Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 400.00 |
P173671
Active
Jie Li , Evi Hermirasari
Republic of Indonesia
October 13, 2020
(as of board presentation)
December 19, 2022
April 12, 2023
US$ 400.00 million
Ministry of Home Affairs,Ministry of National Development Planning / Bappenas,Ministry of Public Works and Housing
2023
US$ 400.00 million
N/A
March 25, 2024
January 31, 2028
Yes
BANK APPROVED
Financier | Commitments |
---|---|
International Bank for Reconstruction and Development | 400.00 |
Product Line | IBRD/IDA |
---|---|
IBRD Commitment | 400.00 |
IDA Commitment | N/A |
IBRD + IDA Commitment | 400.00 |
Lending Instrument | |
---|---|
Grant Amount | N/A |
Total Project Cost** | 400.00 |
Period | Financier | Transaction Type | Amount (US$) |
---|---|---|---|
Dec 19, 2022 | IBRD-94590 | Loan Commitment | 400,000,000.00 |
Feb 15, 2024 | IBRD-94590 | Int Charges | 9,696.96 |
Feb 28, 2024 | IBRD-94590 | Loan Disb | 1,414,000.00 |
Jun 21, 2024 | IBRD-94590 | Loan Disb | 1,125,000.00 |
Oct 27, 2023 | IBRD-94590 | Loan Disb | 500,000.00 |
Aug 15, 2024 | IBRD-94590 | Int Charges | 494,591.25 |
Aug 15, 2024 | IBRD-94590 | Int Charges | 41.72 |
Aug 15, 2024 | IBRD-94590 | Int Charges | 58,570.85 |
Aug 27, 2024 | IBRD-94590 | Loan Disb | 2,298,000.00 |
Feb 15, 2024 | IBRD-94590 | Int Charges | 503,393.03 |
Jun 9, 2023 | IBRD-94590 | Fee Charges | 1,000,000.00 |
Aug 15, 2023 | IBRD-94590 | Int Charges | 221,917.81 |
Name | Review | Date |
---|---|---|
Progress towards achievement of PDO | Moderately Satisfactory | 2024-09-30 |
Procurement | Moderately Satisfactory | 2024-09-30 |
Financial Management | Moderately Satisfactory | 2024-09-30 |
Monitoring and Evaluation | Moderately Satisfactory | 2024-09-30 |
Overall Implementation Progress (IP) | Moderately Satisfactory | 2024-09-30 |
Project Management | Moderately Satisfactory | 2024-09-30 |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Target population benefitting from integrated urban flood resilience measures under the project | Value | 0.00 | 0.00 | 2450000.00 |
Date | September 30, 2022 | March 3, 2023 | October 31, 2027 | |
Comment |
City-level interagency urban flood resilience task forces established and functional | Value | 0.00 | 0.00 | 5.00 |
Date | September 30, 2022 | March 3, 2023 | October 31, 2027 | |
Comment |
National urban flood resilience program established with procedures adopted for investment financing, institutional strengthening, and knowledge exchange | Value | No | No | Yes |
Date | September 30, 2022 | March 3, 2023 | October 31, 2027 | |
Comment |
Regulations and/or policies on integrated urban flood resilience adopted by city governments | Value | 0.00 | 0.00 | 10.00 |
Date | September 30, 2022 | March 3, 2023 | October 31, 2027 | |
Comment |
INDICATOR | BASELINE | CURRENT | TARGET |
---|
Cities with updated flood risk models and mapping that address urbanization and climate change effects | Value | 0.00 | 0.00 | 6.00 |
Date | September 30, 2022 | March 3, 2023 | October 31, 2027 | |
Comment |
Riverbank or drainage upgrades or improvements | Value | 0.00 | 0.00 | 40.00 |
Date | September 30, 2022 | March 3, 2023 | December 31, 2027 | |
Comment |
People trained on relevant flood risk management topics | Value | 0.00 | 0.00 | 500.00 |
Date | September 30, 2022 | March 3, 2023 | October 31, 2027 | |
Comment |
Cities with multi-year urban flood resilience action plans developed with integrated measures and climate risk considerations | Value | 0.00 | 0.00 | 6.00 |
Date | September 30, 2022 | March 3, 2023 | October 31, 2027 | |
Comment |
Subproject activities with green infrastructure and water-sensitive urban design measures | Value | 0.00 | 0.00 | 15.00 |
Date | September 30, 2022 | March 3, 2023 | October 31, 2027 | |
Comment |
Women's representation in decision-making positions on city-level urban flood resilience task forces | Value | 0.00 | 0.00 | 35.00 |
Date | September 30, 2022 | March 3, 2023 | October 31, 2027 | |
Comment |
Cities with an enhanced and functioning flood early warning system | Value | 0.00 | 0.00 | 5.00 |
Date | September 30, 2022 | March 3, 2023 | October 31, 2027 | |
Comment |
Women beneficiaries who report that they have increased knowledge to make decisions on urban flooding as a result of targeted training and preparedness activities | Value | 0.00 | 0.00 | 75.00 |
Date | September 30, 2022 | March 3, 2023 | October 31, 2027 | |
Comment |
Completed subprojects with operations and maintenance plans prepared and costs included in annual budgets | Value | 0.00 | 0.00 | 95.00 |
Date | September 30, 2022 | March 3, 2023 | October 31, 2027 | |
Comment |
Number of cities that have accessed technical support from the national digital knowledge platform | Value | 0.00 | 0.00 | 15.00 |
Date | September 30, 2022 | March 3, 2023 | October 31, 2027 | |
Comment |
Number of cities that have adopted the standard operating procedures of the national program | Value | 0.00 | 0.00 | 6.00 |
Date | September 30, 2022 | March 3, 2023 | October 31, 2027 | |
Comment |
Beneficiaries who report that project investments reflect their needs (disaggregated by gender) | Value | 0.00 | 0.00 | 70.00 |
Date | September 30, 2022 | March 3, 2023 | October 31, 2027 | |
Comment |