Financier | Commitments |
---|---|
IDA Credit | 150.00 |
Social Sustainability Initiative for All | 21.40 |
Borrower/Recipient | 5.00 |
Local Govts. (Prov., District, City) of Borrowing Country | 75.00 |
P173065
Active
John Kinuthia , Pascaline Ndungu, Nicholas Soikan
Republic of Kenya
September 24, 2020
(as of board presentation)
October 26, 2021
February 1, 2022
US$ 251.40 million
Ministry of Environment, Climate Change and Forestry,The National Treasury and Planning
2022
US$ 171.40 million
N/A
June 3, 2024
December 31, 2026
No
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 150.00 |
Social Sustainability Initiative for All | 21.40 |
Borrower/Recipient | 5.00 |
Local Govts. (Prov., District, City) of Borrowing Country | 75.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 150.00 |
IBRD + IDA Commitment | 150.00 |
Lending Instrument | |
---|---|
Grant Amount | 21.40 |
Total Project Cost** | 251.40 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Apr 15, 2023 | IDA-69800 | Int Charges | 843.48 |
Apr 15, 2023 | IDA-69800 | Int Charges | 46,571.15 |
Nov 15, 2022 | IDA-69800 | Loan Disb | 113,977.32 |
Oct 15, 2022 | IDA-69800 | Int Charges | 5,781.35 |
Oct 15, 2022 | IDA-69800 | Int Charges | 5,781.35 |
Oct 15, 2022 | IDA-69800 | Int Charges | 5,312.58 |
Oct 15, 2022 | IDA-69800 | Int Charges | 32,013.67 |
Oct 15, 2022 | IDA-69800 | Int Charges | 32,013.67 |
Oct 15, 2022 | IDA-69800 | Int Charges | 28,574.51 |
Aug 11, 2023 | IDA-69800 | Loan Disb | 83,196.62 |
Jun 21, 2023 | IDA-69800 | Loan Disb | 553,000.00 |
Aug 25, 2023 | IDA-69800 | Loan Disb | 445,704.88 |
Jan 19, 2023 | IDA-69800 | Loan Disb | 363,215.97 |
May 10, 2023 | IDA-69800 | Loan Disb | 88,822.75 |
May 10, 2023 | IDA-69800 | Loan Disb | 85,526.83 |
Apr 15, 2023 | IDA-69800 | Int Charges | 46,571.15 |
Apr 15, 2023 | IDA-69800 | Int Charges | 41,659.10 |
Oct 15, 2023 | IDA-69800 | Int Charges | 1,136.00 |
Oct 15, 2023 | IDA-69800 | Int Charges | 309,959.56 |
Oct 15, 2023 | IDA-69800 | Int Charges | 309,959.56 |
Oct 15, 2023 | IDA-69800 | Int Charges | 282,675.20 |
Dec 5, 2023 | IDA-69800 | Loan Disb | 54,059.68 |
Jun 26, 2023 | IDA-69800 | Loan Disb | 52,800,000.00 |
Jun 23, 2023 | IDA-69800 | Loan Disb | 3,615,000.00 |
Apr 15, 2024 | IDA-69800 | Int Charges | 2,152.49 |
Jun 14, 2024 | IDA-69800 | Loan Disb | 140,009.95 |
Aug 13, 2024 | IDA-69800 | Loan Disb | 469,287.62 |
Nov 3, 2023 | IDA-69800 | Loan Disb | 279,842.53 |
Dec 28, 2023 | IDA-69800 | Loan Disb | 491,969.03 |
Jan 17, 2024 | IDA-69800 | Loan Disb | 6,479.90 |
Oct 10, 2023 | IDA-69800 | Loan Disb | 1,000,000.00 |
Mar 12, 2024 | IDA-69800 | Loan Disb | 164,090.38 |
Apr 9, 2024 | IDA-69800 | Loan Disb | 41,552.44 |
Apr 15, 2024 | IDA-69800 | Int Charges | 491,529.72 |
Feb 1, 2022 | IDA-69800 | Loan Disb | 1,900,368.80 |
Aug 16, 2022 | IDA-69800 | Loan Disb | 181,222.78 |
Jun 6, 2022 | IDA-69800 | Loan Disb | 700,000.00 |
Jun 28, 2022 | IDA-69800 | Loan Disb | 115,673.49 |
Jun 29, 2022 | IDA-69800 | Loan Disb | 3,002,000.00 |
Jun 24, 2022 | IDA-69800 | Loan Disb | 45,617.63 |
Oct 26, 2021 | IDA-69800 | Loan Commitment | 150,000,000.00 |
Apr 15, 2024 | IDA-69800 | Int Charges | 491,529.72 |
Apr 15, 2024 | IDA-69800 | Int Charges | 451,229.12 |
Feb 14, 2024 | IDA-69800 | Loan Disb | 249,242.20 |
Feb 2, 2024 | IDA-69800 | Loan Disb | 127,500.91 |
May 14, 2024 | IDA-69800 | Loan Disb | 219,581.77 |
Apr 25, 2023 | IDA-69800 | Loan Disb | 275,450.94 |
Feb 27, 2023 | IDA-69800 | Loan Disb | 300,000.00 |
Name | Review | Date |
---|---|---|
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-12-16 |
Progress towards achievement of PDO | Moderately Satisfactory | 2024-12-16 |
Monitoring and Evaluation | Satisfactory | 2024-12-16 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of rural wards benefitting from Program-funded functioning resilience investments in the agriculture, environment, water, orother prioritized sectors | Value | 0.00 | 0.00 | 700.00 |
Date | October 26, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |
Counties' average Annual Performance Assessment score | Value | 0.00 | 58.00 | 80.00 |
Date | October 26, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |
Annual national entities capacity building plan delivered | Value | 0.00 | 9.00 | 80.00 |
Date | October 26, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |
Participating counties that spend >50% of their approved budgeted CCRI Grant amount | Value | 0.00 | 0.00 | 100.00 |
Date | October 26, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |
