Comoros Interisland Connectivity Project

Abstract*

Interisland connectivity is among the most important constraints to integrate domestic markets and reduce poverty and inequality in Comoros. The overall program aims at improving maritime connectivity among the islands and ameliorating maritime transport resilience and safety by increasing the port capacity, installing proper infrastructure and protection at the primary and secondary ports and strengthening the regulatory and institutional framework...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The Project Development Objective is to improve maritime transport climate resilience between the islands.

Key Details

Project Details

  • P173114

  • Active

  • Atsushi Iimi

  • The Union of Comoros

  • Comoros

  • June 28, 2020

  • (as of board presentation)

    May 20, 2022

  • August 22, 2022

  • US$ 40.00 million

  • Ministry of Maritime and Air Transport

  • Eastern and Southern Africa

  • 2022

  • US$ 25.00 million

  • N/A

  • High

  • June 30, 2028

  • Yes

  • BANK APPROVED

  • May 6, 2024

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
FRANCE: French Agency for Development 5.00
IDA Credit 10.00
IDA Grant 10.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 20.00
IBRD + IDA Commitment 20.00
Lending Instrument
Grant Amount 5.00
Total Project Cost** 40.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 6, 2022 IDA-E0190 Loan Disb 131,184.77
Oct 30, 2022 IDA-E0190 Loan Disb 126,367.51
Apr 17, 2023 IDA-E0190 Loan Disb 153,040.33
Mar 13, 2023 IDA-E0190 Loan Disb 87,583.68
Oct 30, 2022 IDA-70860 Loan Disb 606,872.80
Oct 30, 2022 IDA-70860 Loan Disb 126,367.50
Oct 15, 2023 IDA-70860 Int Charges 2,907.51
Oct 15, 2023 IDA-70860 Int Charges 2,907.51
Apr 22, 2024 IDA-70860 Loan Disb 26,425.36
Mar 20, 2024 IDA-70860 Loan Disb 116,494.53
Jul 15, 2024 IDA-70860 Loan Disb 42,592.30
Mar 14, 2024 IDA-70860 Loan Disb 215,698.33
Apr 15, 2024 IDA-70860 Int Charges 2,945.94
Apr 15, 2024 IDA-70860 Int Charges 2,945.94
Aug 12, 2024 IDA-70860 Loan Disb 47,466.49
May 16, 2024 IDA-70860 Loan Disb 72,320.61
Jun 12, 2024 IDA-70860 Loan Disb 30,467.33
Apr 15, 2023 IDA-70860 Int Charges 2,802.18
Apr 15, 2023 IDA-70860 Int Charges 2,802.18
Apr 15, 2023 IDA-70860 Int Charges -2,802.18
Apr 15, 2023 IDA-70860 Int Charges -2,802.18
Apr 15, 2023 IDA-70860 Int Charges 2,802.18
Apr 15, 2023 IDA-70860 Int Charges 2,802.18
May 31, 2023 IDA-E2000 Loan Commitment 15,000,000.00
May 20, 2022 IDA-70860 Loan Commitment 10,000,000.00
May 20, 2022 IDA-E0190 Loan Commitment 10,000,000.00
Feb 9, 2024 IDA-E0190 Loan Disb 48,985.56
Jun 13, 2023 IDA-E0190 Loan Disb 103,651.65
Jun 13, 2023 IDA-E0190 Loan Disb 75,183.75
Sep 14, 2023 IDA-E0190 Loan Disb 118,623.10
Oct 6, 2023 IDA-E0190 Loan Disb 134,435.20
Nov 13, 2023 IDA-E0190 Loan Disb 39,582.91
Apr 9, 2024 IDA-E0190 Loan Disb 4,622,092.00
Jan 18, 2023 IDA-E0190 Loan Disb 58,627.59
Feb 21, 2023 IDA-E0190 Loan Disb 246,061.44
Jul 14, 2023 IDA-E0190 Loan Disb 57,704.05
May 15, 2023 IDA-E0190 Loan Disb 79,652.89
Jan 17, 2023 IDA-E0190 Loan Disb 48,858.89
Aug 17, 2023 IDA-E0190 Loan Disb 37,003.72
Oct 30, 2022 IDA-E0190 Loan Disb 605,835.70
Jan 20, 2023 IDA-E0190 Loan Disb 25,358.94
Dec 8, 2022 IDA-E0190 Loan Disb 266,988.75

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Project Management Satisfactory 2024-11-18
Overall Implementation Progress (IP) Moderately Satisfactory 2024-11-18
Progress towards achievement of PDO Satisfactory 2024-11-18
Monitoring and Evaluation Satisfactory 2024-11-18
Procurement Moderately Satisfactory 2024-11-18
Financial Management Moderately Satisfactory 2024-11-18

COMPLETION RATINGS

No data available.

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of days each year when Port Boingoma is nonoperational because of weather conditionsValue216.00216.0020.00
    DateMarch 31, 2021July 11, 2022June 30, 2028
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • Percentage of complaints responded and/or resolved within the stipulated standard for response timesValue0.000.0075.00
    DateMarch 31, 2021July 11, 2022June 30, 2028
    Comment
  • Installation of maritime communication and safety equipment at portsValueNoNoYes
    DateFebruary 1, 2023February 1, 2023June 30, 2028
    Comment
  • Port Boingoma is rehabilitatedValueNoNoYes
    DateMarch 31, 2021July 11, 2022June 30, 2028
    Comment
  • Establishment of a national maritime training centerValueNoNoYes
    DateMarch 14, 2022July 11, 2022June 30, 2028
    Comment
  • Climate resilience strategy in the maritime sector is developedValueNoNoYes
    DateMarch 31, 2021July 11, 2022June 30, 2028
    Comment
  • Share of women that are trained for skilled maritime affairs under the training center and are certified by a recognized authorityValue0.000.0020.00
    DateMarch 14, 2022July 11, 2022June 30, 2028
    Comment
  • Number of operators and stakeholders with training on GBV/SH in the maritime transport sectorValue0.000.0020.00
    DateMarch 31, 2021July 11, 2022June 30, 2028
    Comment
  • Comoros Port Authority fully operationalizedValueNoNoYes
    DateMarch 31, 2021July 11, 2022June 30, 2028
    Comment
  • Legal framework for public-private partnerships formalizedValueNoNoYes
    DateMarch 31, 2021July 11, 2022June 30, 2028
    Comment
  • Satisfaction rating by project beneficiariesValue0.000.0075.00
    DateMarch 31, 2022July 11, 2022June 30, 2028
    Comment