Skip to Main Navigation

Sudan Family Support Project

Abstract*

The Government of Sudan (GoS) is responding to urgent needs to stabilize the economy and begin a long process of clearing arrears to MFIs as part of the Sudan’s larger macroeconomic stabilization and integration. These measures are expected to include exchange rate liberalization/unification and reallocation of public resources away from commodity subsidies, tax exemptions, towards social and development needs. These fiscal adjustments are expected...

* The project abstract is drawn from the PAD, SAR or PGD and may not accurately reflect the project's current nature

Show More

Development Objective

The objective is to deliver cash transfers and improve safety net systems to support the Sudanese families in the Recipient's territory affected by expected economic reforms and other short-term shocks.

Key Details

Project Details

  • P173521

  • Closed

  • Endashaw Gossa

  • Republic of Sudan

  • Sudan

  • April 24, 2020

  • (as of board presentation)

    October 8, 2020

  • December 7, 2020

  • US$ 400.00 million

  • Ministry of Finance and Economic Planning

  • Eastern and Southern Africa

  • 2021

  • US$ 400.00 million

  • N/A

  • April 17, 2024

  • June 30, 2024

  • Yes

  • BANK APPROVED

  • Notes

Finances

Financing Plan (US$ Millions)

No data available.
Financier Commitments
Miscellaneous 1 200.00
IDA Grant 200.00

Total Project Financing (US$ Millions)

Product Line IBRD/IDA
IBRD Commitment N/A
IDA Commitment 200.00
IBRD + IDA Commitment 200.00
Lending Instrument
Grant Amount 200.00
Total Project Cost** 400.00

Summary Status of World Bank Financing (US$ Millions) as of March 31, 2025

Download:
No data available.
Financier Approval Date Closing Date Principal Disbursed Repayments Interest, Charges & Fees

Detailed Financial Activity as of March 31, 2025

Download:
No data available.
Period Financier Transaction Type Amount (US$)
Dec 30, 2020 IDA-D7350 Loan Disb 29,455,200.00
Mar 16, 2021 IDA-D7700 Loan Commitment 210,000,000.00
Oct 8, 2020 IDA-D7350 Loan Commitment 200,000,000.00
Dec 30, 2020 IDA-D7350 Loan Disb 46,023,752.00
Dec 30, 2020 IDA-D7350 Loan Disb 25,159,650.00

Footnotes

Ratings

IMPLEMENTATION RATINGS

Name Review Date
Progress towards achievement of PDO Moderately Satisfactory 2024-06-27
Financial Management Moderately Unsatisfactory 2024-06-27
Procurement Moderately Satisfactory 2024-06-27
Monitoring and Evaluation Moderately Satisfactory 2024-06-27
Overall Implementation Progress (IP) Moderately Satisfactory 2024-06-27
Project Management Moderately Satisfactory 2024-06-27

COMPLETION RATINGS

INDICATORIMPLEMENTATION COMPLETION & RESULTS REPORT:
Outcomes
Risk to Development Outcome
Bank Performance
Borrower Performance
Government Performance
Implementing Agency

INDEPENDENT EVALUATION RATINGS

No data available.

Results Framework

PROJECT DEVELOPMENT OBJECTIVE INDICATORS

INDICATORBASELINECURRENTTARGET
  • Number of families receiving cash/income supportValue0.007200000.000.00
    DateJune 8, 2020June 30, 2022
    Comment
  • National registry platform that functions across the country is strengthenedValueNational platform is functioning, but has low cove• MOU signed with the MOI to upgrade the NCR syste
    DateJune 8, 2020October 25, 2021
    Comment
  • of which females are heads of familiesValue0.000.000.00
    Date
    Comment
  • Number of beneficiaries of SFSPValue0.001300000.000.00
    DateJune 8, 2020June 30, 2022
    Comment
  • of which femaleValue0.000.000.00
    Date
    Comment

INTERMEDIATE RESULTS INDICATORS

INDICATORBASELINECURRENTTARGET
  • SFSP MIS system has been developed and deployedValueNoNo
    DateJune 8, 2020October 25, 2021
    Comment
  • Average number of days for funds to reach beneficiary accountsValue0.0045.000.00
    DateJune 8, 2020October 25, 2021
    Comment
  • ME&L impact evaluation baseline & follow-up survey conducted.ValueNoNo
    DateJune 15, 2020October 25, 2021
    Comment
  • National data protection and privacy law is submitted to governing councilValueNoNo
    DateJune 8, 2020October 25, 2021
    Comment
  • Number of beneficiaries enrolled in basic bank accountsValue0.000.000.00
    DateJune 8, 2020October 25, 2021
    Comment
  • ME&L lessons drawn from Sudan’s experience in an evaluative reportValueNoNo
    DateJune 15, 2020October 25, 2021
    Comment
  • Number of states covered by the SFSP programValue0.0014.000.00
    DateJune 8, 2020October 25, 2021
    Comment
  • Time in days between generation of payroll and fund transfer to PSPsValue8.005.000.00
    DateJune 8, 2020October 25, 2021
    Comment
  • SFSP branded as a national, well-defined and quasi universal programValueNoYes
    DateJune 8, 2020October 25, 2021
    Comment
  • Number of beneficiaries enrolled in mobile moneyValue0.000.000.00
    DateJune 8, 2020October 25, 2021
    Comment
  • Communication campaigns have been launchedValueNoYes
    DateJune 8, 2020October 25, 2021
    Comment
  • A hybrid system for tracking enquiries, complaints, and grievances (GRM) has been establishedValueNoYes
    DateJune 8, 2020October 25, 2021
    Comment
  • Percentage of complaints resolved in 15 days or less through GRMValue0.0086.000.00
    DateJune 8, 2020October 25, 2021
    Comment
  • Gender-focused behavioral science integrated into the community strategy for the SFSP in areas where women are not designated primary beneficiaariesValueNoNo
    DateJune 8, 2020October 25, 2021
    Comment