| Financier | Commitments | 
|---|---|
| International Bank for Reconstruction and Development | 15.00 | 
P173620
Active
Jan Nora , Ruvejda Aliefendic
Montenegro
Western Balkans
June 30, 2022
(as of board presentation)
December 23, 2022
September 28, 2023
US$ 15.00 million
Montenegro Ministry of Transport
2023
US$ 15.00 million
N/A
Moderate
April 30, 2028
BANK APPROVED
October 17, 2023
| Financier | Commitments | 
|---|---|
| International Bank for Reconstruction and Development | 15.00 | 
| Product Line | IBRD/IDA | 
|---|---|
| IBRD Commitment | 15.00 | 
| IDA Commitment | N/A | 
| IBRD + IDA Commitment | 15.00 | 
| Lending Instrument | |
|---|---|
| Grant Amount | N/A | 
| Total Project Cost** | 15.00 | 
| Period | Financier | Transaction Type | Amount (US$) | 
|---|---|---|---|
| Sep 28, 2023 | IBRD-94710 | Fee Charges | 38,207.50 | 
| Sep 28, 2023 | IBRD-94710 | Loan Disb | 38,207.50 | 
| Feb 15, 2024 | IBRD-94710 | Int Charges | 32,683.39 | 
| Aug 15, 2024 | IBRD-94710 | Int Charges | 19,372.08 | 
| Aug 15, 2024 | IBRD-94710 | Int Charges | 18,805.11 | 
| Apr 5, 2024 | IBRD-94710 | Loan Disb | 1,083,500.00 | 
| Dec 23, 2022 | IBRD-94710 | Loan Commitment | 15,000,000.00 | 
| Feb 15, 2024 | IBRD-94710 | Int Charges | 688.63 | 
| Name | Review | Date | 
|---|---|---|
| Project Management | Moderately Satisfactory | 2025-06-10 | 
| Financial Management | Satisfactory | 2025-06-10 | 
| Monitoring and Evaluation | Satisfactory | 2025-06-10 | 
| Procurement | Moderately Unsatisfactory | 2025-06-10 | 
| Progress towards achievement of PDO | Moderately Satisfactory | 2025-06-10 | 
| Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-06-10 | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| Total annual costs to export and import for all shipments of Montenegro | Value | 32239700.00 | 32239700.00 | 29015731.00 | 
| Date | December 31, 2019 | March 16, 2023 | December 15, 2028 | |
| Comment | 
| Cost to export | Value | 31.00 | 31.00 | 28.00 | 
| Date | October 1, 2018 | March 16, 2023 | December 15, 2028 | |
| Comment | 
| Cost to import | Value | 183.00 | 183.00 | 165.00 | 
| Date | December 31, 2019 | March 16, 2023 | December 15, 2028 | |
| Comment | 
| Time required to complete all transit formalities at the Port of Bar | Value | 57.00 | 57.00 | 51.00 | 
| Date | December 1, 2021 | March 16, 2023 | December 15, 2028 | |
| Comment | 
| INDICATOR | BASELINE | CURRENT | TARGET | 
|---|
| Number of Rail Level Crossings improved for safety and efficiency | Value | 0.00 | 0.00 | 5.00 | 
| Date | December 15, 2022 | March 16, 2023 | December 15, 2028 | |
| Comment | 
| Improving capacity of authorities to examine barriers in trade in services through the production of an action plan to remove barriers | Value | No | No | Yes | 
| Date | December 15, 2022 | March 16, 2023 | December 15, 2028 | |
| Comment | 
| Time to import | Value | 14.00 | 14.00 | 11.00 | 
| Date | December 31, 2019 | March 16, 2023 | December 15, 2028 | |
| Comment | 
| Number of IT systems upgraded at the Port of Bar | Value | 0.00 | 0.00 | 2.00 | 
| Date | December 15, 2022 | March 16, 2023 | December 15, 2028 | |
| Comment | 
| Time to export | Value | 7.00 | 7.00 | 5.50 | 
| Date | December 31, 2019 | March 16, 2023 | December 15, 2028 | |
| Comment | 
| National Transport Strategy updated to include an action plan for decarbonizing the transport sector | Value | No | No | Yes | 
| Date | December 15, 2022 | March 16, 2023 | December 15, 2028 | |
| Comment | 
| Number of firms that benefit from reformed custom/border services | Value | 0.00 | 0.00 | 100.00 | 
| Date | December 15, 2022 | March 16, 2023 | December 15, 2028 | |
| Comment | 
| Adoption of technical guideline for integrating climate resilience and mitigation considerations in the design, construction and maintenance of roads | Value | No | No | Yes | 
| Date | December 15, 2022 | March 16, 2023 | December 15, 2028 | |
| Comment | 
| Stakeholders reporting that the design/blueprint of the NWS is aligned with their needs and their contributions in the planning process (citizen engagement) | Value | 0.00 | 0.00 | 80.00 | 
| Date | December 15, 2022 | March 16, 2023 | December 15, 2028 | |
| Comment | 
| Female customs officials recruited at managerial level in Revenue and Customs Agency | Value | 0.00 | 0.00 | 2.00 | 
| Date | December 15, 2022 | March 16, 2023 | December 15, 2028 | |
| Comment | 
| Female students and graduates recruited in 3 to 6 month paid internship programs in technical areas | Value | 0.00 | 0.00 | 4.00 | 
| Date | December 15, 2022 | March 16, 2023 | December 15, 2028 | |
| Comment | 
| Female customs inspectors recruited in the Revenue and Customs Agency | Value | 0.00 | 0.00 | 5.00 | 
| Date | December 15, 2022 | March 16, 2023 | December 15, 2028 | |
| Comment |