Participating counties where at least 60% of the utilized CCRI Grant budget is spent on climate-resilient actions relevant to agriculture, environment, and/or water sectors | Value | 0.00 | 0.00 | 90.00 |
Date | October 26, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |
Participating counties where at least 30% of agriculture, environment, and/or water actions directly benefit women | Value | 0.00 | 0.00 | 100.00 |
Date | October 26, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |
Participating counties where at least 30% of agriculture, environment, and/or water actions directly benefit women, youth and othermarginalized groups | Value | 0.00 | 0.00 | 100.00 |
Date | October 31, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
DLI-1: Participating counties that meet the Minimum Access Conditions for the County Climate and Institutional Support Grant | Value | 0.00 | 45.00 | 47.00 |
Date | October 26, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |
Participating counties with County Climate Change Action Plans developed through participatory methodologies and approved | Value | 3.00 | 45.00 | 41.00 |
Date | October 26, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |
National and county level stakeholders trained on the National Social Risk Management Framework | Value | National SRM Framework being developed by the MLSP | Framework developed and awaiting approval by Cabin | National officers of MLSP, NEMA, Labour, Gender, o |
Date | October 26, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |
DLI-2: Participating counties that meet the Minimum Performance Conditions for the County Climate Resilience Investment Grant | Value | 0.00 | 45.00 | 41.00 |
Date | October 26, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |
Average community satisfaction with the Program's participatory process | Value | 0.00 | 0.00 | 80.00 |
Date | October 26, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |
Number of county climate change entities whose capacity is strengthened to address climate change risks | Value | 0.00 | 516.00 | 1400.00 |
Date | October 26, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |
Average community satisfaction with the Program's participatory process - female | Value | 0.00 | 0.00 | 80.00 |
Date | October 26, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |
Participating counties with an operational Climate Information and Knowledge Management System | Value | 0.00 | 0.00 | 100.00 |
Date | October 26, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |
Average community satisfaction with the Program's climate resilience actions | Value | 0.00 | 0.00 | 80.00 |
Date | October 26, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |
An Inter-Agency Technical Advisory Committee Operationalized | Value | Terms of Reference available and members appointed | ITAC meeting on a quarterly basis and executing it | ITAC meeting on a quarterly basis and executing it |
Date | October 26, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |
Participating counties where at least 50% of Ward Climate Change Planning Committees' membership is from marginalized and vulnerable groups, including women | Value | 0.00 | 82.00 | 80.00 |
Date | October 26, 2021 | May 8, 2024 | June 30, 2026 | |
Comment |
Maarifa Center climate change-related functions operationalized | Value | No | Yes | Yes |
Date | October 26, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |
Average community satisfaction with the Program's climate resilience actions - female | Value | 0.00 | 0.00 | 80.00 |
Date | October 26, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |
Participating counties where at least 50% of community members consulted as part of the participatory climate risk assessment are marginalized and vulnerable groups, including women | Value | 0.00 | 82.00 | 100.00 |
Date | October 26, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |
Citizens with increased awareness of climate risks and resilience actions | Value | 0.00 | 0.00 | 75.00 |
Date | October 26, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |
An annual County Delivery Support Plan for climate action executed | Value | Annual County Delivery Support Plan non-existent | Annual County Delivery Support Plan yet to be fina | 80% of actions executed annually |
Date | October 26, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |
Citizens with increased awareness of climate risks and resilience actions - female | Value | 0.00 | 0.00 | 75.00 |
Date | August 24, 2021 | May 8, 2024 | December 31, 2026 | |
Comment |