Financier | Commitments |
---|---|
IDA Credit | 200.00 |
Borrower/Recipient | 50.00 |
P173663
Active
Shahnaz Arshad , Qingyun Shen
Islamic Republic of Pakistan
November 10, 2021
(as of board presentation)
March 10, 2022
October 12, 2022
US$ 250.00 million
Province of Punjab
2022
US$ 200.00 million
N/A
May 24, 2024
June 30, 2027
TBD
BANK APPROVED
Financier | Commitments |
---|---|
IDA Credit | 200.00 |
Borrower/Recipient | 50.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | N/A |
IDA Commitment | 200.00 |
IBRD + IDA Commitment | 200.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 250.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Mar 10, 2022 | IDA-70430 | Loan Commitment | 200,000,000.00 |
Feb 23, 2024 | IDA-70430 | Loan Disb | 47,631.75 |
Jul 26, 2024 | IDA-70430 | Loan Disb | 499,376.00 |
Aug 15, 2024 | IDA-70430 | Int Charges | 6,902.10 |
Aug 15, 2024 | IDA-70430 | Int Charges | 6,902.10 |
Aug 15, 2024 | IDA-70430 | Int Charges | 3,042.55 |
Aug 15, 2024 | IDA-70430 | Int Charges | 32,618.28 |
Aug 15, 2024 | IDA-70430 | Int Charges | 32,618.28 |
Aug 15, 2024 | IDA-70430 | Int Charges | 1,970.84 |
Dec 21, 2023 | IDA-70430 | Loan Disb | 5,820,498.00 |
Nov 3, 2023 | IDA-70430 | Loan Disb | 147,708.02 |
Jun 26, 2024 | IDA-70430 | Loan Disb | 7,552,158.00 |
Feb 15, 2024 | IDA-70430 | Int Charges | 447.49 |
Feb 15, 2024 | IDA-70430 | Int Charges | 447.49 |
Dec 29, 2023 | IDA-70430 | Loan Disb | 493,456.16 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Satisfactory | 2025-01-07 |
Monitoring and Evaluation | Satisfactory | 2025-01-07 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2025-01-07 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Housing units delivered in Punjab supported by the Program | Value | 0.00 | 0.00 | 77000.00 |
Date | March 21, 2022 | May 17, 2024 | June 30, 2027 | |
Comment |
Affordable housing units built to agreed standards, including green design principles that promote climate resilience and sustainability | Value | 0.00 | 0.00 | 37000.00 |
Date | March 21, 2022 | May 17, 2024 | June 30, 2027 | |
Comment |
Housing policies, programs, and systems in Punjab updated/developed and operationalized | Value | 0.00 | 2.00 | 5.00 |
Date | January 3, 2022 | May 17, 2024 | June 30, 2027 | |
Comment |
of which, affordable housing units | Value | 0.00 | 0.00 | 37000.00 |
Date | March 21, 2022 | May 17, 2024 | June 30, 2027 | |
Comment |
of which, percentage of women beneficiaries | Value | 0.00 | 0.00 | 0.00 |
Date | ||||
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Housing Market Information System (HMIS) developed, approved, and operational | Value | No | Yes | Yes |
Date | March 21, 2022 | May 17, 2024 | June 30, 2027 | |
Comment |
Program Management Information System (PMIS) developed, approved, and operational | Value | No | Yes | Yes |
Date | March 21, 2022 | May 17, 2024 | June 30, 2027 | |
Comment |
Beneficiary Management Information System (BMIS) developed, approved, and operational | Value | No | No | Yes |
Date | December 1, 2023 | May 17, 2024 | June 30, 2027 | |
Comment |
Rules, regulations, and procedures for APHS and JV schemes revised, approved and applied | Value | 0.00 | 0.00 | 4.00 |
Date | March 21, 2022 | May 17, 2024 | June 30, 2027 | |
Comment |
Housing Policy, Strategy and Programs formulated in a participatory manner with effective stakeholder consultation and citizen engagement | Value | 0.00 | 0.00 | 100.00 |
Date | May 17, 2024 | May 17, 2024 | June 30, 2027 | |
Comment |
Location and infrastructure investment criteria and procedures developed, approved, and applied | Value | 0.00 | 1.00 | 3.00 |
Date | March 21, 2022 | May 17, 2024 | June 30, 2027 | |
Comment |
Housing scheme applications processed per revised criteria and procedures | Value | 0.00 | 0.00 | 30.00 |
Date | March 21, 2022 | May 17, 2024 | June 30, 2027 | |
Comment |