Financier | Commitments |
---|---|
Free-standing Single Purpose Trust Fund | 26.78 |
P172753
Active
Denise Stolt , Vincent Perrot
National Recovery Program Bureau
St Maarten
July 10, 2020
(as of board presentation)
June 9, 2022
June 30, 2022
US$ 26.78 million
National Recovery Program Bureau
2022
US$ 26.78 million
N/A
Moderate
April 30, 2027
Yes
BANK APPROVED
January 4, 2024
Financier | Commitments |
---|---|
Free-standing Single Purpose Trust Fund | 26.78 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | N/A |
IBRD + IDA Commitment | N/A |
Lending Instrument | |
---|---|
Grant Amount | 26.78 |
Total Project Cost** | 26.78 |
Name | Review | Date |
---|---|---|
Financial Management | Satisfactory | 2025-06-25 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-06-25 |
Progress towards achievement of PDO | Moderately Satisfactory | 2025-06-25 |
Project Management | Satisfactory | 2025-06-25 |
Procurement | Moderately Satisfactory | 2025-06-25 |
Monitoring and Evaluation | Satisfactory | 2025-06-25 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Students with restored access to an adequate learning environment through the reconstruction of Sister Marie Laurence School | Value | 0.00 | 0.00 | 200.00 |
Date | June 30, 2022 | November 20, 2023 | April 30, 2027 | |
Comment |
Availability and use of an Integrated database at MECYS for evidence-based decision making in education, culture and sport sectors | Value | MECYS current Management Information System does n | The bidding package for the MMIS implementation fi | New MMIS is operational and rolled out internally |
Date | June 30, 2022 | November 20, 2023 | April 30, 2027 | |
Comment |
Girls with restored access to an adequate learning environment through the reconstruction of Sister Marie Laurence School | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Students benefitting from a package of interventions at CLB to address chronic behavior challenges | Value | 0.00 | 0.00 | 120.00 |
Date | June 30, 2022 | November 20, 2023 | April 30, 2027 | |
Comment |
Girls benefitting from a package of interventions at CLB to address chronic behavior challenges | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Library open and operating at full capacity for Sint Maarten’s population and visitors | Value | No | No | Yes |
Date | June 30, 2022 | November 20, 2023 | April 30, 2027 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Design and implementation of MMIS | Value | Fragmented system. Diagnostic of the MMIS complete | The bidding package for the MMIS implementation fi | Availability of an integrated database for Educati |
Date | June 30, 2022 | November 20, 2023 | April 30, 2027 | |
Comment |
Students benefiting from direct interventions to enhance learning | Value | 0.00 | 0.00 | 1000.00 |
Date | June 30, 2022 | November 20, 2023 | April 30, 2027 | |
Comment |
Reconstruction of the Library | Value | The Library has been damaged beyond repair. | No change from baseline | Library reopened and operating at full capacity |
Date | December 11, 2020 | November 20, 2023 | April 30, 2027 | |
Comment |
Mid-Term review undertaken | Value | No | No | Yes |
Date | June 30, 2022 | November 20, 2023 | April 30, 2027 | |
Comment |
Community consultations at schools and library with at least one written decision incorporated into the building and site design | Value | 0.00 | 0.00 | 100.00 |
Date | June 30, 2021 | November 20, 2023 | April 30, 2027 | |
Comment |
Students benefiting from direct interventions to enhance learning - Female | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Reconstruction of Sister Marie Laurence primary school | Value | Sister Marie Laurence Primary School needs needs t | No change from baseline | School reopened and ready to operate at full capac |
Date | December 11, 2020 | November 20, 2023 | April 30, 2027 | |
Comment |
Reconstruction of Charles Leopold Bell primary school | Value | School damaged beyond repair and students relocate | No change from baseline | School reopened and ready to operate at fully capa |
Date | December 11, 2020 | November 20, 2023 | April 30, 2027 | |
Comment |
Share of students having benefited from a package of intervention services at CLB transitioning back to general education schools per academic year | Value | 0.00 | 0.00 | 75.00 |
Date | June 30, 2022 | November 20, 2023 | April 30, 2027 | |
Comment |