Financier | Commitments |
---|---|
Miscellaneous 1 | 200.00 |
IDA Grant | 200.00 |
P173521
Closed
Endashaw Gossa
Republic of Sudan
April 24, 2020
(as of board presentation)
October 8, 2020
December 7, 2020
US$ 400.00 million
Ministry of Finance and Economic Planning
2021
US$ 400.00 million
N/A
April 17, 2024
June 30, 2024
Yes
BANK APPROVED
Financier | Commitments |
---|---|
Miscellaneous 1 | 200.00 |
IDA Grant | 200.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 200.00 |
IBRD + IDA Commitment | 200.00 |
Lending Instrument | |
---|---|
Grant Amount | 200.00 |
Total Project Cost** | 400.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 30, 2020 | IDA-D7350 | Loan Disb | 29,455,200.00 |
Mar 16, 2021 | IDA-D7700 | Loan Commitment | 210,000,000.00 |
Oct 8, 2020 | IDA-D7350 | Loan Commitment | 200,000,000.00 |
Dec 30, 2020 | IDA-D7350 | Loan Disb | 46,023,752.00 |
Dec 30, 2020 | IDA-D7350 | Loan Disb | 25,159,650.00 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2024-06-27 |
Financial Management | Moderately Unsatisfactory | 2024-06-27 |
Procurement | Moderately Satisfactory | 2024-06-27 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-06-27 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-06-27 |
Project Management | Moderately Satisfactory | 2024-06-27 |
INDICATOR | IMPLEMENTATION COMPLETION & RESULTS REPORT: |
---|---|
Outcomes | |
Risk to Development Outcome | |
Bank Performance | |
Borrower Performance | |
Government Performance | |
Implementing Agency |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Number of families receiving cash/income support | Value | 0.00 | 7200000.00 | 0.00 |
Date | June 8, 2020 | June 30, 2022 | ||
Comment |
National registry platform that functions across the country is strengthened | Value | National platform is functioning, but has low cove | • MOU signed with the MOI to upgrade the NCR syste | |
Date | June 8, 2020 | October 25, 2021 | ||
Comment |
of which females are heads of families | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
Number of beneficiaries of SFSP | Value | 0.00 | 1300000.00 | 0.00 |
Date | June 8, 2020 | June 30, 2022 | ||
Comment |
of which female | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
SFSP MIS system has been developed and deployed | Value | No | No | |
Date | June 8, 2020 | October 25, 2021 | ||
Comment |
Average number of days for funds to reach beneficiary accounts | Value | 0.00 | 45.00 | 0.00 |
Date | June 8, 2020 | October 25, 2021 | ||
Comment |
ME&L impact evaluation baseline & follow-up survey conducted. | Value | No | No | |
Date | June 15, 2020 | October 25, 2021 | ||
Comment |
National data protection and privacy law is submitted to governing council | Value | No | No | |
Date | June 8, 2020 | October 25, 2021 | ||
Comment |
Number of beneficiaries enrolled in basic bank accounts | Value | 0.00 | 0.00 | 0.00 |
Date | June 8, 2020 | October 25, 2021 | ||
Comment |
ME&L lessons drawn from Sudan’s experience in an evaluative report | Value | No | No | |
Date | June 15, 2020 | October 25, 2021 | ||
Comment |
Number of states covered by the SFSP program | Value | 0.00 | 14.00 | 0.00 |
Date | June 8, 2020 | October 25, 2021 | ||
Comment |
Time in days between generation of payroll and fund transfer to PSPs | Value | 8.00 | 5.00 | 0.00 |
Date | June 8, 2020 | October 25, 2021 | ||
Comment |
SFSP branded as a national, well-defined and quasi universal program | Value | No | Yes | |
Date | June 8, 2020 | October 25, 2021 | ||
Comment |
Number of beneficiaries enrolled in mobile money | Value | 0.00 | 0.00 | 0.00 |
Date | June 8, 2020 | October 25, 2021 | ||
Comment |
Communication campaigns have been launched | Value | No | Yes | |
Date | June 8, 2020 | October 25, 2021 | ||
Comment |
A hybrid system for tracking enquiries, complaints, and grievances (GRM) has been established | Value | No | Yes | |
Date | June 8, 2020 | October 25, 2021 | ||
Comment |
Percentage of complaints resolved in 15 days or less through GRM | Value | 0.00 | 86.00 | 0.00 |
Date | June 8, 2020 | October 25, 2021 | ||
Comment |
Gender-focused behavioral science integrated into the community strategy for the SFSP in areas where women are not designated primary beneficiaaries | Value | No | No | |
Date | June 8, 2020 | October 25, 2021 | ||
Comment |