Financier | Commitments |
---|---|
IDA Credit | 500.00 |
Borrower/Recipient | 6.20 |
P173312
Active
Yohannes Kesete , Swarna Kazi
PEOPLE’S REPUBLIC OF BANGLADESH
July 9, 2020
(as of board presentation)
July 15, 2022
May 2, 2023
US$ 506.20 million
LOCAL GOVERNMENT ENGINEERING DEPARTMENT (LGED)
2023
US$ 500.00 million
N/A
November 6, 2023
June 30, 2028
Yes
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 500.00 |
Borrower/Recipient | 6.20 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 500.00 |
IBRD + IDA Commitment | 500.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 506.20 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Sep 12, 2023 | IDA-71670 | Loan Disb | 12,727,273.00 |
Dec 1, 2023 | IDA-71670 | Int Charges | 21,118.16 |
Dec 1, 2023 | IDA-71670 | Int Charges | 21,118.16 |
Dec 1, 2023 | IDA-71670 | Int Charges | 34,466.50 |
Jul 15, 2022 | IDA-71670 | Loan Commitment | 500,000,000.00 |
Jun 1, 2024 | IDA-71670 | Int Charges | 47,802.37 |
Jun 1, 2024 | IDA-71670 | Int Charges | 47,802.37 |
Jun 1, 2024 | IDA-71670 | Int Charges | 79,670.65 |
Jun 1, 2024 | IDA-71670 | Int Charges | 725.66 |
Jun 18, 2024 | IDA-71670 | Loan Disb | 2,479,864.20 |
Name | Review | Date |
---|---|---|
Procurement | Moderately Satisfactory | 2024-12-22 |
Project Management | Satisfactory | 2024-12-22 |
Progress towards achievement of PDO | Satisfactory | 2024-12-22 |
Monitoring and Evaluation | Satisfactory | 2024-12-22 |
Financial Management | Moderately Satisfactory | 2024-12-22 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-12-22 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Enhanced operationalization of a systematic damage, loss and needs assessment methodology for the LGED | Value | No | No | Yes |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
Communities with improved basic disaster preparedness and response capacities | Value | 0.00 | 0.00 | 500.00 |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
Of which 50 percent is women | Value | 0.00 | 0.00 | 626858.00 |
Date | July 1, 2021 | September 25, 2023 | June 30, 2028 | |
Comment |
People with reduced flood vulnerability due to resilient infrastructure constructed under the project | Value | 0.00 | 0.00 | 1253715.00 |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Assessment of damage and needs reporting completed | Value | No | No | Yes |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
People with access to climate-resilient flood shelters as a result of the project | Value | 0.00 | 0.00 | 325000.00 |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
LGED upazila officials trained on the damage and needs assessments | Value | 0.00 | 0.00 | 300.00 |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
Of which 50 percent is women | Value | 0.00 | 0.00 | 162500.00 |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
ICT monitoring system developed | Value | No | Yes | Yes |
Date | July 1, 2022 | April 25, 2023 | June 30, 2028 | |
Comment |
Climate-resilient flood shelters constructed | Value | 0.00 | 0.00 | 500.00 |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
Categories of Operational Plans and Guidelines developed in a participatory manner with communities | Value | 0.00 | 0.00 | 3.00 |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
Share of shelters with improved infrastructure for women | Value | 0.00 | 0.00 | 100.00 |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
Participants in consultation activities during project implementation | Value | 0.00 | 0.00 | 15000.00 |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
Construction/Installation of solar PV nano-grid systems | Value | 0.00 | 0.00 | 100.00 |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
Women participants in consultation activities during project implementation | Value | 0.00 | 0.00 | 7500.00 |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
Land raised above flood levels | Value | 0.00 | 0.00 | 100000.00 |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
Data collection that supports understanding on women’s use and needs of shelters | Value | No | No | Yes |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
Beneficiaries satisfied with the flood shelters constructed under the project | Value | 0.00 | 0.00 | 75.00 |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
Community risk mapping completed | Value | 0.00 | 0.00 | 500.00 |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
Women beneficiaries satisfied with the flood Shelters constructed under the Project | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
People in the project areas benefitting from village level interventions | Value | 0.00 | 0.00 | 1132875.00 |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
Beneficiaries satisfied with the community infrastructure constructed under the project | Value | 0.00 | 0.00 | 70.00 |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
Women beneficiaries satisfied with the community infrastructures constructed under the project | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Schoolboys who have received skills training | Value | 0.00 | 0.00 | 5000.00 |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
Resilient community access and evacuation roads and shelter connecting roads rehabilitated and improved | Value | 0.00 | 0.00 | 415.00 |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
Schoolgirls who have received skills training | Value | 0.00 | 0.00 | 5000.00 |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
Bridges and culverts constructed under the project | Value | 0.00 | 0.00 | 250.00 |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |
Lightning protection systems installed | Value | 0.00 | 0.00 | 1400.00 |
Date | July 1, 2022 | September 25, 2023 | June 30, 2028 | |
Comment |