Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 512.15 |
P173025
Active
Ahmet Kindap , Zoe Trohanis, Bontje Zaengerling
Republic of Türkiye,Iller Bankasi Anonim Sirketi
June 20, 2020
(as of board presentation)
September 27, 2022
April 18, 2023
US$ 512.15 million
Urban Transformation Presidency,Urban Transformation Presidency,Local Authorities
2023
US$ 512.15 million
N/A
February 21, 2024
October 31, 2028
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 512.15 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 512.15 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 512.15 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 512.15 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Apr 5, 2024 | IBRD-94430 | Loan Disb | 13,002,000.00 |
Jul 17, 2024 | IBRD-94440 | Fee Charges | 463,201.12 |
Jul 17, 2024 | IBRD-94440 | Loan Disb | 463,201.12 |
Jun 5, 2023 | IBRD-94430 | Fee Charges | 883,509.10 |
Jun 26, 2023 | IBRD-94430 | Loan Disb | 1,090,400.00 |
Oct 15, 2023 | IBRD-94430 | Int Charges | 12,745.18 |
Oct 15, 2023 | IBRD-94430 | Int Charges | 544,439.80 |
Apr 15, 2024 | IBRD-94430 | Int Charges | 24,648.76 |
Sep 27, 2022 | IBRD-94440 | Loan Commitment | 173,618,000.00 |
Apr 15, 2024 | IBRD-94430 | Int Charges | 438,574.22 |
Sep 27, 2022 | IBRD-94430 | Loan Commitment | 338,529,984.00 |
Name | Review | Date |
---|---|---|
Financial Management | Moderately Satisfactory | 2024-12-19 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2024-12-19 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2024-12-19 |
Procurement | Moderately Unsatisfactory | 2024-12-19 |
Project Management | Moderately Satisfactory | 2024-12-19 |
Monitoring and Evaluation | Satisfactory | 2024-12-19 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
People in urban areas provided with access to climate and/or disaster resilient municipal infrastructure and services | Value | 0.00 | 0.00 | 1000000.00 |
Date | October 31, 2022 | December 6, 2023 | October 31, 2028 | |
Comment |
People living in housing retrofitted or reconstructed to reduce impacts of seismic and climate hazards | Value | 0.00 | 0.00 | 32000.00 |
Date | October 31, 2022 | December 6, 2023 | October 31, 2028 | |
Comment |
Of which women | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Of which women | Value | 0.00 | 0.00 | 50.00 |
Date | ||||
Comment |
Cities with improved livability, sustainability, and/or management | Value | 0.00 | 0.00 | 7.00 |
Date | October 31, 2022 | December 6, 2023 | October 31, 2028 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Municipal Urban Transformation Strategies prepared jointly with local authorities and citizen engagement, and using standardized approach for assessing risks | Value | 0.00 | 0.00 | 5.00 |
Date | October 31, 2022 | December 6, 2023 | October 31, 2028 | |
Comment |
Continued provision of differentiated loan terms based on income level | Value | No | Yes | Yes |
Date | October 31, 2022 | December 6, 2023 | October 31, 2028 | |
Comment |
Grievances addressed in accordance with the stipulated service standards (MoEUCC) | Value | 0.00 | 0.00 | 90.00 |
Date | October 31, 2022 | December 6, 2023 | October 31, 2028 | |
Comment |
Owners of housing or commericial units in risky buildings provided with affordable loans for resilient retrofitting or reconstruction under the Project | Value | 0.00 | 0.00 | 10000.00 |
Date | October 31, 2022 | December 6, 2023 | October 31, 2028 | |
Comment |
Beneficiaries who report that the Project has established effective engagement processes (MoEUCC) | Value | 0.00 | 0.00 | 90.00 |
Date | October 31, 2022 | December 6, 2023 | October 31, 2028 | |
Comment |
Municipal service delivery infrastructure (water, wastewater, sewage, drainage, etc.) retrofitted or constructed | Value | 0.00 | 0.00 | 1530.00 |
Date | October 31, 2022 | December 6, 2023 | October 31, 2028 | |
Comment |
MoEUCC and local authorities staff trained to increase technical and institutional capacities for design, implementation, and monitoring of urban transformation programs | Value | 0.00 | 0.00 | 500.00 |
Date | October 31, 2022 | December 6, 2023 | October 31, 2028 | |
Comment |
Female-headed households that apply for a resilient housing loan | Value | 0.00 | 0.00 | 1250.00 |
Date | October 31, 2022 | December 6, 2023 | October 31, 2028 | |
Comment |
Grievances addressed in accordance with the stipulated service standards (ILBANK) | Value | 0.00 | 0.00 | 90.00 |
Date | October 31, 2022 | December 6, 2023 | October 31, 2028 | |
Comment |
Beneficiaries who report that the Project has established effective engagement processes (ILBANK) | Value | 0.00 | 0.00 | 90.00 |
Date | October 31, 2022 | December 6, 2023 | October 31, 2028 | |
Comment |
Of which women | Value | 0.00 | 0.00 | 50.00 |
Date | ||||
Comment |
Of which received a resilient housing loan | Value | 0.00 | 0.00 | 50.00 |
Date | ||||
Comment |
Implementation support provided to owners interested in resilient housing reconstruction/retrofitting | Value | No | No | Yes |
Date | October 31, 2022 | December 6, 2023 | October 31, 2028 | |
Comment |
Housing or commercial units in risky buildings structurally strengthened in accordance with climate and disaster-resilient and energy efficiency standards under the Project | Value | 0.00 | 0.00 | 10000.00 |
Date | October 31, 2022 | December 6, 2023 | October 31, 2028 | |
Comment |
Women in design and supervision consultancies contracted under the Project who are technical staff | Value | 0.00 | 0.00 | 20.00 |
Date | October 31, 2022 | December 6, 2023 | October 31, 2028 | |
Comment |
Of which with Class C Energy Performance Certificate | Value | 0.00 | 0.00 | 7500.00 |
Date | October 31, 2022 | December 6, 2023 | October 31, 2028 | |
Comment |
Of which with Class A or B Energy Performance Certificate | Value | 0.00 | 0.00 | 2500.00 |
Date | October 31, 2022 | December 6, 2023 | October 31, 2028 | |
Comment |