Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 40.00 |
P173283
Active
Kosuke Anan , Enrique Pantoja
Republic of Ecuador
March 18, 2020
(as of board presentation)
September 25, 2020
January 12, 2022
US$ 40.00 million
National Institute of Popular and Solidarity Economy,Higher Education, Science, Technology and Innovation Secretariat
2021
US$ 40.00 million
N/A
November 14, 2024
December 31, 2026
No
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 40.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 40.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 40.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 40.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 25, 2020 | IBRD-91630 | Loan Commitment | 40,000,000.00 |
Mar 15, 2023 | IBRD-91630 | Int Charges | 2,600.89 |
Mar 28, 2022 | IBRD-91630 | Fee Charges | 100,000.00 |
Mar 15, 2022 | IBRD-91630 | Int Charges | 73,150.69 |
Mar 15, 2024 | IBRD-91630 | Int Charges | 48,661.71 |
Mar 15, 2024 | IBRD-91630 | Int Charges | 34,839.04 |
Oct 11, 2023 | IBRD-91630 | Loan Disb | 253,396.86 |
Jun 28, 2023 | IBRD-91630 | Loan Disb | 230,748.81 |
Sep 15, 2023 | IBRD-91630 | Int Charges | 49,729.72 |
Sep 15, 2023 | IBRD-91630 | Int Charges | 18,648.65 |
Sep 15, 2022 | IBRD-91630 | Int Charges | 50,316.28 |
Sep 15, 2022 | IBRD-91630 | Int Charges | 1,086.38 |
Mar 30, 2023 | IBRD-91630 | Loan Disb | 378,988.60 |
Mar 15, 2023 | IBRD-91630 | Int Charges | 49,473.27 |
Apr 20, 2022 | IBRD-91630 | Loan Disb | 93,376.65 |
Name | Review | Date |
---|---|---|
Project Management | Moderately Satisfactory | 2025-02-05 |
Monitoring and Evaluation | Satisfactory | 2025-02-05 |
Financial Management | Moderately Satisfactory | 2025-02-05 |
Overall Implementation Progress (IP) | Moderately Unsatisfactory | 2025-02-05 |
Progress towards achievement of PDO | Moderately Unsatisfactory | 2025-02-05 |
Procurement | Moderately Satisfactory | 2025-02-05 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
IPAMs in beneficiary territories that feel project investments reflect development priorities/needs established during planning process (disaggregated by P/N and gender) | Value | 0.00 | 0.00 | 70.00 |
Date | August 4, 2020 | December 12, 2023 | December 24, 2026 | |
Comment |
IPAM beneficiaries in selected territories that have secured, for the first time, formal financial services from FIs supported by the Project (disaggregated by gender) | Value | 0.00 | 0.00 | 1000.00 |
Date | November 3, 2020 | December 12, 2023 | October 22, 2026 | |
Comment |
New internships or jobs for IPAMs facilitated by Project-financed activities (disaggregated by P/N and gender) | Value | 0.00 | 0.00 | 200.00 |
Date | August 4, 2020 | December 12, 2023 | December 17, 2026 | |
Comment |
Increase in attendance of IPAMs in participating in higher education programs (disaggregated by P/N and gender) | Value | 0.00 | 0.00 | 500.00 |
Date | January 11, 2021 | December 12, 2023 | November 27, 2026 | |
Comment |
IPAM households benefiting from livelihood subprojects and investments | Value | 0.00 | 0.00 | 50000.00 |
Date | January 11, 2021 | December 12, 2023 | December 24, 2026 | |
Comment |
National Platform for structured dialogue between IPAM representatives and the State is established and operational | Value | No | No | Yes |
Date | January 11, 2021 | December 12, 2023 | June 30, 2022 | |
Comment |
IPAM women in prioritized territories that have secured, for the first time, formal financial services from FIs supported by the Project | Value | 0.00 | 0.00 | 300.00 |
Date | January 4, 2021 | December 12, 2023 | January 1, 2026 | |
Comment |
New internships or jobs for female IPAMs facilitated by Project-financed activities (disaggregated by P/N) | Value | 0.00 | 0.00 | 60.00 |
Date | January 4, 2021 | December 12, 2023 | January 1, 2026 | |
Comment |
Direct IPAM project beneficiaries (disaggregated by gender) | Value | 0.00 | 0.00 | 1000000.00 |
Date | August 4, 2020 | December 12, 2023 | December 25, 2026 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Partnership agreements signed with universities, cultural institutes and technical programs for strengthening IPAM attendance | Value | 0.00 | 0.00 | 7.00 |
Date | December 29, 2016 | September 26, 2022 | August 4, 2025 | |
Comment |
IPAMs Strategic Development Investment Plans (SDIPs) are developed and validated using territorial platforms | Value | 0.00 | 0.00 | 10.00 |
Date | January 4, 2021 | September 26, 2022 | December 31, 2025 | |
Comment |
Subproject investments financed under the Project that are operational/completed and assessed as good quality in technical audit | Value | 0.00 | 0.00 | 80.00 |
Date | August 4, 2020 | September 26, 2022 | September 2, 2025 | |
Comment |
Grievances responded and/or resolved within the stipulated service standards for response times | Value | 0.00 | 0.00 | 85.00 |
Date | August 4, 2020 | September 26, 2022 | September 2, 2025 | |
Comment |
Improved employability and competitiveness | Value | 0.00 | 0.00 | 75.00 |
Date | January 29, 2021 | September 26, 2022 | December 31, 2025 | |
Comment |
IPAM women's active participation in structured dialogue platforms at the national and territorial levels | Value | 0.00 | 0.00 | 30.00 |
Date | August 4, 2020 | September 26, 2022 | September 2, 2025 | |
Comment |
New IPAM associations/companies led by IPAMs established under the Project (disaggregated by gender) | Value | 0.00 | 0.00 | 5.00 |
Date | January 4, 2021 | September 26, 2022 | December 30, 2025 | |
Comment |
IPAM community banks formed and strengthened | Value | 0.00 | 0.00 | 20.00 |
Date | August 4, 2020 | September 26, 2022 | September 2, 2025 | |
Comment |