Bangladesh Road Safety Project

Development Objective

The Project Development Objective is to build road safety management capacity and achieve targeted reduction in traffic fatalities and serious injuries in Bangladesh.

Key Details

Project Details

  • P173019

  • Active

  • Cheick Diallo , Dipan Bose, Wameq Raza

  • People's Republic of Bangladesh

  • Bangladesh

  • November 2, 2020

  • (as of board presentation)

    March 28, 2022

  • June 12, 2023

  • US$ 527.00 million

  • Bangladesh Police,Directorate General of Health Services,Roads and Highways Division,Bangladesh Road Transport Authority

  • South Asia

  • 2022

  • US$ 358.00 million

  • N/A

  • April 9, 2024

  • June 30, 2027

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
IDA Credit 358.00
National Government 169.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 358.00
IBRD + IDA Commitment 358.00
Lending Instrument
Grant Amount N/A
Total Project Cost** 527.00

Summary Status of World Bank Financing (US$ Millions) as of February 28, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of February 28, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Jul 15, 2024 IDA-70590 Int Charges 45,467.69
Jul 15, 2024 IDA-70590 Int Charges 27,410.81
Jul 15, 2024 IDA-70590 Int Charges 27,410.81
May 6, 2024 IDA-70590 Loan Disb 19,000,000.00
Mar 28, 2022 IDA-70590 Loan Commitment 358,000,000.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Unsatisfactory 2024-12-16
Project Management Unsatisfactory 2024-12-16
Overall Implementation Progress (IP) Moderately Unsatisfactory 2024-12-16
Financial Management Satisfactory 2024-12-16
Monitoring and Evaluation Satisfactory 2024-12-16
Procurement Moderately Unsatisfactory 2024-12-16

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • National Road Safety Authority or equivalent is established and operational with adequate resource provisionValueNot establishedNot yet establishedRoad Safety authority or equivalent agency fully o
    DateMarch 1, 2022February 26, 2024March 31, 2027
    Comment
  • Reduction in fatal crashes per year on the highway pilot corridors and mass-action treatment roadsValue0.000.0030.00
    DateMarch 1, 2022February 26, 2024March 31, 2027
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of Police Stations recording and managing crash data using the developed systemValue0.000.0020.00
    DateAugust 23, 2021February 26, 2024March 31, 2027
    Comment
  • Multi-sectoral Safe Corridor Pilot Program on N4 and N6 highway section implementedValueNot implementedNot yet implementedRegular monitoring on the demonstration corridor c
    DateMarch 1, 2022February 26, 2024March 31, 2027
    Comment
  • National Road Safety Program launched along with budget allocated for a multi-year investment planValueNoNoYes
    DateMarch 1, 2022February 26, 2024March 31, 2025
    Comment
  • Gender-disaggregated data collection on road crashesValueNoNoYes
    DateMarch 15, 2022February 26, 2024January 1, 2027
    Comment
  • Launch of the motorcycle ambulance program in urban pilot areasValueNoNoYes
    DateAugust 23, 2021February 26, 2024January 1, 2027
    Comment
  • Trauma registries and trauma system improvement programs (TSIP) implemented in district hospitalsValue0.000.004.00
    DateAugust 23, 2021February 26, 2024March 31, 2027
    Comment
  • Gender Strategy and Action Plan implementedValueNoNoYes
    DateMarch 30, 2022February 26, 2024March 31, 2027
    Comment
  • Number of km with enhanced highway patrol capacity and surveillance equipmentValue0.000.00100.00
    DateAugust 23, 2021February 26, 2024January 1, 2027
    Comment
  • Development and launch of district road safety action plan in both pilot districtsValueNoNoYes
    DateAugust 23, 2021February 26, 2024March 31, 2027
    Comment
  • Share of project-related grievances received that are processed within the stipulated service standardsValue0.000.0080.00
    DateAugust 23, 2021February 26, 2024January 1, 2027
    Comment
  • User satisfaction with road safety conditionValueNot AvailableSurvey not yet conductedRoad user satisfaction rate increased by 50% compa
    DateAugust 23, 2021February 26, 2024March 31, 2027
    Comment
  • Share of trained bus employees reporting on intervening during an incident or taking action to improve female users’ safetyValue0.000.0050.00
    DateMarch 30, 2022February 26, 2024January 1, 2027
    Comment
  • Roll-out of free ambulance services accessible through a toll-free numberValueNot establishedMotorcycle ambulance service not yet launchedAmbulance services fully operational in at least 2
    DateMarch 1, 2022February 26, 2024March 31, 2027
    Comment
  • Portion of the surveyed mass action program network implemented with safety recommendationValue0.000.0050.00
    DateMarch 1, 2022February 26, 2024March 31, 2027
    Comment
  • Improved incident response times on N4 and N6 highwaysValue30.0030.0020.00
    DateMarch 1, 2022February 26, 2024March 31, 2027
    Comment