | IBRD-91660 | Loan Disb | 6,365.37 |
Dec 30, 2021 | IBRD-91660 | Loan Disb | 7,638.45 |
Dec 30, 2021 | IBRD-91660 | Loan Disb | 6,365.37 |
Dec 30, 2021 | IBRD-91660 | Loan Disb | 3,472.31 |
Dec 30, 2021 | IBRD-91660 | Loan Disb | 5,092.30 |
Apr 1, 2022 | IBRD-91660 | Int Charges | 410.96 |
Sep 30, 2020 | IBRD-91660 | Loan Commitment | 200,000,000.00 |
Aug 2, 2022 | IBRD-91660 | Loan Disb | 121,506.97 |
Apr 1, 2023 | IBRD-91660 | Int Charges | 49.94 |
Apr 1, 2023 | IBRD-91660 | Int Charges | 21,092.33 |
Apr 1, 2023 | IBRD-91660 | Int Charges | 229,542.02 |
Apr 1, 2023 | IBRD-91660 | Int Charges | 420,094.25 |
Oct 1, 2022 | IBRD-91660 | Int Charges | 231,113.66 |
Oct 1, 2022 | IBRD-91660 | Int Charges | 232,801.38 |
Oct 31, 2023 | IBRD-91660 | Loan Disb | 211,463.33 |
Oct 31, 2023 | IBRD-91660 | Loan Disb | 437,232.66 |
Apr 1, 2024 | IBRD-91660 | Int Charges | 228,491.45 |
Apr 1, 2024 | IBRD-91660 | Int Charges | 613,201.94 |
Aug 14, 2024 | IBRD-91660 | Loan Disb | 99,176.38 |
Oct 1, 2023 | IBRD-91660 | Int Charges | 9,232.17 |
Oct 1, 2023 | IBRD-91660 | Int Charges | 230,705.25 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Satisfactory | 2024-10-02 |
Monitoring and Evaluation | Moderately Unsatisfactory | 2024-10-02 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2024-10-02 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-10-02 |
Financial Management | Moderately Satisfactory | 2024-10-02 |
Procurement | Moderately Unsatisfactory | 2024-10-02 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Reduction in Greenhouse gas emissions (CO2 equiv.) from municipal solid waste | Value | 0.00 | 0.00 | 30.00 |
Date | July 1, 2022 | December 11, 2023 | June 30, 2026 | |
Comment |
Greenhouse gas emissions (CO2 equiv.) from public buses on selected routes | Value | 100.00 | 100.00 | 77.00 |
Date | June 1, 2020 | July 10, 2023 | December 31, 2026 | |
Comment |
Targeted people taking self-protective action in response to alert of a high pollution event (Share of surveyed people adopting avoidance behavior) | Value | 0.00 | 0.00 | 5.00 |
Date | June 1, 2020 | December 11, 2023 | December 31, 2026 | |
Comment |
Reduction, avoidance of emissions of POPs to air from point and non-points sources (gTEQ) | Value | 71.40 | 71.40 | 64.24 |
Date | October 6, 2021 | July 10, 2023 | December 31, 2026 | |
Comment |
Reduction of large-scale solid waste fires per annum | Value | 0.00 | 0.00 | 20.00 |
Date | June 1, 2020 | December 11, 2023 | December 31, 2026 | |
Comment |
Black Carbon emissions from public buses | Value | 100.00 | 100.00 | 98.00 |
Date | June 1, 2020 | July 10, 2023 | December 31, 2026 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Bus service quality action plan elaborated, consulted and disclosed | Value | No | No | |
Date | ||||
Comment |
Increased percentage of women employed in the solid waste chain | Value | 0.00 | 0.00 | 10.00 |
Date | September 1, 2020 | December 11, 2023 | December 31, 2026 | |
Comment |
Perception of security among users of public e-bus | Value | TBD | TBD | TBD |
Date | October 20, 2021 | December 11, 2023 | December 31, 2026 | |
Comment |
People reached out with air quality and climate change information | Value | TBD | TBD | TBD |
Date | September 1, 2020 | December 11, 2023 | December 31, 2026 | |
Comment |
Perception of security among female users of public e-bus | Value | TBD | TBD | |
Date | ||||
Comment |
Perception of security among male users of public e-bus | Value | TBD | TBD | |
Date | ||||
Comment |
E-bus pilot implementation progress | Value | N/A | N/A | Satisfactory |
Date | October 11, 2021 | December 11, 2023 | December 31, 2026 | |
Comment |
Electric buses in operation | Value | No | No | |
Date | ||||
Comment |
Charging stations in operation (percentage) | Value | No | No | |
Date | ||||
Comment |
E-bus maintenance facilities in operation | Value | No | No | |
Date | ||||
Comment |
