Financier | Commitments |
---|---|
Inter-American Development Bank | 49.34 |
International Bank for Reconstruction and Development | 300.00 |
Borrower/Recipient | 227.26 |
P172689
Active
Lizmara Kirchner , Maria Ramirez
Argentine Republic
August 19, 2020
(as of board presentation)
February 25, 2021
September 21, 2021
US$ 576.60 million
Agua y Saneamientos Argentinos S.A. (AySA)
2021
US$ 349.34 million
N/A
January 26, 2024
May 26, 2026
BANK APPROVED
Financier | Commitments |
---|---|
Inter-American Development Bank | 49.34 |
International Bank for Reconstruction and Development | 300.00 |
Borrower/Recipient | 227.26 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 300.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 300.00 |
Lending Instrument | |
---|---|
Grant Amount | 49.34 |
Total Project Cost** | 576.60 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Feb 25, 2021 | IBRD-92070 | Loan Commitment | 300,000,000.00 |
Aug 15, 2022 | IBRD-92070 | Int Charges | 164,159.47 |
Aug 15, 2023 | IBRD-92070 | Int Charges | 299,409.53 |
Aug 15, 2023 | IBRD-92070 | Int Charges | 990,642.06 |
Aug 15, 2023 | IBRD-92070 | Int Charges | 448,136.30 |
Aug 15, 2023 | IBRD-92070 | Int Charges | 240,635.23 |
Feb 15, 2023 | IBRD-92070 | Int Charges | 814,715.25 |
Feb 15, 2023 | IBRD-92070 | Int Charges | 326,271.75 |
Feb 15, 2023 | IBRD-92070 | Int Charges | 25,434.28 |
Feb 15, 2023 | IBRD-92070 | Int Charges | 326,271.75 |
Jun 27, 2023 | IBRD-92070 | Loan Disb | 21,066,246.00 |
Aug 15, 2024 | IBRD-92070 | Int Charges | 261,848.56 |
Aug 15, 2024 | IBRD-92070 | Int Charges | 2,987,848.20 |
Aug 15, 2024 | IBRD-92070 | Int Charges | 13,891.22 |
Aug 15, 2024 | IBRD-92070 | Int Charges | 261,848.56 |
Dec 12, 2023 | IBRD-92070 | Loan Disb | 15,519,620.00 |
Feb 15, 2024 | IBRD-92070 | Int Charges | 196,689.14 |
Feb 15, 2024 | IBRD-92070 | Int Charges | 74,164.14 |
Feb 15, 2024 | IBRD-92070 | Int Charges | 203,759.31 |
Feb 15, 2024 | IBRD-92070 | Int Charges | 2,879,591.00 |
Feb 15, 2024 | IBRD-92070 | Int Charges | 7,070.18 |
Sep 21, 2021 | IBRD-92070 | Loan Disb | 750,000.00 |
Sep 21, 2021 | IBRD-92070 | Fee Charges | 750,000.00 |
Feb 15, 2022 | IBRD-92070 | Int Charges | 60,519.40 |
Feb 15, 2022 | IBRD-92070 | Int Charges | 253,726.03 |
Nov 23, 2021 | IBRD-92070 | Loan Disb | 15,000,000.00 |
Oct 12, 2022 | IBRD-92070 | Loan Disb | 37,034,320.00 |
Aug 15, 2022 | IBRD-92070 | Int Charges | 352,392.12 |
Aug 15, 2023 | IBRD-92070 | Int Charges | 54,201.62 |
Name | Review | Date |
---|---|---|
Monitoring and Evaluation | Satisfactory | 2024-12-04 |
Overall Implementation Progress (IP) | Unsatisfactory | 2024-12-04 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2024-12-04 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of households gaining access to safely managed water services | Value | 0.00 | 2595.00 | 35000.00 |
Date | March 1, 2021 | November 15, 2023 | September 30, 2024 | |
Comment |
Number of households gaining access to safely managed sanitation services | Value | 0.00 | 5459.00 | 76359.00 |
Date | March 1, 2021 | November 15, 2023 | September 30, 2025 | |
Comment |
Annual savings from operational and commercial efficiency measures ($/year) | Value | 0.00 | 705732.00 | 9528566.00 |
Date | March 1, 2021 | November 15, 2023 | May 29, 2026 | |
Comment |
Number of AySA’s emergency response mechanisms strenghtened | Value | 0.00 | 2.00 | 2.00 |
Date | March 1, 2021 | November 15, 2023 | March 1, 2024 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Increase in wastewater treatment capacity (m3/s) | Value | 2.26 | 2.26 | 3.98 |
Date | December 15, 2020 | November 15, 2023 | December 1, 2025 | |
Comment |
Length of water supply pipes replaced | Value | 0.00 | 121.00 | 510.00 |
Date | December 15, 2020 | November 15, 2023 | May 29, 2026 | |
Comment |
Prevention and Emergency Plan strengthened | Value | No | Yes | Yes |
Date | December 15, 2020 | November 15, 2023 | March 31, 2022 | |
Comment |
Increased pumping capacity in Belgrano WTP to deliver service to Florencio Varela (m3/h) | Value | 0.00 | 0.00 | 4000.00 |
Date | December 15, 2020 | November 15, 2023 | May 29, 2026 | |
Comment |
Number of sewage pumping stations where energy monitoring equipment will be installed | Value | 69.00 | 146.00 | 215.00 |
Date | December 15, 2020 | November 15, 2023 | September 30, 2024 | |
Comment |
Number of digital solutions implemented | Value | 0.00 | 1.00 | 5.00 |
Date | November 16, 2021 | November 15, 2023 | March 31, 2023 | |
Comment |
Number of cooperatives trained in the Agua / Cloaca + Trabajo programs | Value | 0.00 | 24.00 | 30.00 |
Date | December 15, 2020 | November 15, 2023 | May 29, 2026 | |
Comment |
Number of wells where energy monitoring equipment will be installed | Value | 0.00 | 320.00 | 800.00 |
Date | December 1, 2020 | November 15, 2023 | September 30, 2024 | |
Comment |
Mobile app for citizen engagement in operation | Value | No | Yes | Yes |
Date | December 15, 2020 | November 15, 2023 | March 31, 2022 | |
Comment |
Number of large consumers tele-metered | Value | 0.00 | 0.00 | 440.00 |
Date | December 15, 2020 | November 15, 2023 | December 15, 2021 | |
Comment |
CRM system for citizen engagement strategy built | Value | No | No | Yes |
Date | March 1, 2021 | November 15, 2023 | September 30, 2022 | |
Comment |
Number of micro-meters installed | Value | 0.00 | 20000.00 | 71400.00 |
Date | December 15, 2020 | November 15, 2023 | December 31, 2025 | |
Comment |
Increased share of female staff in management level positions at AySA | Value | 22.00 | 25.00 | 28.00 |
Date | December 15, 2020 | November 15, 2023 | March 31, 2026 | |
Comment |