Financier | Commitments |
---|---|
IDA Grant | 120.00 |
P172988
Active
Francis Ovanda Mbele , Peter Taniform
Ministry of Finance, Budget and Economic Planification
December 18, 2020
(as of board presentation)
September 30, 2022
May 10, 2023
US$ 120.00 million
Ministry of Trade, Transport, Industry and Tourism,Ministry of Infrastructure, Equipment and Housing
2023
US$ 120.00 million
N/A
High
December 31, 2027
Yes
BANK APPROVED
February 21, 2024
Financier | Commitments |
---|---|
IDA Grant | 120.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 120.00 |
IBRD + IDA Commitment | 120.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 120.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
May 10, 2023 | IDA-E1280 | Loan Disb | 1,168,951.20 |
Jun 8, 2023 | IDA-E1280 | Loan Disb | 3,413,800.00 |
Nov 10, 2023 | IDA-E1280 | Loan Disb | 123,156.58 |
Jan 18, 2024 | IDA-E1280 | Loan Disb | 386,042.44 |
Sep 30, 2022 | IDA-E1280 | Loan Commitment | 120,000,000.00 |
Aug 5, 2024 | IDA-E1280 | Loan Disb | 748,637.20 |
Aug 21, 2024 | IDA-E1280 | Loan Disb | 160,600.00 |
May 30, 2024 | IDA-E1280 | Loan Disb | 246,225.16 |
Sep 3, 2024 | IDA-E1280 | Loan Disb | 83,511.60 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2025-02-17 |
Project Management | Satisfactory | 2025-02-17 |
Financial Management | Moderately Satisfactory | 2025-02-17 |
Progress towards achievement of PDO | Satisfactory | 2025-02-17 |
Monitoring and Evaluation | Satisfactory | 2025-02-17 |
Overall Implementation Progress (IP) | Satisfactory | 2025-02-17 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
1. Travel time in NR-3 Bujumbura-Gitaza road section. | Value | 50.00 | 50.00 | 25.00 |
Date | May 31, 2022 | September 29, 2023 | December 31, 2026 | |
Comment |
4. Percentage of the Burundian section of the Central Corridor to Tanzania Dar Sea Port in good and fair condition | Value | 27.00 | 27.00 | 90.00 |
Date | May 31, 2022 | September 29, 2023 | December 31, 2026 | |
Comment |
2. Number of crash fatalities along the NR-3 section | Value | 50.00 | 50.00 | 15.00 |
Date | May 31, 2022 | September 29, 2023 | December 31, 2026 | |
Comment |
5. People benefiting from improved climate resilient roads | Value | 0.00 | 0.00 | 550000.00 |
Date | May 31, 2022 | September 29, 2023 | December 31, 2026 | |
Comment |
3. Number of days annually NR-3 Bujumbura-Gitaza section is impassable | Value | 5.00 | 5.00 | 0.00 |
Date | April 12, 2022 | September 29, 2023 | December 31, 2027 | |
Comment |
People benefiting from improved climate resilient road who are women | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Road safety strategy and action plan prepared | Value | No | No | Yes |
Date | April 8, 2022 | September 29, 2023 | December 31, 2027 | |
Comment |
Length of climate resilient road sections rehabilitated/upgraded in compliance with standards and technical specifications defined in works contracts | Value | 0.00 | 0.00 | 25.00 |
Date | May 31, 2022 | September 29, 2023 | December 31, 2026 | |
Comment |
Climate Resilient Road Infrastructure and Logistics Master Plan (CR-RILMP), and Climate Resilient Integrated Road Infrastructure and Logistics Strategy (CR-IRILS) developed and adopted | Value | No | No | Yes |
Date | April 8, 2022 | September 29, 2023 | December 31, 2027 | |
Comment |
Length of road network safety assessed | Value | 0.00 | 0.00 | 3500.00 |
Date | April 8, 2022 | September 29, 2023 | December 31, 2027 | |
Comment |
Length of Pilot Road sections upgraded to include NMT facilities | Value | 0.00 | 0.00 | 4.00 |
Date | April 8, 2022 | September 29, 2023 | December 31, 2027 | |
Comment |
Number of people enrolled in the First Generation of Climate Resilient Transport Specialists Programs | Value | 0.00 | 0.00 | 50.00 |
Date | April 8, 2022 | September 29, 2023 | December 31, 2027 | |
Comment |
Pilot vehicle Crash data recording and analysis system installed | Value | No | No | Yes |
Date | April 8, 2022 | September 29, 2023 | December 31, 2027 | |
Comment |
Number of social infrastructure implemented | Value | 0.00 | 0.00 | 5.00 |
Date | April 8, 2022 | September 29, 2023 | December 31, 2027 | |
Comment |
Share of people enrolled in the Program that are women | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Storage/market facilities reserved/leased for women | Value | 0.00 | 0.00 | 30.00 |
Date | May 20, 2022 | September 29, 2023 | December 31, 2026 | |
Comment |
Percentage of graduates who report being employed 12 months after they complete the internship of which are women | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Percentage of consultations conducted with women and groups in a situation of vulnerability,to select type and locations of social services | Value | 0.00 | 0.00 | 100.00 |
Date | May 20, 2022 | September 29, 2023 | December 31, 2027 | |
Comment |
Construction workers on project site who have signed the code of conduct (CoC) and attended the CoC training | Value | 0.00 | 0.00 | 100.00 |
Date | April 8, 2022 | September 29, 2023 | December 31, 2027 | |
Comment |
System is in place to receive and log grievances related to design, construction and operations of project road sections including GBV, within the stipulated services | Value | No | No | Yes |
Date | April 8, 2022 | September 29, 2023 | December 31, 2027 | |
Comment |
Percentage of graduates who report being employed 12 months after they complete the internship of which are women | Value | 0.00 | 0.00 | 20.00 |
Date | May 20, 2022 | September 29, 2023 | December 31, 2026 | |
Comment |