CTA staff trained for operation and maintenance efficiency improvement | Value | No | No | |
Date | ||||
Comment |
Monitoring of Key Performance Indicators (KPIs) for e-buses | Value | No | No | Yes |
Date | October 20, 2021 | December 11, 2023 | December 31, 2026 | |
Comment |
Average daily business day ridership on selected e-bus routes | Value | TBD | TBD | |
Date | ||||
Comment |
Level of satisfaction of stakeholders with the quality of project's engagement | Value | This is a project management related indicator, an | N/A yet, TBD as the project moves forward | The end target of the level of satisfaction will b |
Date | September 1, 2020 | July 10, 2023 | December 31, 2026 | |
Comment |
Integrated municipal solid waste facility established in Greater Cairo | Value | No | No | Yes |
Date | September 1, 2020 | December 11, 2023 | December 31, 2026 | |
Comment |
User satisfaction with bus service (percentage) | Value | TBD | TBD | TBD |
Date | October 20, 2021 | December 11, 2023 | December 31, 2026 | |
Comment |
Climate pollutant monitors (including Short Lived Climate Pollutants and GHGs) installed and operational in a select number of locations | Value | 0.00 | 0.00 | 12.00 |
Date | September 1, 2020 | December 11, 2023 | December 31, 2026 | |
Comment |
Number of emission control technologies / practices implemented | Value | 0.00 | 0.00 | 5.00 |
Date | October 6, 2021 | December 11, 2023 | December 31, 2026 | |
Comment |
Pilot Community-based Social Marketing (CBSM) initiatives implemented | Value | 0.00 | 0.00 | 2.00 |
Date | September 1, 2020 | December 11, 2023 | December 31, 2026 | |
Comment |
Percentage of?grievances received and addressed in a timely manner | Value | 0.00 | 0.00 | 80.00 |
Date | September 1, 2020 | December 11, 2023 | December 31, 2026 | |
Comment |
Healthcare waste facility established and operational in the 10th of Ramadan Site | Value | No | No | Yes |
Date | September 1, 2020 | December 11, 2023 | December 31, 2026 | |
Comment |
Improving municipal solid waste segragation at source at households level | Value | 0.00 | 0.00 | 1.00 |
Date | September 1, 2020 | December 11, 2023 | December 31, 2026 | |
Comment |
Institutional Air Quality response mechanism established and operational | Value | No | No | Yes |
Date | June 1, 2020 | December 11, 2023 | December 31, 2026 | |
Comment |
Number of emission control technologies/practices implemented in the eWaste Sector | Value | 0.00 | 0.00 | 3.00 |
Date | May 12, 2022 | December 11, 2023 | December 31, 2026 | |
Comment |
Female user satisfaction with bus service (percentage) | Value | TBD | TBD | |
Date | ||||
Comment |
Municipal Solid Waste Dump Sites Closed and Rehabilitated | Value | 0.00 | 0.00 | 1.00 |
Date | September 1, 2020 | December 11, 2023 | December 31, 2026 | |
Comment |
Number of emission control technologies/practices implemented in the healthcare waste sector | Value | 0.00 | 0.00 | 2.00 |
Date | May 12, 2022 | December 11, 2023 | December 31, 2026 | |
Comment |
Greater Cairo Climate and Air Quality Management Plan developed and submitted to the Council of Ministers | Value | No | No | Yes |
Date | June 1, 2020 | December 11, 2023 | December 31, 2026 | |
Comment |
Number of NGOs/CBOs led initiatives in collabration with local authorites | Value | 0.00 | 0.00 | 10.00 |
Date | September 1, 2020 | December 11, 2023 | December 31, 2026 | |
Comment |
Male user satisfaction with bus service (percentage) | Value | TBD | TBD | |
Date | ||||
Comment |
Solid Waste Management Unit in Qalyubia Governorate established with Operations Manual, monitoring and reporting systems (data bases, IT infrastructure and other tools) for solid waste management | Value | No | No | Yes |
Date | September 1, 2020 | December 11, 2023 | December 31, 2026 | |
Comment |
Number of women groups or CSOs engaged in monitoring SWM services | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |